1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4084010 MGR.NO. 052 PAGE 001 CONT 6175 SEC 12 JOB 001 RES ENGR HORST, MARTIN PROJ RMC - 617512001 HWY FM0665 P O BOX 9907 CORPUS CHRIS CNTY NUECES DIST 16 CONTRACT PRICE $ 426,007.07 REPORT DATE 06/06/2008 08.46.37 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD MAY 19,2008 TO MAY 23,2008 EST NO 001 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 19, 2008 TIME COMPUTED FROM MAY 22, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 27 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAY 08 TOTAL DAYS ALLOWED = 27 DATE WORK COMPLETED 05/23/08 DAYS CHARGED TO DATE = 3 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 500 0 LIQUIDATED DAMAGES 0 DAYS AT $ 500 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER 0 19 1 WORK STARTED/NO TIME CHARGED 20 1 21 1 22 1 TIME CHARGES STARTED 23 1 WORK COMPLETED AND ACCEPTED - - - ----- ----- ----- 5 3 2 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK STARTED/NO TIME CHARGED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4084010 MGR.NO. 052 PAGE 001 CONT 6175 SEC 12 JOB 001 RES ENGR HORST, MARTIN PROJ RMC - 617512001 HWY FM0665 P O BOX 9907 CORPUS CHRIS CNTY NUECES DIST 16 CONTRACT PRICE $ 426,007.07 REPORT DATE 06/06/2008 08.46.37 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD MAY 19,2008 TO MAY 23,2008 EST NO 001 DIST. 16 COUNTY NUECES CONTROL 6175-12-001 PROJECT RMC - 617512001 HIGHWAY FM0665 0LIMITS- 0.25 MI W OF FM 892 0.25 MI E OF FM 1694 0TYPE OF WORK- BLADE LEVEL UP & PAVEMENT MARKINGS 0 0005 PREPARED BY KRISTI GILBERTSON 0 0055 BLADE LEVEL UP & PAVEMENT MARKINGS NET LENGTH 4.300 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0672 REFL PAV MRKR TY I-A EA 550.000 0.000 3.000 .00 0060 0672 ADJ EST QUANTITY TO DATE 0.000 0065 0672 REFL PAV MRKR TY II-A-A EA 372.000 0.000 3.000 .00 0065 0672 ADJ EST QUANTITY TO DATE 0.000 0070 3035 BLADE LEVEL-UP (LIMESTONE ROCK ASPHALT) CY 4,685.200 5,812.000 87.240 507,038.88 0070 3035 ADJ EST QUANTITY TO DATE 5,812.000 0075 6110 REF PAV MRK TY I (W)(4")(SLD)(90 MIL) LF 44,954.000 0.000 .230 .00 0075 6110 ADJ EST QUANTITY TO DATE 55,763.000 0080 6110 REF PAV MRK TY I (W)(24")(SLD)(90 MIL) LF 80.000 0.000 6.000 .00 0080 6110 ADJ EST QUANTITY TO DATE 99.000 0085 6110 REF PAV MRK TY I (Y)(4")(BRK)(90 MIL) LF 4,610.000 3,000.000 .250 750.00 0085 6110 ADJ EST QUANTITY TO DATE 5,718.000 0090 6110 REF PAV MRK TY I (Y)(4")(SLD)(90 MIL) LF 11,010.000 11,010.000 .230 2,532.30 0090 6110 ADJ EST QUANTITY TO DATE 13,657.000 0 SUBTOTAL BID ITEMS $ 510,321.18 0 TOTAL AMOUNT WORK DONE BLADE LEVEL UP & PAVEMENT MARKINGS $ 510,321.18 0 TOTAL AMOUNT WORK DONE CONTROL 6175-12-001 $ 510,321.18 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4084010 MGR.NO. 052 PAGE 001 CONT 6175 SEC 12 JOB 001 RES ENGR HORST, MARTIN PROJ RMC - 617512001 HWY FM0665 P O BOX 9907 CORPUS CHRIS CNTY NUECES DIST 16 CONTRACT PRICE $ 426,007.07 REPORT DATE 06/06/2008 08.46.37 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD MAY 19,2008 TO MAY 23,2008 EST NO 001 0*********************************************************************************************************************************** -LIMITS - 0.25 MI W OF FM 892 0 0.25 MI E OF FM 1694 DATE WORK BEGAN MAY 19, 2008 WORKING DAYS USED 3 PERCENT COMPLETE 100.00 PERCENT TIME USED 11.10 DATE COMPLETED MAY 23 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6175-12-001 RMC - 617512001 16 FM0665 NUECES - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -3035 BLADE LEVEL-UP (LIMESTONE ROCK ASPHALT) CY 4,685.200 5,812.000 87.240 507,038.88 3035 ADJ EST QUANTITY TO DATE 5,812.000 6110 REF PAV MRK TY I (Y)(4")(BRK)(90 MIL) LF 4,610.000 3,000.000 .250 750.00 6110 ADJ EST QUANTITY TO DATE 5,718.000 6110 REF PAV MRK TY I (Y)(4")(SLD)(90 MIL) LF 11,010.000 11,010.000 .230 2,532.30 6110 ADJ EST QUANTITY TO DATE 13,657.000 0 SUBTOTAL BID ITEMS $ 510,321.18 0 CONTRACT TOTAL ALL ITEMS $ 510,321.18 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4084010 MGR.NO. 052 PAGE 001 CONT 6175 SEC 12 JOB 001 RES ENGR HORST, MARTIN PROJ RMC - 617512001 HWY FM0665 P O BOX 9907 CORPUS CHRIS CNTY NUECES DIST 16 CONTRACT PRICE $ 426,007.07 REPORT DATE 06/06/2008 08.46.37 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD MAY 19,2008 TO MAY 23,2008 EST NO 001 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 178 RMC - 617512001 6175-12-001 510,321.18 .00 510,321.18 .00 .00 510,321.18 .00 510,321.18 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 510,321.18 .00 510,321.18 .00 .00 510,321.18 .00 510,321.18 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4084010 MGR.NO. 052 PAGE 001 CONT 6175 SEC 12 JOB 001 RES ENGR HORST, MARTIN PROJ RMC - 617512001 HWY FM0665 P O BOX 9907 CORPUS CHRIS CNTY NUECES DIST 16 CONTRACT PRICE $ 426,007.07 REPORT DATE 06/06/2008 08.46.37 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD MAY 19,2008 TO MAY 23,2008 EST NO 001 ********************************************************************************************************** - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6175-12-001 RMC - 617512001 16 FM0665 NUECES -LIMITS - 0.25 MI W OF FM 892 0.25 MI E OF FM 1694 ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 03035 BLADE LEVEL-UP (LIMESTONE CY 4,685.200 5,812.000 87.240 507,038.88 ROCK ASPHALT) 6110 REF PAV MRK TY I LF 4,610.000 3,000.000 0.250 750.00 (Y)(4")(BRK)(90 MIL) 6110 REF PAV MRK TY I LF 11,010.000 11,010.000 0.230 2,532.30 (Y)(4")(SLD)(90 MIL) --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 510,321.18 0 TOTAL AMOUNT WORK DONE TO DATE - $ 510,321.18