1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 12101602 MGR.NO. 058 PAGE 001 CONT 6179 SEC 05 JOB 001 RES ENGR REITMANN,BILL PROJ RMC - 617905001 HWY FM2046 PO BOX 1367 SINTON CNTY SAN PATRICIO DIST 16 CONTRACT PRICE $ 218,546.38 REPORT DATE 02/20/2013 13.27.27 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD MAR 16,2011 TO MAR 28,2011 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAR 21, 2011 TIME COMPUTED FROM MAR 16, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 15 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAR 11 TOTAL DAYS ALLOWED = 15 DATE WORK COMPLETED 03/28/11 DAYS CHARGED TO DATE = 8 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 500 0 LIQUIDATED DAMAGES 0 DAYS AT $ 500 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - 16 1 TIME BEGAN ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 SATURDAY 20 1 SUNDAY 21 1 WORK BEGAN 22 1 23 1 24 1 25 1 26 1 SATURDAY 27 1 SUNDAY 28 1 WORK COMPLETED AND ACCEPTED - ----- ----- ----- 13 8 5 2 SATURDAY 2 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 12101602 MGR.NO. 058 PAGE 001 CONT 6179 SEC 05 JOB 001 RES ENGR REITMANN,BILL PROJ RMC - 617905001 HWY FM2046 PO BOX 1367 SINTON CNTY SAN PATRICIO DIST 16 CONTRACT PRICE $ 218,546.38 REPORT DATE 02/20/2013 13.27.27 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD MAR 16,2011 TO MAR 28,2011 EST NO 002 & FINAL DIST. 16 COUNTY SAN PATRICIO CONTROL 6179-05-001 PROJECT RMC - 617905001 HIGHWAY FM2046 0LIMITS- VARIOUS . 0TYPE OF WORK- BLADE LEVEL UP 0 0005 PREPARED BY ORLANDO CARRILLO 0 0055 BLADE LEVEL UP NET LENGTH 4.060 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0500 MOBILIZATION LS 1.000 1.000 14,276.000 14,276.00 0065 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 1,461.000 1,461.00 0070 0662 WK ZN PAV MRK SHT TERM RMV(Y)(4") LF 3,755.000 0.000 1.000 .00 0070 0662 ADJ EST QUANTITY TO DATE 0.000 0071 0662*WK ZN PAV MRK SHT TERM (TAB) TY Y EA 1,187.000 1,187.000 1.000 1,187.00 0075 0668 PREFAB PAV MRK TY C (W) (24") (SLD) LF 44.000 44.000 12.000 528.00 0080 0672 REFL PAV MRKR TY II-A-A EA 320.000 333.000 3.250 1,082.25 0080 0672 ADJ EST QUANTITY TO DATE 333.000 0085 3035 BLADE LEVEL-UP (LIMESTONE ROCK ASPHALT) CY 2,157.000 2,931.300 83.060 243,473.78 0085 3035 ADJ EST QUANTITY TO DATE 2,931.300 0090 8251 RE PM W/RET REQ TY I(W)4"(SLD)(090MIL) LF 42,356.000 41,490.000 .350 14,521.50 0090 8251 ADJ EST QUANTITY TO DATE 41,490.000 0095 8251 RE PM W/RET REQ TY I(Y)4"(BRK)(090MIL) LF 5,290.000 5,660.000 .360 2,037.60 0095 8251 ADJ EST QUANTITY TO DATE 5,660.000 0100 8251 RE PM W/RET REQ TY I(Y)4"(SLD)(090MIL) LF 4,436.000 5,298.000 .360 1,907.28 0100 8251 ADJ EST QUANTITY TO DATE 5,298.000 0 SUBTOTAL BID ITEMS $ 280,474.41 0 TOTAL AMOUNT WORK DONE BLADE LEVEL UP $ 280,474.41 1 TOTAL AMOUNT WORK DONE CONTROL 6179-05-001 $ 280,474.41 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 12101602 MGR.NO. 058 PAGE 001 CONT 6179 SEC 05 JOB 001 RES ENGR REITMANN,BILL PROJ RMC - 617905001 HWY FM2046 PO BOX 1367 SINTON CNTY SAN PATRICIO DIST 16 CONTRACT PRICE $ 218,546.38 REPORT DATE 02/20/2013 13.27.27 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD MAR 16,2011 TO MAR 28,2011 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN MAR 21, 2011 WORKING DAYS USED 8 PERCENT COMPLETE 100.00 PERCENT TIME USED 53.30 DATE COMPLETED MAR 28 2011 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6179-05-001 RMC - 617905001 16 FM2046 SAN PATRICIO - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0500 MOBILIZATION LS 1.000 1.000 14,276.000 14,276.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 1,461.000 1,461.00 0668 PREFAB PAV MRK TY C (W) (24") (SLD) LF 44.000 44.000 12.000 528.00 0672 REFL PAV MRKR TY II-A-A EA 320.000 333.000 3.250 1,082.25 0672 ADJ EST QUANTITY TO DATE 333.000 3035 BLADE LEVEL-UP (LIMESTONE ROCK ASPHALT) CY 2,157.000 2,931.300 83.060 243,473.78 3035 ADJ EST QUANTITY TO DATE 2,931.300 8251 RE PM W/RET REQ TY I(W)4"(SLD)(090MIL) LF 42,356.000 41,490.000 .350 14,521.50 8251 ADJ EST QUANTITY TO DATE 41,490.000 8251 RE PM W/RET REQ TY I(Y)4"(BRK)(090MIL) LF 5,290.000 5,660.000 .360 2,037.60 8251 ADJ EST QUANTITY TO DATE 5,660.000 8251 RE PM W/RET REQ TY I(Y)4"(SLD)(090MIL) LF 4,436.000 5,298.000 .360 1,907.28 8251* ADJ EST QUANTITY TO DATE 5,298.000 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00662* WK ZN PAV MRK SHT TERM (TAB) TY Y EA 1,187.000 1,187.000 1.000 1,187.00 1 SUBTOTAL BID ITEMS $ 280,474.41 0 CONTRACT TOTAL ALL ITEMS $ 280,474.41 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 12101602 MGR.NO. 058 PAGE 001 CONT 6179 SEC 05 JOB 001 RES ENGR REITMANN,BILL PROJ RMC - 617905001 HWY FM2046 PO BOX 1367 SINTON CNTY SAN PATRICIO DIST 16 CONTRACT PRICE $ 218,546.38 REPORT DATE 02/20/2013 13.27.27 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD MAR 16,2011 TO MAR 28,2011 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 205 RMC - 617905001 6179-05-001 280,474.41 .00 280,474.41 .00 .00 280,474.41 280,474.41 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 280,474.41 .00 280,474.41 .00 .00 280,474.41 280,474.41 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 12101602 MGR.NO. 058 PAGE 001 CONT 6179 SEC 05 JOB 001 RES ENGR REITMANN,BILL PROJ RMC - 617905001 HWY FM2046 PO BOX 1367 SINTON CNTY SAN PATRICIO DIST 16 CONTRACT PRICE $ 218,546.38 REPORT DATE 02/20/2013 13.27.27 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD MAR 16,2011 TO MAR 28,2011 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6179-05-001 RMC - 617905001 16 FM2046 SAN PATRICIO -LIMITS - VARIOUS . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 280,474.41