1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4084022 MGR.NO. 056 PAGE 001 CONT 6174 SEC 91 JOB 001 RES ENGR CONDRA, RALPH PROJ RMC - 617491001 HWY US0059 800 S 181 KARNES CITY CNTY BEE DIST 16 CONTRACT PRICE $ 815,914.12 REPORT DATE 07/15/2008 08.46.59 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD JUL 01,2008 TO JUL 02,2008 EST NO 002 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 09, 2008 TIME COMPUTED FROM JUN 12, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 39 22 12 10 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 08 1 1 TOTAL DAYS ALLOWED = 39 2 1 WORK COMPLETED & ACCEPTED DATE WORK COMPLETED 07/02/08 DAYS CHARGED TO DATE = 13 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 500 0 LIQUIDATED DAMAGES 0 DAYS AT $ 500 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 24 13 11 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED & ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4084022 MGR.NO. 056 PAGE 001 CONT 6174 SEC 91 JOB 001 RES ENGR CONDRA, RALPH PROJ RMC - 617491001 HWY US0059 800 S 181 KARNES CITY CNTY BEE DIST 16 CONTRACT PRICE $ 815,914.12 REPORT DATE 07/15/2008 08.47.00 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD JUL 01,2008 TO JUL 02,2008 EST NO 002 DIST. 16 COUNTY BEE CONTROL 6174-91-001 PROJECT RMC - 617491001 HIGHWAY US0059 0LIMITS- VARIOUS . 0TYPE OF WORK- BLADE LEVEL UP & PAVEMENT MARKINGS 0 0005 PREPARED BY KRISTI GILBERTSON 0 0055 BLADE LEVEL UP & PAVEMENT MARKINGS NET LENGTH 25.029 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0668 PREFAB PAV MRK TY C (W) (24") (SLD) LF 190.000 72.000 7.750 558.00 0060 0668 ADJ EST QUANTITY TO DATE 213.000 0065 0668 PREFAB PAV MRK TY C (W) (ARROW) EA 12.000 12.000 150.000 1,800.00 0065 0668 ADJ EST QUANTITY TO DATE 13.000 0070 0668 PREFAB PAV MRK TY C (W) (WORD) EA 2.000 2.000 225.000 450.00 0070 0668 ADJ EST QUANTITY TO DATE 3.000 0075 0668 PREFAB PAV MRK TY C (Y) (24") (SLD) LF 150.000 135.000 7.750 1,046.25 0075 0668 ADJ EST QUANTITY TO DATE 168.000 0080 0672 REFL PAV MRKR TY I-C EA 225.000 195.000 3.500 682.50 0080 0672 ADJ EST QUANTITY TO DATE 252.000 0085 0672 REFL PAV MRKR TY II-A-A EA 1,487.000 1,657.000 3.500 5,799.50 0085 0672 ADJ EST QUANTITY TO DATE 1,667.000 0090 3035 BLADE LEVEL-UP (LIMESTONE ROCK ASPHALT) CY 9,450.000 10,577.000 80.080 847,006.16 0090 3035 ADJ EST QUANTITY TO DATE 10,596.000 0095 6110 REF PAV MRK TY I (W)(4")(SLD)(100 MIL) LF 122,325.000 119,514.000 .240 28,683.36 0095 6110 ADJ EST QUANTITY TO DATE 137,167.000 0100 6110 REF PAV MRK TY I (Y)(4")(BRK)(100 MIL) LF 13,515.000 14,760.000 .260 3,837.60 0100 6110 ADJ EST QUANTITY TO DATE 15,155.000 0105 6110 REF PAV MRK TY I (W)(4")(BRK)(100 MIL) LF 2,560.000 2,550.000 .260 663.00 0105 6110 ADJ EST QUANTITY TO DATE 2,872.000 0110 6110 REF PAV MRK TY I 1 (W)(8")(SLD)(100 MIL) LF 550.000 479.000 .750 359.25 0110 6110 ADJ EST QUANTITY TO DATE 616.000 0115 6110 REF PAV MRK TY I (Y)(4")(SLD)(100 MIL) LF 59,713.000 66,138.000 .240 15,873.12 0115 6110 ADJ EST QUANTITY TO DATE 66,958.000 0 SUBTOTAL BID ITEMS $ 906,758.74 0 TOTAL AMOUNT WORK DONE BLADE LEVEL UP & PAVEMENT MARKINGS $ 906,758.74 0 TOTAL AMOUNT WORK DONE CONTROL 6174-91-001 $ 906,758.74 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4084022 MGR.NO. 056 PAGE 001 CONT 6174 SEC 91 JOB 001 RES ENGR CONDRA, RALPH PROJ RMC - 617491001 HWY US0059 800 S 181 KARNES CITY CNTY BEE DIST 16 CONTRACT PRICE $ 815,914.12 REPORT DATE 07/15/2008 08.47.00 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD JUL 01,2008 TO JUL 02,2008 EST NO 002 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN JUN 9 , 2008 WORKING DAYS USED 13 PERCENT COMPLETE 100.00 PERCENT TIME USED 33.30 DATE COMPLETED JUL 2 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6174-91-001 RMC - 617491001 16 US0059 BEE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0668 PREFAB PAV MRK TY C (W) (24") (SLD) LF 190.000 72.000 7.750 558.00 0668 ADJ EST QUANTITY TO DATE 213.000 0668 PREFAB PAV MRK TY C (W) (ARROW) EA 12.000 12.000 150.000 1,800.00 0668 ADJ EST QUANTITY TO DATE 13.000 0668 PREFAB PAV MRK TY C (W) (WORD) EA 2.000 2.000 225.000 450.00 0668 ADJ EST QUANTITY TO DATE 3.000 0668 PREFAB PAV MRK TY C (Y) (24") (SLD) LF 150.000 135.000 7.750 1,046.25 0668 ADJ EST QUANTITY TO DATE 168.000 0672 REFL PAV MRKR TY I-C EA 225.000 195.000 3.500 682.50 0672 ADJ EST QUANTITY TO DATE 252.000 0672 REFL PAV MRKR TY II-A-A EA 1,487.000 1,657.000 3.500 5,799.50 0672 ADJ EST QUANTITY TO DATE 1,667.000 3035 BLADE LEVEL-UP (LIMESTONE ROCK ASPHALT) CY 9,450.000 10,577.000 80.080 847,006.16 3035 ADJ EST QUANTITY TO DATE 10,596.000 6110 REF PAV MRK TY I (W)(4")(SLD)(100 MIL) LF 122,325.000 119,514.000 .240 28,683.36 6110 ADJ EST QUANTITY TO DATE 137,167.000 6110 REF PAV MRK TY I (Y)(4")(BRK)(100 MIL) LF 13,515.000 14,760.000 .260 3,837.60 6110 ADJ EST QUANTITY TO DATE 15,155.000 16110 REF PAV MRK TY I (W)(4")(BRK)(100 MIL) LF 2,560.000 2,550.000 .260 663.00 6110 ADJ EST QUANTITY TO DATE 2,872.000 6110 REF PAV MRK TY I (W)(8")(SLD)(100 MIL) LF 550.000 479.000 .750 359.25 6110 ADJ EST QUANTITY TO DATE 616.000 6110 REF PAV MRK TY I (Y)(4")(SLD)(100 MIL) LF 59,713.000 66,138.000 .240 15,873.12 6110 ADJ EST QUANTITY TO DATE 66,958.000 0 SUBTOTAL BID ITEMS $ 906,758.74 0 CONTRACT TOTAL ALL ITEMS $ 906,758.74 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4084022 MGR.NO. 056 PAGE 001 CONT 6174 SEC 91 JOB 001 RES ENGR CONDRA, RALPH PROJ RMC - 617491001 HWY US0059 800 S 181 KARNES CITY CNTY BEE DIST 16 CONTRACT PRICE $ 815,914.12 REPORT DATE 07/15/2008 08.47.00 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD JUL 01,2008 TO JUL 02,2008 EST NO 002 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 13 RMC - 617491001 6174-91-001 906,758.74 .00 906,758.74 .00 .00 906,758.74 887,833.64 18,925.10 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 906,758.74 .00 906,758.74 .00 .00 906,758.74 887,833.64 18,925.10 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4084022 MGR.NO. 056 PAGE 001 CONT 6174 SEC 91 JOB 001 RES ENGR CONDRA, RALPH PROJ RMC - 617491001 HWY US0059 800 S 181 KARNES CITY CNTY BEE DIST 16 CONTRACT PRICE $ 815,914.12 REPORT DATE 07/15/2008 08.47.00 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD JUL 01,2008 TO JUL 02,2008 EST NO 002 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6174-91-001 RMC - 617491001 16 US0059 BEE -LIMITS - VARIOUS . LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0668 PREFAB PAV MRK TY C (W) LF 190.000 60.000 7.750 465.00 (24") (SLD) 65 0668 PREFAB PAV MRK TY C (W) EA 12.000 12.000 150.000 1,800.00 (ARROW) 70 0668 PREFAB PAV MRK TY C (W) EA 2.000 2.000 225.000 450.00 (WORD) 75 0668 PREFAB PAV MRK TY C (Y) LF 150.000 135.000 7.750 1,046.25 (24") (SLD) 80 0672 REFL PAV MRKR TY I-C EA 225.000 195.000 3.500 682.50 85 0672 REFL PAV MRKR TY II-A-A EA 1,487.000 541.000 3.500 1,893.50 95 6110 REF PAV MRK TY I LF 122,325.000 20,690.000 0.240 4,965.60 (W)(4")(SLD)(100 MIL) 100 6110 REF PAV MRK TY I LF 13,515.000 4,440.000 0.260 1,154.40 (Y)(4")(BRK)(100 MIL) 105 6110 REF PAV MRK TY I LF 2,560.000 2,550.000 0.260 663.00 (W)(4")(BRK)(100 MIL) 110 6110 REF PAV MRK TY I LF 550.000 479.000 0.750 359.25 (W)(8")(SLD)(100 MIL) 115 6110 REF PAV MRK TY I LF 59,713.000 22,690.000 0.240 5,445.60 (Y)(4")(SLD)(100 MIL) --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 18,925.10 0 TOTAL AMOUNT WORK DONE TO DATE - $ 906,758.74