1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 3081602 MGR.NO. 050 PAGE 001 CONT 6174 SEC 92 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 617492001 HWY FM0892 P O BOX 889 ALICE CNTY NUECES DIST 16 CONTRACT PRICE $ 298,937.67 REPORT DATE 06/06/2008 16.51.02 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD JUN 01,2008 TO JUN 02,2008 EST NO 002 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 22, 2008 TIME COMPUTED FROM MAY 23, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 22 10 5 5 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUN 08 1 1 SUNDAY TOTAL DAYS ALLOWED = 22 2 1 WORK COMPLETED AND ACCEPTED DATE WORK COMPLETED 06/02/08 DAYS CHARGED TO DATE = 5 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 400 0 LIQUIDATED DAMAGES 0 DAYS AT $ 400 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 12 5 7 0 SATURDAY 1 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 3081602 MGR.NO. 050 PAGE 001 CONT 6174 SEC 92 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 617492001 HWY FM0892 P O BOX 889 ALICE CNTY NUECES DIST 16 CONTRACT PRICE $ 298,937.67 REPORT DATE 06/06/2008 16.51.02 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD JUN 01,2008 TO JUN 02,2008 EST NO 002 DIST. 16 COUNTY NUECES CONTROL 6174-92-001 PROJECT RMC - 617492001 HIGHWAY FM0892 0LIMITS- FM 665 FM 70 0TYPE OF WORK- BLADE LEVEL UP & PAVEMENT MARKINGS 0 0005 PREPARED BY KRISTI GILBERTSON 0 0055 BLADE LEVEL UP & PAVEMENT MARKINGS NET LENGTH 6.712 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 2,618.000 2,618.000 1.000 2,618.00 0065 0672 REFL PAV MRKR TY II-A-A EA 607.000 277.000 3.250 900.25 0070 3035 BLADE LEVEL-UP (LIMESTONE ROCK ASPHALT) CY 3,018.000 3,018.000 89.630 270,503.34 0075 6055 IN-LANE OR TRANSVERSE RUMBLE STRIP LF 160.000 60.000 12.000 720.00 0080 6110 REF PAV MRK TY I (W)(4")(SLD)(100 MIL) LF 70,876.000 32,636.000 .230 7,506.28 0085 6110 REF PAV MRK TY I (Y)(4")(BRK)(100 MIL) LF 5,680.000 3,660.000 .250 915.00 0090 6110 REF PAV MRK TY I (Y)(4")(SLD)(100 MIL) LF 18,270.000 7,523.000 .230 1,730.29 0 SUBTOTAL BID ITEMS $ 284,893.16 0 TOTAL AMOUNT WORK DONE BLADE LEVEL UP & PAVEMENT MARKINGS $ 284,893.16 0 TOTAL AMOUNT WORK DONE CONTROL 6174-92-001 $ 284,893.16 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 3081602 MGR.NO. 050 PAGE 001 CONT 6174 SEC 92 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 617492001 HWY FM0892 P O BOX 889 ALICE CNTY NUECES DIST 16 CONTRACT PRICE $ 298,937.67 REPORT DATE 06/06/2008 16.51.02 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD JUN 01,2008 TO JUN 02,2008 EST NO 002 0*********************************************************************************************************************************** -LIMITS - FM 665 0 FM 70 DATE WORK BEGAN MAY 22, 2008 WORKING DAYS USED 5 PERCENT COMPLETE 100.00 PERCENT TIME USED 22.70 DATE COMPLETED JUN 2 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6174-92-001 RMC - 617492001 16 FM0892 NUECES - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 2,618.000 2,618.000 1.000 2,618.00 0672 REFL PAV MRKR TY II-A-A EA 607.000 277.000 3.250 900.25 3035 BLADE LEVEL-UP (LIMESTONE ROCK ASPHALT) CY 3,018.000 3,018.000 89.630 270,503.34 6055 IN-LANE OR TRANSVERSE RUMBLE STRIP LF 160.000 60.000 12.000 720.00 6110 REF PAV MRK TY I (W)(4")(SLD)(100 MIL) LF 70,876.000 32,636.000 .230 7,506.28 6110 REF PAV MRK TY I (Y)(4")(BRK)(100 MIL) LF 5,680.000 3,660.000 .250 915.00 6110 REF PAV MRK TY I (Y)(4")(SLD)(100 MIL) LF 18,270.000 7,523.000 .230 1,730.29 0 SUBTOTAL BID ITEMS $ 284,893.16 0 CONTRACT TOTAL ALL ITEMS $ 284,893.16 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 3081602 MGR.NO. 050 PAGE 001 CONT 6174 SEC 92 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 617492001 HWY FM0892 P O BOX 889 ALICE CNTY NUECES DIST 16 CONTRACT PRICE $ 298,937.67 REPORT DATE 06/06/2008 16.51.02 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD JUN 01,2008 TO JUN 02,2008 EST NO 002 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 178 RMC - 617492001 6174-92-001 284,893.16 .00 284,893.16 .00 .00 284,893.16 283,272.91 1,620.25 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 284,893.16 .00 284,893.16 .00 .00 284,893.16 283,272.91 1,620.25 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 3081602 MGR.NO. 050 PAGE 001 CONT 6174 SEC 92 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 617492001 HWY FM0892 P O BOX 889 ALICE CNTY NUECES DIST 16 CONTRACT PRICE $ 298,937.67 REPORT DATE 06/06/2008 16.51.02 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD JUN 01,2008 TO JUN 02,2008 EST NO 002 ********************************************************************************************************** - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6174-92-001 RMC - 617492001 16 FM0892 NUECES -LIMITS - FM 665 FM 70 ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 00672 REFL PAV MRKR TY II-A-A EA 607.000 277.000 3.250 900.25 6055 IN-LANE OR TRANSVERSE RUMBLE LF 160.000 60.000 12.000 720.00 STRIP --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 1,620.25 0 TOTAL AMOUNT WORK DONE TO DATE - $ 284,893.16