1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5121703 MGR.NO. 053 PAGE 001 CONT 6236 SEC 24 JOB 001 RES ENGR JAQUEZ, RANDY PROJ BPM - 623624001 HWY FM1373 P.O. BOX 506 HEARNE CNTY ROBERTSON DIST 17 CONTRACT PRICE $ 22,400.00 REPORT DATE 11/08/2012 18.30.39 CONTRACTOR TEXCAVATION CO. 13474 EST PERIOD AUG 17,2012 TO OCT 04,2012 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 17, 2012 TIME COMPUTED FROM AUG 25, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 30 45 20 25 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 12 1 1 AWAITING AREA ENGINEER ACCEPTANCE TOTAL DAYS ALLOWED = 30 2 1 AWAITING AREA ENGINEER ACCEPTANCE DATE WORK COMPLETED 10/04/12 3 1 AWAITING AREA ENGINEER ACCEPTANCE DAYS CHARGED TO DATE = 20 4 1 WORK ACCEPTED ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 570 0 LIQUIDATED DAMAGES 0 DAYS AT $ 570 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 49 20 29 0 SATURDAY 0 SUNDAY 0 HOLIDAY 3 AWAITING AREA ENGINEER ACCEPTANCE 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5121703 MGR.NO. 053 PAGE 001 CONT 6236 SEC 24 JOB 001 RES ENGR JAQUEZ, RANDY PROJ BPM - 623624001 HWY FM1373 P.O. BOX 506 HEARNE CNTY ROBERTSON DIST 17 CONTRACT PRICE $ 22,400.00 REPORT DATE 11/08/2012 18.30.41 CONTRACTOR TEXCAVATION CO. 13474 EST PERIOD AUG 17,2012 TO OCT 04,2012 EST NO 003 & FINAL DIST. 17 COUNTY ROBERTSON CONTROL 6236-24-001 PROJECT BPM - 623624001 HIGHWAY FM1373 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- BRIDGE STEEL PILE REPAIR 0 0005 PREPARED BY THE BRYAN DISTRICT BRIDGE OFFICE 0 0055 BRIDGE STEEL PILE REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0100 PREPARING ROW STA 2.000 2.000 1,250.000 2,500.00 0065 0420 CL C CONC (PILE ENCASEMENT) LF 44.000 44.000 350.000 15,400.00 0070 0446 CLEAN AND PAINT EXIST STR (REF NO. 2) EA 1.000 1.000 2,000.000 2,000.00 0075 0500 MOBILIZATION LS 1.000 1.000 1,000.000 1,000.00 0080 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 1,000.000 1,000.00 0085 0506 TEMPORARY SEDIMENT CONTROL FENCE LF 100.000 100.000 5.000 500.00 0 SUBTOTAL BID ITEMS $ 22,400.00 0 TOTAL AMOUNT WORK DONE BRIDGE STEEL PILE REPAIR $ 22,400.00 0 TOTAL AMOUNT WORK DONE CONTROL 6236-24-001 $ 22,400.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5121703 MGR.NO. 053 PAGE 001 CONT 6236 SEC 24 JOB 001 RES ENGR JAQUEZ, RANDY PROJ BPM - 623624001 HWY FM1373 P.O. BOX 506 HEARNE CNTY ROBERTSON DIST 17 CONTRACT PRICE $ 22,400.00 REPORT DATE 11/08/2012 18.30.41 CONTRACTOR TEXCAVATION CO. 13474 EST PERIOD AUG 17,2012 TO OCT 04,2012 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN AUG 17, 2012 WORKING DAYS USED 20 PERCENT COMPLETE 100.00 PERCENT TIME USED 66.60 DATE COMPLETED OCT 4 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6236-24-001 BPM - 623624001 17 FM1373 ROBERTSON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0100 PREPARING ROW STA 2.000 2.000 1,250.000 2,500.00 0420 CL C CONC (PILE ENCASEMENT) LF 44.000 44.000 350.000 15,400.00 0446 CLEAN AND PAINT EXIST STR (REF NO. 2) EA 1.000 1.000 2,000.000 2,000.00 0500 MOBILIZATION LS 1.000 1.000 1,000.000 1,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 1,000.000 1,000.00 0506 TEMPORARY SEDIMENT CONTROL FENCE LF 100.000 100.000 5.000 500.00 0 SUBTOTAL BID ITEMS $ 22,400.00 0 CONTRACT TOTAL ALL ITEMS $ 22,400.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5121703 MGR.NO. 053 PAGE 001 CONT 6236 SEC 24 JOB 001 RES ENGR JAQUEZ, RANDY PROJ BPM - 623624001 HWY FM1373 P.O. BOX 506 HEARNE CNTY ROBERTSON DIST 17 CONTRACT PRICE $ 22,400.00 REPORT DATE 11/08/2012 18.30.41 CONTRACTOR TEXCAVATION CO. 13474 EST PERIOD AUG 17,2012 TO OCT 04,2012 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 198 BPM - 623624001 6236-24-001 22,400.00 .00 22,400.00 .00 .00 22,400.00 22,300.00 100.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 22,400.00 .00 22,400.00 .00 .00 22,400.00 22,300.00 100.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5121703 MGR.NO. 053 PAGE 001 CONT 6236 SEC 24 JOB 001 RES ENGR JAQUEZ, RANDY PROJ BPM - 623624001 HWY FM1373 P.O. BOX 506 HEARNE CNTY ROBERTSON DIST 17 CONTRACT PRICE $ 22,400.00 REPORT DATE 11/08/2012 18.30.41 CONTRACTOR TEXCAVATION CO. 13474 EST PERIOD AUG 17,2012 TO OCT 04,2012 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6236-24-001 BPM - 623624001 17 FM1373 ROBERTSON -LIMITS - VARIOUS VARIOUS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 75 0500 MOBILIZATION LS 1.000 0.100 1,000.000 100.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 100.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 22,400.00