1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8082301 MGR.NO. PAGE 001 CONT 6184 SEC 39 JOB 001 RES ENGR SMITH, LARRY PROJ EMC - 618439001 HWY IH0020 906 EAST MAIN EASTLAND CNTY EASTLAND DIST 23 CONTRACT PRICE $ 77,000.00 REPORT DATE 09/11/2008 09.01.55 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD AUG 14,2008 TO AUG 18,2008 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 14, 2008 TIME COMPUTED FROM AUG 14, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 10 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 08 TOTAL DAYS ALLOWED = 10 DATE WORK COMPLETED 08/18/08 DAYS CHARGED TO DATE = 0 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 0 0 LIQUIDATED DAMAGES 0 DAYS AT $ 0 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR 14 1 WORK BEGAN 15 1 WORK ON PROJECT 16 1 WORK ON PROJECT ---------------------------- 17 1 WORK ON PROJECT AREA/PROJECT ENGINEER 18 1 WORK COMPLETED AND ACCEPTED - - - - 0 ----- ----- ----- 5 0 5 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK BEGAN 3 WORK ON PROJECT 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8082301 MGR.NO. PAGE 001 CONT 6184 SEC 39 JOB 001 RES ENGR SMITH, LARRY PROJ EMC - 618439001 HWY IH0020 906 EAST MAIN EASTLAND CNTY EASTLAND DIST 23 CONTRACT PRICE $ 77,000.00 REPORT DATE 09/11/2008 09.01.55 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD AUG 14,2008 TO AUG 18,2008 EST NO 002 & FINAL DIST. 23 COUNTY EASTLAND CONTROL 6184-39-001 PROJECT EMC - 618439001 HIGHWAY IH0020 0LIMITS- IH 20 @ US 183 OVERPASS " 0TYPE OF WORK- EMERGENCY BRIDGE REPAIR 0 0050 EMERGENCY BRIDGE REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0055 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 3,000.000 3,000.00 0060 0788 CONCRETE BEAM REPAIR EA 2.000 2.000 5,000.000 10,000.00 0065 4191 CARBON FIBER REINF POLY CONC STRENGTHEN SF 4.000 0.000 16,000.000 .00 0065 4191 ADJ EST QUANTITY TO DATE 0.000 0080 9001*CONCRETE BEAM REPAIR (W/CFRP STRENGTH) EA 4.000 4.000 16,000.000 64,000.00 0 SUBTOTAL BID ITEMS $ 77,000.00 0 TOTAL AMOUNT WORK DONE EMERGENCY BRIDGE REPAIR $ 77,000.00 0 TOTAL AMOUNT WORK DONE CONTROL 6184-39-001 $ 77,000.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8082301 MGR.NO. PAGE 001 CONT 6184 SEC 39 JOB 001 RES ENGR SMITH, LARRY PROJ EMC - 618439001 HWY IH0020 906 EAST MAIN EASTLAND CNTY EASTLAND DIST 23 CONTRACT PRICE $ 77,000.00 REPORT DATE 09/11/2008 09.01.55 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD AUG 14,2008 TO AUG 18,2008 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - IH 20 @ US 183 OVERPASS 0 " DATE WORK BEGAN AUG 14, 2008 WORKING DAYS USED 0 PERCENT COMPLETE 100.00 PERCENT TIME USED 0.00 DATE COMPLETED AUG 18 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6184-39-001 EMC - 618439001 23 IH0020 EASTLAND - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 3,000.000 3,000.00 0788 CONCRETE BEAM REPAIR EA 2.000 2.000 5,000.000 10,000.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09001* CONCRETE BEAM REPAIR (W/CFRP STRENGTH) EA 4.000 4.000 16,000.000 64,000.00 0 SUBTOTAL BID ITEMS $ 77,000.00 0 CONTRACT TOTAL ALL ITEMS $ 77,000.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8082301 MGR.NO. PAGE 001 CONT 6184 SEC 39 JOB 001 RES ENGR SMITH, LARRY PROJ EMC - 618439001 HWY IH0020 906 EAST MAIN EASTLAND CNTY EASTLAND DIST 23 CONTRACT PRICE $ 77,000.00 REPORT DATE 09/11/2008 09.01.55 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD AUG 14,2008 TO AUG 18,2008 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 68 EMC - 618439001 6184-39-001 77,000.00 .00 77,000.00 .00 .00 77,000.00 77,000.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 77,000.00 .00 77,000.00 .00 .00 77,000.00 77,000.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8082301 MGR.NO. PAGE 001 CONT 6184 SEC 39 JOB 001 RES ENGR SMITH, LARRY PROJ EMC - 618439001 HWY IH0020 906 EAST MAIN EASTLAND CNTY EASTLAND DIST 23 CONTRACT PRICE $ 77,000.00 REPORT DATE 09/11/2008 09.01.55 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD AUG 14,2008 TO AUG 18,2008 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6184-39-001 EMC - 618439001 23 IH0020 EASTLAND -LIMITS - IH 20 @ US 183 OVERPASS " - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 77,000.00