1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5092301 MGR.NO. PAGE 001 CONT 6016 SEC 45 JOB 001 RES ENGR JOHNSON, CARL PROJ RMC - 601645001 HWY US0180 2495 HWY 183 N BROWNWOOD CNTY STEPHENS DIST 23 CONTRACT PRICE $ 218,874.21 REPORT DATE 06/28/2012 12.04.13 CONTRACTOR BIG CREEK CONSTRUCTION, LTD. 8175 EST PERIOD JUL 28,2009 TO FEB 16,2011 EST NO 004 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 28, 2009 TIME COMPUTED FROM JUL 28, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 40 65 25 40 BROUGHT FORWARD ADDL DAYS GRANTED = 40 FEB 11 1 1 TIME SUSPENDED TOTAL DAYS ALLOWED = 80 2 1 TIME SUSPENDED DATE WORK COMPLETED 02/16/11 3 1 TIME SUSPENDED DAYS CHARGED TO DATE = 22 4 1 TIME SUSPENDED ASSESSED LIQ DAMAGES = 0 5 1 TIME SUSPENDED LIQ DAMAGE RATE $ 500 6 1 TIME SUSPENDED 7 1 TIME SUSPENDED LIQUIDATED DAMAGES 8 1 TIME SUSPENDED 0 DAYS AT $ 500 PER DAY 9 1 TIME SUSPENDED TOTAL = $ .00 10 1 TIME SUSPENDED 11 1 TIME SUSPENDED CERTIFIED AS CORRECT AND 12 1 TIME SUSPENDED ONE COPY HAS BEEN GIVEN 13 1 TIME SUSPENDED TO THE CONTRACTOR 14 1 TIME SUSPENDED 15 1 TIME SUSPENDED 16 1 WORK COMPLETED AND ACCEPTED ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 81 25 56 0 SATURDAY 0 SUNDAY 0 HOLIDAY 15 TIME SUSPENDED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5092301 MGR.NO. PAGE 001 CONT 6016 SEC 45 JOB 001 RES ENGR JOHNSON, CARL PROJ RMC - 601645001 HWY US0180 2495 HWY 183 N BROWNWOOD CNTY STEPHENS DIST 23 CONTRACT PRICE $ 218,874.21 REPORT DATE 06/28/2012 12.04.14 CONTRACTOR BIG CREEK CONSTRUCTION, LTD. 8175 EST PERIOD JUL 28,2009 TO FEB 16,2011 EST NO 004 & FINAL DIST. 23 COUNTY STEPHENS CONTROL 6016-45-001 PROJECT RMC - 601645001 HIGHWAY US0180 0LIMITS- VARIOUS " " 0TYPE OF WORK- REMOVE AND INLAY ACP AS NEEDED 0 0050 REMOVE AND INLAY ACP AS NEEDED NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0055 0105 REMOVING STAB BASE AND ASPH PAV (0-4") SY 26,600.640 27,470.090 1.500 41,205.14 0055 0105 ADJ EST QUANTITY TO DATE 53,201.280 0060 0341 D-GR HMA(QCQA) TY-C SAC-B PG76-22 TON 2,294.310 2,629.120 75.000 197,184.00 0060 0341 ADJ EST QUANTITY TO DATE 4,588.620 0065 0500 MOBILIZATION LS 1.000 1.000 4,500.000 4,500.00 0070 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 1,200.000 2,400.00 0070 0502 ADJ EST QUANTITY TO DATE 4.000 0100 9001*CREDIT FOR 2 DAYS LIQUIDATED DAMAGES LS 1.000 1.000 1,000.000 1,000.00 0 SUBTOTAL BID ITEMS $ 246,289.14 0 SPECIAL DEDUCTIONS - 0 LINE MATRL. NO MATERIAL DESCRIPTION UNIT QUANTITY UNIT AMOUNT NO. PRICE($) ($) - 0900 00000000799 LIQUIDATED DAMAGES EA 2.000 500.000 -1,000.00 0 TOTAL SPECIAL DEDUCTIONS - $ -1,000.00 0 TOTAL AMOUNT WORK DONE REMOVE AND INLAY ACP AS NEEDED $ 246,289.14 TOTAL SPECIAL DEDUCTIONS REMOVE AND INLAY ACP AS NEEDED $ -1,000.00 0 TOTAL AMOUNT WORK DONE CONTROL 6016-45-001 $ 246,289.14 0 TOTAL SPECIAL DEDUCTIONS CONTROL 6016-45-001 $ -1,000.00 1 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5092301 MGR.NO. PAGE 001 CONT 6016 SEC 45 JOB 001 RES ENGR JOHNSON, CARL PROJ RMC - 601645001 HWY US0180 2495 HWY 183 N BROWNWOOD CNTY STEPHENS DIST 23 CONTRACT PRICE $ 218,874.21 REPORT DATE 06/28/2012 12.04.14 CONTRACTOR BIG CREEK CONSTRUCTION, LTD. 8175 EST PERIOD JUL 28,2009 TO FEB 16,2011 EST NO 004 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 " " DATE WORK BEGAN JUL 28, 2009 WORKING DAYS USED 22 PERCENT COMPLETE 100.00 PERCENT TIME USED 27.50 DATE COMPLETED FEB 16 2011 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6016-45-001 RMC - 601645001 23 US0180 STEPHENS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0105 REMOVING STAB BASE AND ASPH PAV (0-4") SY 26,600.640 27,470.090 1.500 41,205.14 0105 ADJ EST QUANTITY TO DATE 53,201.280 0341 D-GR HMA(QCQA) TY-C SAC-B PG76-22 TON 2,294.310 2,629.120 75.000 197,184.00 0341 ADJ EST QUANTITY TO DATE 4,588.620 0500 MOBILIZATION LS 1.000 1.000 4,500.000 4,500.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 1,200.000 2,400.00 0502* ADJ EST QUANTITY TO DATE 4.000 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09001* CREDIT FOR 2 DAYS LIQUIDATED DAMAGES LS 1.000 1.000 1,000.000 1,000.00 0 SUBTOTAL BID ITEMS $ 246,289.14 0 CONTRACT TOTAL ALL ITEMS $ 246,289.14 SPECIAL DEDUCTIONS 0 UNIT AMOUNT MATRL. NO. MATERIAL DESCRIPTION UNIT QUANTITY PRICE ($) ($) 0 00000000799 LIQUIDATED DAMAGES EA 2.000 500.000 -1,000.00 1 TOTAL SPECIAL DEDUCTIONS $ -1,000.00 0 CONTRACT TOTAL SPECIAL DEDUCTIONS $ -1,000.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5092301 MGR.NO. PAGE 001 CONT 6016 SEC 45 JOB 001 RES ENGR JOHNSON, CARL PROJ RMC - 601645001 HWY US0180 2495 HWY 183 N BROWNWOOD CNTY STEPHENS DIST 23 CONTRACT PRICE $ 218,874.21 REPORT DATE 06/28/2012 12.04.14 CONTRACTOR BIG CREEK CONSTRUCTION, LTD. 8175 EST PERIOD JUL 28,2009 TO FEB 16,2011 EST NO 004 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 215 RMC - 601645001 6016-45-001 246,289.14 .00 246,289.14 1,000.00 .00 245,289.14 245,289.14 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 246,289.14 .00 246,289.14 1,000.00 .00 245,289.14 245,289.14 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5092301 MGR.NO. PAGE 001 CONT 6016 SEC 45 JOB 001 RES ENGR JOHNSON, CARL PROJ RMC - 601645001 HWY US0180 2495 HWY 183 N BROWNWOOD CNTY STEPHENS DIST 23 CONTRACT PRICE $ 218,874.21 REPORT DATE 06/28/2012 12.04.14 CONTRACTOR BIG CREEK CONSTRUCTION, LTD. 8175 EST PERIOD JUL 28,2009 TO FEB 16,2011 EST NO 004 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6016-45-001 RMC - 601645001 23 US0180 STEPHENS -LIMITS - VARIOUS " " - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 246,289.14