1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5121604 MGR.NO. 058 PAGE 001 CONT 6235 SEC 56 JOB 001 RES ENGR REITMANN, BILL PROJ BPM - 623556001 HWY FM1945 11571 US 181 SINTON CNTY SAN PATRICIO DIST 16 CONTRACT PRICE $ 15,972.06 REPORT DATE 03/04/2013 07.43.16 CONTRACTOR ADK ENVIRONMENTAL, INC. 12462 EST PERIOD JUN 18,2012 TO JUL 10,2012 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 25, 2012 TIME COMPUTED FROM JUN 18, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 18 13 6 7 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 12 1 1 SUNDAY TOTAL DAYS ALLOWED = 18 2 1 TOO WET DATE WORK COMPLETED 07/10/12 3 1 TOO WET DAYS CHARGED TO DATE = 7 4 1 TOO WET ASSESSED LIQ DAMAGES = 0 5 1 TOO WET LIQ DAMAGE RATE $ 570 6 1 TOO WET 7 1 SATURDAY LIQUIDATED DAMAGES 8 1 SUNDAY 0 DAYS AT $ 570 PER DAY 9 1 TOTAL = $ .00 10 1 WORK COMPLETED AND ACCEPTED CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 23 7 16 1 SATURDAY 2 SUNDAY 0 HOLIDAY 5 TOO WET 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5121604 MGR.NO. 058 PAGE 001 CONT 6235 SEC 56 JOB 001 RES ENGR REITMANN, BILL PROJ BPM - 623556001 HWY FM1945 11571 US 181 SINTON CNTY SAN PATRICIO DIST 16 CONTRACT PRICE $ 15,972.06 REPORT DATE 03/04/2013 07.43.16 CONTRACTOR ADK ENVIRONMENTAL, INC. 12462 EST PERIOD JUN 18,2012 TO JUL 10,2012 EST NO 003 & FINAL DIST. 16 COUNTY SAN PATRICIO CONTROL 6235-56-001 PROJECT BPM - 623556001 HIGHWAY FM1945 0LIMITS- FM1945 AT CHILTIPIN CREEK TRIBUTARY BRDG . 0TYPE OF WORK- BRIDGE STRUCTURAL REPAIR 0 0005 PREPARED BY RUBEN GARCIA 0 0055 BRIDGE STRUCTURAL REPAIR NET LENGTH 0.999 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0132 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 3.000 3.000 693.120 2,079.36 0065 0420 CL S CONC (BENT) CY 1.778 1.778 1,939.810 3,448.98 0070 0429 CNC STR REP (VERTICAL OR OVERHEAD) SF 2.000 5.300 858.720 4,551.22 0075 0432 RIPRAP (CONC)(5 IN) CY 9.560 9.560 752.490 7,193.80 0080 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 984.380 984.38 0085 0500 MOBILIZATION LS 1.000 1.000 548.100 548.10 0 SUBTOTAL BID ITEMS $ 18,805.84 0 TOTAL AMOUNT WORK DONE BRIDGE STRUCTURAL REPAIR $ 18,805.84 0 TOTAL AMOUNT WORK DONE CONTROL 6235-56-001 $ 18,805.84 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5121604 MGR.NO. 058 PAGE 001 CONT 6235 SEC 56 JOB 001 RES ENGR REITMANN, BILL PROJ BPM - 623556001 HWY FM1945 11571 US 181 SINTON CNTY SAN PATRICIO DIST 16 CONTRACT PRICE $ 15,972.06 REPORT DATE 03/04/2013 07.43.17 CONTRACTOR ADK ENVIRONMENTAL, INC. 12462 EST PERIOD JUN 18,2012 TO JUL 10,2012 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - FM1945 AT CHILTIPIN CREEK TRIBUTARY BRDG 0 . DATE WORK BEGAN JUN 25, 2012 WORKING DAYS USED 7 PERCENT COMPLETE 100.00 PERCENT TIME USED 38.80 DATE COMPLETED JUL 10 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6235-56-001 BPM - 623556001 16 FM1945 SAN PATRICIO - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0132 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 3.000 3.000 693.120 2,079.36 0420 CL S CONC (BENT) CY 1.778 1.778 1,939.810 3,448.98 0429 CNC STR REP (VERTICAL OR OVERHEAD) SF 2.000 5.300 858.720 4,551.22 0432 RIPRAP (CONC)(5 IN) CY 9.560 9.560 752.490 7,193.80 0500 MOBILIZATION LS 1.000 1.000 548.100 548.10 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 984.380 984.38 0 SUBTOTAL BID ITEMS $ 18,805.84 0 CONTRACT TOTAL ALL ITEMS $ 18,805.84 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5121604 MGR.NO. 058 PAGE 001 CONT 6235 SEC 56 JOB 001 RES ENGR REITMANN, BILL PROJ BPM - 623556001 HWY FM1945 11571 US 181 SINTON CNTY SAN PATRICIO DIST 16 CONTRACT PRICE $ 15,972.06 REPORT DATE 03/04/2013 07.43.17 CONTRACTOR ADK ENVIRONMENTAL, INC. 12462 EST PERIOD JUN 18,2012 TO JUL 10,2012 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 205 BPM - 623556001 6235-56-001 18,805.84 .00 18,805.84 .00 .00 18,805.84 18,805.84 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 18,805.84 .00 18,805.84 .00 .00 18,805.84 18,805.84 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5121604 MGR.NO. 058 PAGE 001 CONT 6235 SEC 56 JOB 001 RES ENGR REITMANN, BILL PROJ BPM - 623556001 HWY FM1945 11571 US 181 SINTON CNTY SAN PATRICIO DIST 16 CONTRACT PRICE $ 15,972.06 REPORT DATE 03/04/2013 07.43.17 CONTRACTOR ADK ENVIRONMENTAL, INC. 12462 EST PERIOD JUN 18,2012 TO JUL 10,2012 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6235-56-001 BPM - 623556001 16 FM1945 SAN PATRICIO -LIMITS - FM1945 AT CHILTIPIN CREEK TRIBUTARY BRDG . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 18,805.84