1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 9121703 MGR.NO. 059 PAGE 001 CONT 6247 SEC 18 JOB 001 RES ENGR KROLL, RAYMOND PROJ RMC - 624718001 HWY SH0006 2591 N. EARL RUDDER BRYAN CNTY ROBERTSON DIST 17 CONTRACT PRICE $ 228,959.44 REPORT DATE 05/08/2013 17.25.50 CONTRACTOR EXPERT MAINTENANCE SERVICES EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 006 LLC 15331 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 27, 2012 TIME COMPUTED FROM DEC 05, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 108 125 0 125 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 13 1 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013)TOTAL DAYS ALLOWED = 108 2 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013)DATE WORK COMPLETED 3 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013)DAYS CHARGED TO DATE = 0 4 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013)ASSESSED LIQ DAMAGES = 0 5 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013)LIQ DAMAGE RATE $ 590 6 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 7 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) LIQUIDATED DAMAGES 8 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 0 DAYS AT $ 590 PER DAY 9 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013)TOTAL = $ .00 10 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 11 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013)CERTIFIED AS CORRECT AND 12 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013)ONE COPY HAS BEEN GIVEN 13 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013)TO THE CONTRACTOR 14 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 15 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 16 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013)---------------------------- 17 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013)AREA/PROJECT ENGINEER 18 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 19 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 20 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 21 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 22 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 23 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 24 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 25 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 26 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 27 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 28 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 29 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 30 1 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 0 ----- ----- ----- 155 0 155 0 SATURDAY 0 SUNDAY 0 HOLIDAY 30 AWAITING WORK ORDER (TO BEGIN 5/3/2013) 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 9121703 MGR.NO. 059 PAGE 001 CONT 6247 SEC 18 JOB 001 RES ENGR KROLL, RAYMOND PROJ RMC - 624718001 HWY SH0006 2591 N. EARL RUDDER BRYAN CNTY ROBERTSON DIST 17 CONTRACT PRICE $ 228,959.44 REPORT DATE 05/08/2013 17.25.50 CONTRACTOR EXPERT MAINTENANCE SERVICES EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 006 LLC 15331 DIST. 17 COUNTY ROBERTSON CONTROL 6247-18-001 PROJECT RMC - 624718001 HIGHWAY SH0006 0LIMITS- VARIOU VARIOUS 0TYPE OF WORK- CLEANING AND SWEEPING HIGHWAYS 0 0005 PREPARED BY DISTRICT MAINTENANCE 0 0055 CLEANING AND SWEEPING OF HIGHWAYS NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0738 CLEANING/SWEEPING (CENTER MEDIAN) MI 300.440 0.000 349.000 .00 0065 0738 CLEANING/SWEEPING (OUTSIDE MAIN LANE) MI 297.120 0.000 349.000 .00 0070 0738 CLEANING/SWEEPING (FRONTAGE ROAD) MI 3.520 0.000 50.000 .00 0075 0738 CLEANING/SWEEPING (ENTRANCE/EXIT RAMP) MI 43.520 0.000 200.000 .00 0080 0738 CLEANING/SWEEPING (AGGREGATE REMOVAL) MI 73.540 0.000 150.000 .00 0085 0738 CLEANING/SWEEPING (SPOT) MI 8.000 0.000 50.000 .00 0090 0738 CLEANING/SWEEPING (HANDWORK) SY 500.000 0.000 .200 .00 0 TOTAL AMOUNT WORK DONE CLEANING AND SWEEPING OF HIGHWAYS $ .00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 9121703 MGR.NO. 059 PAGE 001 CONT 6247 SEC 18 JOB 001 RES ENGR KROLL, RAYMOND PROJ RMC - 624718001 HWY SH0006 2591 N. EARL RUDDER BRYAN CNTY ROBERTSON DIST 17 CONTRACT PRICE $ 228,959.44 REPORT DATE 05/08/2013 17.25.50 CONTRACTOR EXPERT MAINTENANCE SERVICES EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 006 LLC 15331 0*********************************************************************************************************************************** -LIMITS - VARIOU 0 VARIOUS DATE WORK BEGAN NOV 27, 2012 WORKING DAYS USED 0 PERCENT COMPLETE 0.00 PERCENT TIME USED 0.00 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6247-18-001 RMC - 624718001 17 SH0006 ROBERTSON 0***** NO WORK TO DATE FOR CONTRACT ***** 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 9121703 MGR.NO. 059 PAGE 001 CONT 6247 SEC 18 JOB 001 RES ENGR KROLL, RAYMOND PROJ RMC - 624718001 HWY SH0006 2591 N. EARL RUDDER BRYAN CNTY ROBERTSON DIST 17 CONTRACT PRICE $ 228,959.44 REPORT DATE 05/08/2013 17.25.50 CONTRACTOR EXPERT MAINTENANCE SERVICES EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 006 LLC 15331 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 198 RMC - 624718001 6247-18-001 .00 .00 .00 .00 .00 .00 .00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** .00 .00 .00 .00 .00 .00 .00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 9121703 MGR.NO. 059 PAGE 001 CONT 6247 SEC 18 JOB 001 RES ENGR KROLL, RAYMOND PROJ RMC - 624718001 HWY SH0006 2591 N. EARL RUDDER BRYAN CNTY ROBERTSON DIST 17 CONTRACT PRICE $ 228,959.44 REPORT DATE 05/08/2013 17.25.51 CONTRACTOR EXPERT MAINTENANCE SERVICES EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 006 LLC 15331 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6247-18-001 RMC - 624718001 17 SH0006 ROBERTSON -LIMITS - VARIOU VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 0.00