1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5071608 MGR.NO. 050 PAGE 001 CONT 6159 SEC 96 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 615996001 HWY SH0044 P O BOX 889 ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 101,835.00 REPORT DATE 09/05/2008 08.52.23 CONTRACTOR HIGHWAY TECHNOLOGIES, L.P. 13367 EST PERIOD AUG 01,2008 TO AUG 24,2008 EST NO 013 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 24, 2007 TIME COMPUTED FROM AUG 24, 2007 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 343 343 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 08 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 08/23/08 3 1 DAYS CHARGED TO DATE = 365 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 450 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 450 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 WORK COMPLETED AND ACCEPTED - - - ----- ----- ----- 366 365 1 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5071608 MGR.NO. 050 PAGE 001 CONT 6159 SEC 96 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 615996001 HWY SH0044 P O BOX 889 ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 101,835.00 REPORT DATE 09/05/2008 08.52.23 CONTRACTOR HIGHWAY TECHNOLOGIES, L.P. 13367 EST PERIOD AUG 01,2008 TO AUG 24,2008 EST NO 013 DIST. 16 COUNTY JIM WELLS CONTROL 6159-96-001 PROJECT RMC - 615996001 HIGHWAY SH0044 0LIMITS- VARIOUS . 0TYPE OF WORK- SPECIALTY PAVEMENT MARKINGS 0 0005 PREPARED BY KRISTI GILBERTSON 0 0055 SPECIALTY PAVEMENT MARKINGS NET LENGTH841.400 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0668 PREFAB PAV MRK TY C (W) (12") (SLD) LF 4,000.000 2,821.000 3.750 10,578.75 0065 0668 PREFAB PAV MRK TY C (W) (24") (SLD) LF 5,000.000 3,600.000 7.500 27,000.00 0070 0668 PREFAB PAV MRK TY C (W) (ARROW) EA 50.000 28.000 85.000 2,380.00 0075 0668 PREFAB PAV MRK TY C (W) (DBL ARROW) EA 5.000 0.000 125.000 .00 0080 0668 PREFAB PAV MRK TY C (W) (ENTR GORE) EA 5.000 0.000 1,850.000 .00 0085 0668 PREFAB PAV MRK TY C (W) (EXIT GORE) EA 5.000 0.000 2,750.000 .00 0090 0668 PREFAB PAV MRK TY C (W) (RR XING) EA 25.000 17.000 350.000 5,950.00 0095 0668 PREFAB PAV MRK TY C (W) (WORD) EA 40.000 22.000 125.000 2,750.00 0100 0668 PREFAB PAV MRK TY C (Y) (12") (SLD) LF 500.000 0.000 4.500 .00 0105 0668 PREFAB PAV MRK TY C (Y) (24") (SLD) LF 500.000 0.000 9.000 .00 0110 6055 IN-LANE OR TRANSVERSE RUMBLE STRIP LF 160.000 0.000 6.000 .00 0 SUBTOTAL BID ITEMS $ 48,658.75 0 TOTAL AMOUNT WORK DONE SPECIALTY PAVEMENT MARKINGS $ 48,658.75 0 TOTAL AMOUNT WORK DONE CONTROL 6159-96-001 $ 48,658.75 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5071608 MGR.NO. 050 PAGE 001 CONT 6159 SEC 96 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 615996001 HWY SH0044 P O BOX 889 ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 101,835.00 REPORT DATE 09/05/2008 08.52.24 CONTRACTOR HIGHWAY TECHNOLOGIES, L.P. 13367 EST PERIOD AUG 01,2008 TO AUG 24,2008 EST NO 013 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN AUG 24, 2007 WORKING DAYS USED 365 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED AUG 23 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6159-96-001 RMC - 615996001 16 SH0044 JIM WELLS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0668 PREFAB PAV MRK TY C (W) (12") (SLD) LF 4,000.000 2,821.000 3.750 10,578.75 0668 PREFAB PAV MRK TY C (W) (24") (SLD) LF 5,000.000 3,600.000 7.500 27,000.00 0668 PREFAB PAV MRK TY C (W) (ARROW) EA 50.000 28.000 85.000 2,380.00 0668 PREFAB PAV MRK TY C (W) (RR XING) EA 25.000 17.000 350.000 5,950.00 0668 PREFAB PAV MRK TY C (W) (WORD) EA 40.000 22.000 125.000 2,750.00 0 SUBTOTAL BID ITEMS $ 48,658.75 0 CONTRACT TOTAL ALL ITEMS $ 48,658.75 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5071608 MGR.NO. 050 PAGE 001 CONT 6159 SEC 96 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 615996001 HWY SH0044 P O BOX 889 ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 101,835.00 REPORT DATE 09/05/2008 08.52.24 CONTRACTOR HIGHWAY TECHNOLOGIES, L.P. 13367 EST PERIOD AUG 01,2008 TO AUG 24,2008 EST NO 013 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 126 RMC - 615996001 6159-96-001 48,658.75 .00 48,658.75 .00 .00 48,658.75 48,658.75 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 48,658.75 .00 48,658.75 .00 .00 48,658.75 48,658.75 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5071608 MGR.NO. 050 PAGE 001 CONT 6159 SEC 96 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 615996001 HWY SH0044 P O BOX 889 ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 101,835.00 REPORT DATE 09/05/2008 08.52.24 CONTRACTOR HIGHWAY TECHNOLOGIES, L.P. 13367 EST PERIOD AUG 01,2008 TO AUG 24,2008 EST NO 013 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6159-96-001 RMC - 615996001 16 SH0044 JIM WELLS -LIMITS - VARIOUS . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 48,658.75