1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1084038 MGR.NO. 052 PAGE 001 CONT 6173 SEC 57 JOB 001 RES ENGR HORST, MARTIN PROJ RMC - 617357001 HWY US0077 P O BOX 9907 CORPUS CHRIS CNTY NUECES DIST 16 CONTRACT PRICE $ 322,360.10 REPORT DATE 11/06/2009 16.20.27 CONTRACTOR BENTEX, INC. 6904 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 016 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 14, 2008 TIME COMPUTED FROM JUL 10, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 634 448 448 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 09 1 1 TOTAL DAYS ALLOWED = 634 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 479 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 500 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 500 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 479 479 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1084038 MGR.NO. 052 PAGE 001 CONT 6173 SEC 57 JOB 001 RES ENGR HORST, MARTIN PROJ RMC - 617357001 HWY US0077 P O BOX 9907 CORPUS CHRIS CNTY NUECES DIST 16 CONTRACT PRICE $ 322,360.10 REPORT DATE 11/06/2009 16.20.27 CONTRACTOR BENTEX, INC. 6904 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 016 DIST. 16 COUNTY NUECES CONTROL 6173-57-001 PROJECT RMC - 617357001 HIGHWAY US0077 0LIMITS- VARIOUS . 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 PREPARED BY KRISTI GILBERTSON 0 0055 MOWING HIGHWAY RIGHT OF WAY NET LENGTH186.700 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 16,149.000 5,992.000 19.900 119,240.80 0065 0730 SPOT MOWING AC 50.000 6.500 19.900 129.35 0 SUBTOTAL BID ITEMS $ 119,370.15 0 TOTAL AMOUNT WORK DONE MOWING HIGHWAY RIGHT OF WAY $ 119,370.15 0 TOTAL AMOUNT WORK DONE CONTROL 6173-57-001 $ 119,370.15 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1084038 MGR.NO. 052 PAGE 001 CONT 6173 SEC 57 JOB 001 RES ENGR HORST, MARTIN PROJ RMC - 617357001 HWY US0077 P O BOX 9907 CORPUS CHRIS CNTY NUECES DIST 16 CONTRACT PRICE $ 322,360.10 REPORT DATE 11/06/2009 16.20.27 CONTRACTOR BENTEX, INC. 6904 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 016 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN JUL 14, 2008 WORKING DAYS USED 479 PERCENT COMPLETE 37.03 PERCENT TIME USED 75.50 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6173-57-001 RMC - 617357001 16 US0077 NUECES - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 16,149.000 5,992.000 19.900 119,240.80 0730 SPOT MOWING AC 50.000 6.500 19.900 129.35 0 SUBTOTAL BID ITEMS $ 119,370.15 0 CONTRACT TOTAL ALL ITEMS $ 119,370.15 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1084038 MGR.NO. 052 PAGE 001 CONT 6173 SEC 57 JOB 001 RES ENGR HORST, MARTIN PROJ RMC - 617357001 HWY US0077 P O BOX 9907 CORPUS CHRIS CNTY NUECES DIST 16 CONTRACT PRICE $ 322,360.10 REPORT DATE 11/06/2009 16.20.27 CONTRACTOR BENTEX, INC. 6904 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 016 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 178 RMC - 617357001 6173-57-001 119,370.15 .00 119,370.15 .00 .00 119,370.15 106,315.75 13,054.40 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 119,370.15 .00 119,370.15 .00 .00 119,370.15 106,315.75 13,054.40 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1084038 MGR.NO. 052 PAGE 001 CONT 6173 SEC 57 JOB 001 RES ENGR HORST, MARTIN PROJ RMC - 617357001 HWY US0077 P O BOX 9907 CORPUS CHRIS CNTY NUECES DIST 16 CONTRACT PRICE $ 322,360.10 REPORT DATE 11/06/2009 16.20.27 CONTRACTOR BENTEX, INC. 6904 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 016 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6173-57-001 RMC - 617357001 16 US0077 NUECES -LIMITS - VARIOUS . LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0730 FULL-WIDTH MOWING AC 16,149.000 656.000 19.900 13,054.40 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 13,054.40 0 TOTAL AMOUNT WORK DONE TO DATE - $ 119,370.15