1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4082304 MGR.NO. PAGE 001 CONT 6176 SEC 49 JOB 001 RES ENGR WILSON, JAMES PROJ RMC - 617649001 HWY US0190 2502 W WALLACE SAN SABA CNTY SAN SABA DIST 23 CONTRACT PRICE $ 97,359.00 REPORT DATE 01/20/2011 15.59.01 CONTRACTOR R&M INCORPORATED 10648 EST PERIOD JUN 24,2008 TO DEC 18,2009 EST NO 020 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 24, 2008 TIME COMPUTED FROM JUL 01, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 35 525 7 518 BROUGHT FORWARD ADDL DAYS GRANTED = 0 DEC 09 1 1 TIME SUSP - LETTER SUBMITTED TOTAL DAYS ALLOWED = 35 2 1 TIME SUSP - LETTER SUBMITTED DATE WORK COMPLETED 12/18/09 3 1 TIME SUSP - LETTER SUBMITTED DAYS CHARGED TO DATE = 14 4 1 TIME SUSP - LETTER SUBMITTED ASSESSED LIQ DAMAGES = 0 5 1 TIME SUSP - LETTER SUBMITTED LIQ DAMAGE RATE $ 400 6 1 TIME SUSP - LETTER SUBMITTED 7 1 TIME SUSP - LETTER SUBMITTED LIQUIDATED DAMAGES 8 1 TIME SUSP - LETTER SUBMITTED 0 DAYS AT $ 400 PER DAY 9 1 TIME SUSP - LETTER SUBMITTED TOTAL = $ .00 10 1 TIME SUSP - LETTER SUBMITTED 11 1 TIME BEGINS - DAY CHARGED CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 SUNDAY TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 DAY CHARGED - WORK ACCEPTED & COMPLETED - - - - 0 ----- ----- ----- 543 14 529 0 SATURDAY 1 SUNDAY 0 HOLIDAY 10 TIME SUSP - LETTER SUBMITTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4082304 MGR.NO. PAGE 001 CONT 6176 SEC 49 JOB 001 RES ENGR WILSON, JAMES PROJ RMC - 617649001 HWY US0190 2502 W WALLACE SAN SABA CNTY SAN SABA DIST 23 CONTRACT PRICE $ 97,359.00 REPORT DATE 01/20/2011 15.59.02 CONTRACTOR R&M INCORPORATED 10648 EST PERIOD JUN 24,2008 TO DEC 18,2009 EST NO 020 & FINAL DIST. 23 COUNTY SAN SABA CONTROL 6176-49-001 PROJECT RMC - 617649001 HIGHWAY US0190 0LIMITS- VARIOUS "." 0TYPE OF WORK- ROADSIDE MOWING 0 0050 ROADSIDE MOWING NET LENGTH213.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0055 0730 STRIP MOWING AC 2,331.000 2,845.000 24.900 70,840.50 0060 0730 FULL-WIDTH MOWING AC 1,579.000 1,885.000 24.900 46,936.50 0 SUBTOTAL BID ITEMS $ 117,777.00 0 TOTAL AMOUNT WORK DONE ROADSIDE MOWING $ 117,777.00 0 TOTAL AMOUNT WORK DONE CONTROL 6176-49-001 $ 117,777.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4082304 MGR.NO. PAGE 001 CONT 6176 SEC 49 JOB 001 RES ENGR WILSON, JAMES PROJ RMC - 617649001 HWY US0190 2502 W WALLACE SAN SABA CNTY SAN SABA DIST 23 CONTRACT PRICE $ 97,359.00 REPORT DATE 01/20/2011 15.59.02 CONTRACTOR R&M INCORPORATED 10648 EST PERIOD JUN 24,2008 TO DEC 18,2009 EST NO 020 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 "." DATE WORK BEGAN JUN 24, 2008 WORKING DAYS USED 14 PERCENT COMPLETE 100.00 PERCENT TIME USED 40.00 DATE COMPLETED DEC 18 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6176-49-001 RMC - 617649001 23 US0190 SAN SABA - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 STRIP MOWING AC 2,331.000 2,845.000 24.900 70,840.50 0730 FULL-WIDTH MOWING AC 1,579.000 1,885.000 24.900 46,936.50 0 SUBTOTAL BID ITEMS $ 117,777.00 0 CONTRACT TOTAL ALL ITEMS $ 117,777.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4082304 MGR.NO. PAGE 001 CONT 6176 SEC 49 JOB 001 RES ENGR WILSON, JAMES PROJ RMC - 617649001 HWY US0190 2502 W WALLACE SAN SABA CNTY SAN SABA DIST 23 CONTRACT PRICE $ 97,359.00 REPORT DATE 01/20/2011 15.59.02 CONTRACTOR R&M INCORPORATED 10648 EST PERIOD JUN 24,2008 TO DEC 18,2009 EST NO 020 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 206 RMC - 617649001 6176-49-001 117,777.00 .00 117,777.00 .00 .00 117,777.00 117,777.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 117,777.00 .00 117,777.00 .00 .00 117,777.00 117,777.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4082304 MGR.NO. PAGE 001 CONT 6176 SEC 49 JOB 001 RES ENGR WILSON, JAMES PROJ RMC - 617649001 HWY US0190 2502 W WALLACE SAN SABA CNTY SAN SABA DIST 23 CONTRACT PRICE $ 97,359.00 REPORT DATE 01/20/2011 15.59.02 CONTRACTOR R&M INCORPORATED 10648 EST PERIOD JUN 24,2008 TO DEC 18,2009 EST NO 020 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6176-49-001 RMC - 617649001 23 US0190 SAN SABA -LIMITS - VARIOUS "." - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 117,777.00