1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1131632 MGR.NO. 052 PAGE 001 CONT 6254 SEC 13 JOB 001 RES ENGR HORST, MARTIN PROJ SUP - 625413001 HWY SH0358 1701 S.P.I.D. CORPUS CHRI CNTY NUECES DIST 16 CONTRACT PRICE $ 93,666.82 REPORT DATE 04/25/2014 13.42.32 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 21,2013 TO JUL 30,2013 EST NO 008 & FINAL THE EB FOUNDATION, INC. 14997 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JAN 21, 2013 TIME COMPUTED FROM JAN 21, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 191 161 161 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 13 1 1 TOTAL DAYS ALLOWED = 191 2 1 DATE WORK COMPLETED 07/30/13 3 1 DAYS CHARGED TO DATE = 190 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 WORK COMPLETED AND ACCEPTED 0 ----- ----- ----- 191 190 1 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1131632 MGR.NO. 052 PAGE 001 CONT 6254 SEC 13 JOB 001 RES ENGR HORST, MARTIN PROJ SUP - 625413001 HWY SH0358 1701 S.P.I.D. CORPUS CHRI CNTY NUECES DIST 16 CONTRACT PRICE $ 93,666.82 REPORT DATE 04/25/2014 13.42.33 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 21,2013 TO JUL 30,2013 EST NO 008 & FINAL THE EB FOUNDATION, INC. 14997 DIST. 16 COUNTY NUECES CONTROL 6254-13-001 PROJECT SUP - 625413001 HIGHWAY SH0358 0LIMITS- VARIOUS . 0TYPE OF WORK- PALM TREE AND OLEANDER TRIMMING 0 0005 PREPARED BY ORLANDO J CARRILLO 0 0055 PALM TREE & OLEANDER TRIMMING NET LENGTH 0.999 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 7205 TREE TRIMMING EA 1,846.000 1,852.000 35.770 66,246.04 0065 7205 PRUNING TREES & SHRUBS - SITE 1 CYC 2,500.000 2,536.000 10.410 26,399.76 0070 0752 TREE REMOVAL (4"-12" DIA) EA 10.000 38.000 135.000 5,130.00 0075 0752 SMALL TREE REMOVAL-4" OR LESS IN DIA EA 10.000 0.000 26.040 .00 0 SUBTOTAL BID ITEMS $ 97,775.80 0 TOTAL AMOUNT WORK DONE PALM TREE & OLEANDER TRIMMING $ 97,775.80 0 TOTAL AMOUNT WORK DONE CONTROL 6254-13-001 $ 97,775.80 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1131632 MGR.NO. 052 PAGE 001 CONT 6254 SEC 13 JOB 001 RES ENGR HORST, MARTIN PROJ SUP - 625413001 HWY SH0358 1701 S.P.I.D. CORPUS CHRI CNTY NUECES DIST 16 CONTRACT PRICE $ 93,666.82 REPORT DATE 04/25/2014 13.42.33 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 21,2013 TO JUL 30,2013 EST NO 008 & FINAL THE EB FOUNDATION, INC. 14997 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN JAN 21, 2013 WORKING DAYS USED 190 PERCENT COMPLETE 100.00 PERCENT TIME USED 99.40 DATE COMPLETED JUL 30 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6254-13-001 SUP - 625413001 16 SH0358 NUECES - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0752 TREE REMOVAL (4"-12" DIA) EA 10.000 38.000 135.000 5,130.00 7205 TREE TRIMMING EA 1,846.000 1,852.000 35.770 66,246.04 7205 PRUNING TREES & SHRUBS - SITE 1 CYC 2,500.000 2,536.000 10.410 26,399.76 0 SUBTOTAL BID ITEMS $ 97,775.80 0 CONTRACT TOTAL ALL ITEMS $ 97,775.80 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1131632 MGR.NO. 052 PAGE 001 CONT 6254 SEC 13 JOB 001 RES ENGR HORST, MARTIN PROJ SUP - 625413001 HWY SH0358 1701 S.P.I.D. CORPUS CHRI CNTY NUECES DIST 16 CONTRACT PRICE $ 93,666.82 REPORT DATE 04/25/2014 13.42.33 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 21,2013 TO JUL 30,2013 EST NO 008 & FINAL THE EB FOUNDATION, INC. 14997 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 178 SUP - 625413001 6254-13-001 97,775.80 .00 97,775.80 .00 .00 97,775.80 97,775.80 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 97,775.80 .00 97,775.80 .00 .00 97,775.80 97,775.80 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1131632 MGR.NO. 052 PAGE 001 CONT 6254 SEC 13 JOB 001 RES ENGR HORST, MARTIN PROJ SUP - 625413001 HWY SH0358 1701 S.P.I.D. CORPUS CHRI CNTY NUECES DIST 16 CONTRACT PRICE $ 93,666.82 REPORT DATE 04/25/2014 13.42.33 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 21,2013 TO JUL 30,2013 EST NO 008 & FINAL THE EB FOUNDATION, INC. 14997 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6254-13-001 SUP - 625413001 16 SH0358 NUECES -LIMITS - VARIOUS . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 97,775.80