1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7111701 MGR.NO. 050 PAGE 001 CONT 6219 SEC 34 JOB 001 RES ENGR LAYWELL, BLANE PROJ RMC - 621934001 HWY FM0485 3303 N TRAVIS CAMERON CNTY MILAM DIST 17 CONTRACT PRICE $ 219,328.56 REPORT DATE 06/12/2012 14.57.21 CONTRACTOR RAY FARIS, INC. 643 EST PERIOD FEB 07,2012 TO MAY 31,2012 EST NO 004 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN FEB 07, 2012 TIME COMPUTED FROM FEB 15, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 25 84 16 68 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAY 12 1 1 TOTAL DAYS ALLOWED = 25 2 1 DATE WORK COMPLETED 05/25/12 3 1 DAYS CHARGED TO DATE = 23 4 1 ASSESSED LIQ DAMAGES = 0 5 1 SATURDAY LIQ DAMAGE RATE $ 500 6 1 SUNDAY 7 1 LIQUIDATED DAMAGES 8 1 RAIN 0 DAYS AT $ 500 PER DAY 9 1 TOO WET TOTAL = $ .00 10 1 TOO WET 11 1 TOO WET CERTIFIED AS CORRECT AND 12 1 SATURDAY ONE COPY HAS BEEN GIVEN 13 1 SUNDAY TO THE CONTRACTOR 14 1 TOO WET 15 1 RAIN 16 1 TOO WET ---------------------------- 17 1 TOO WET AREA/PROJECT ENGINEER 18 1 TOO WET 19 1 SATURDAY 20 1 SUNDAY 21 1 22 1 AWAITING DECISION FROM AREA ENGINEER 23 1 AWAITING DECISION FROM AREA ENGINEER 24 1 WORK COMPLETED 25 1 WORK ACCEPTED - - ----- ----- ----- 109 23 86 3 SATURDAY 3 SUNDAY 0 HOLIDAY 2 RAIN 7 TOO WET 2 AWAITING DECISION FROM AREA ENGINEER 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7111701 MGR.NO. 050 PAGE 001 CONT 6219 SEC 34 JOB 001 RES ENGR LAYWELL, BLANE PROJ RMC - 621934001 HWY FM0485 3303 N TRAVIS CAMERON CNTY MILAM DIST 17 CONTRACT PRICE $ 219,328.56 REPORT DATE 06/12/2012 14.57.22 CONTRACTOR RAY FARIS, INC. 643 EST PERIOD FEB 07,2012 TO MAY 31,2012 EST NO 004 & FINAL DIST. 17 COUNTY MILAM CONTROL 6219-34-001 PROJECT RMC - 621934001 HIGHWAY FM0485 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- REPLACE CULVERTS 0 0005 PREPARED BY DISTRICT MAINTENANCE 0 0055 REPLACE CULVERTS ON FM 485 FM 979 NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0100 PREPARING ROW STA 3.000 3.000 1,900.000 5,700.00 0065 0110 EXCAVATION (SPECIAL) CY 60.000 60.000 30.000 1,800.00 0070 0132 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 213.000 213.000 45.000 9,585.00 0075 0158 SPEC EXCAV WORK (BACKHOE) HR 12.000 10.000 50.000 500.00 0080 0158 SPEC EXCAV WORK (HYD EXCAVATOR) HR 9.000 9.000 135.000 1,215.00 0085 0164 STRAW/HAY MLCH SEED(PERM)(RURAL)(SANDY) SY 261.000 355.556 3.840 1,365.34 0090 0168 VEGETATIVE WATERING MG 2.600 0.000 385.000 .00 0095 0400 CEM STABIL BKFL CY 290.000 290.000 80.000 23,200.00 0100 0400 CUT & RESTORING PAV SY 54.000 54.000 60.000 3,240.00 0105 0401 FLOWABLE BACKFILL CY 33.000 33.000 78.000 2,574.00 0110 0402 TRENCH EXCAVATION PROTECTION LF 230.000 230.000 5.000 1,150.00 0115 0403 TEMPORARY SPL SHORING SF 1,207.000 874.000 20.000 17,480.00 0120 0432 RIPRAP (CONC)(4 IN) CY 10.000 10.000 350.000 3,500.00 0125 0432 RIPRAP (STONE PROTECTION)(15 IN) CY 44.000 47.404 95.000 4,503.38 0130 0460 CMP (GAL STL 24 IN) LF 9.000 7.000 65.000 455.00 0135 0460 CMP (GAL STL 30 IN) LF 6.000 6.000 95.000 570.00 0140 0464 RC PIPE (CL III)(24 IN) LF 99.000 99.000 95.000 9,405.00 0145 0464 RC PIPE (CL III)(30 IN) LF 147.000 147.000 85.000 12,495.00 0150 0464 RC PIPE (CL III)(36 IN) LF 44.000 44.000 87.000 3,828.00 0155 0465 INLET (COMPL)(TY H) EA 1.000 1.000 3,100.000 3,100.00 0160 0465 MANH (COMPL)(JUNCT BOX)(TY M) EA 2.000 2.000 3,300.000 6,600.00 0165 0466 HEADWALL (CH-FW-0)(DIA= 36 IN) EA 2.000 2.000 5,900.000 11,800.00 0170 0467 SET (TY II)(24 1 IN)(RCP)(3:1)(C) EA 1.000 1.000 760.000 760.00 0175 0467 SET (TY II)(30 IN)(RCP)(3:1)(C) EA 1.000 1.000 1,300.000 1,300.00 0180 0467 SET (TY II)(30 IN)(RCP)(4:1)(C) EA 1.000 1.000 1,500.000 1,500.00 0185 0467 SET (TY II)(24 IN)(RCP)(6:1)(C) EA 1.000 1.000 980.000 980.00 0190 0496 REMOV STR (INLET) EA 1.000 1.000 500.000 500.00 0195 0496 REMOV STR (SET) EA 1.000 1.000 500.000 500.00 0200 0496 REMOV STR (PIPE) EA 4.000 4.000 500.000 2,000.00 0205 0500 MOBILIZATION LS 1.000 1.000 29,632.860 29,632.86 0210 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 5,897.230 11,794.46 0215 0506 ROCK FILTER DAMS (INSTALL) (TY 1) LF 36.000 36.000 35.000 1,260.00 0220 0506 ROCK FILTER DAMS (REMOVE) LF 36.000 0.000 10.000 .00 0225 0506 BACKHOE WORK (EROSION & SEDM CONT) HR 4.000 0.000 65.000 .00 0230 0506 TEMPORARY SEDIMENT CONTROL FENCE LF 235.000 240.000 3.000 720.00 0235 0506 SANDBAGS FOR EROSION CONTROL (6 IN) LF 32.000 34.000 8.000 272.00 0240 0508 CONSTRUCTING DETOURS EA 4.000 4.000 8,500.000 34,000.00 0245 0552 WIRE FENCE (TY A) LF 90.000 75.000 25.000 1,875.00 0 SUBTOTAL BID ITEMS $ 211,160.04 0 MATERIAL ON HAND 0 LINE MATRL. NO MATERIAL DESCRIPTION UNIT QUANTITY % INV UNIT PRICE AMOUNT NO. PRICE ALLOWED($) ($) 0 0250 933 PRECAST CONC END SECTIONS EA 0.000 100 629.990 .00 0255 926 RC PIPE LF 0.000 100 36.050 .00 0260 911 PRECAST INLET EA 0.000 100 1,900.000 .00 0265 911 PRECAST INLET EA 0.000 100 3,300.000 .00 0270 926 RC PIPE LF 0.000 100 25.550 .00 0275 926 RC PIPE LF 0.000 100 51.550 .00 0 TOTAL AMOUNT WORK DONE REPLACE CULVERTS ON FM 485 FM 979 $ 211,160.04 0 TOTAL AMOUNT WORK DONE CONTROL 6219-34-001 $ 211,160.04 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7111701 MGR.NO. 050 PAGE 001 CONT 6219 SEC 34 JOB 001 RES ENGR LAYWELL, BLANE PROJ RMC - 621934001 HWY FM0485 3303 N TRAVIS CAMERON CNTY MILAM DIST 17 CONTRACT PRICE $ 219,328.56 REPORT DATE 06/12/2012 14.57.22 CONTRACTOR RAY FARIS, INC. 643 EST PERIOD FEB 07,2012 TO MAY 31,2012 EST NO 004 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN FEB 7 , 2012 WORKING DAYS USED 23 PERCENT COMPLETE 100.00 PERCENT TIME USED 92.00 DATE COMPLETED MAY 25 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6219-34-001 RMC - 621934001 17 FM0485 MILAM - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0100 PREPARING ROW STA 3.000 3.000 1,900.000 5,700.00 0110 EXCAVATION (SPECIAL) CY 60.000 60.000 30.000 1,800.00 0132 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 213.000 213.000 45.000 9,585.00 0158 SPEC EXCAV WORK (BACKHOE) HR 12.000 10.000 50.000 500.00 0158 SPEC EXCAV WORK (HYD EXCAVATOR) HR 9.000 9.000 135.000 1,215.00 0164 STRAW/HAY MLCH SEED(PERM)(RURAL)(SANDY) SY 261.000 355.556 3.840 1,365.34 0400 CEM STABIL BKFL CY 290.000 290.000 80.000 23,200.00 0400 CUT & RESTORING PAV SY 54.000 54.000 60.000 3,240.00 0401 FLOWABLE BACKFILL CY 33.000 33.000 78.000 2,574.00 0402 TRENCH EXCAVATION PROTECTION LF 230.000 230.000 5.000 1,150.00 0403 TEMPORARY SPL SHORING SF 1,207.000 874.000 20.000 17,480.00 0432 RIPRAP (CONC)(4 IN) CY 10.000 10.000 350.000 3,500.00 0432 RIPRAP (STONE PROTECTION)(15 IN) CY 44.000 47.404 95.000 4,503.38 0460 CMP (GAL STL 24 IN) LF 9.000 7.000 65.000 455.00 0460 CMP (GAL STL 30 IN) LF 6.000 6.000 95.000 570.00 0464 RC PIPE (CL III)(24 IN) LF 99.000 99.000 95.000 9,405.00 0464 RC PIPE (CL III)(30 IN) LF 147.000 147.000 85.000 12,495.00 0464 RC PIPE (CL III)(36 IN) LF 44.000 44.000 87.000 3,828.00 0465 INLET (COMPL)(TY H) EA 1.000 1.000 3,100.000 3,100.00 0465 MANH (COMPL)(JUNCT BOX)(TY M) EA 2.000 2.000 3,300.000 6,600.00 10466 HEADWALL (CH-FW-0)(DIA= 36 IN) EA 2.000 2.000 5,900.000 11,800.00 0467 SET (TY II)(24 IN)(RCP)(3:1)(C) EA 1.000 1.000 760.000 760.00 0467 SET (TY II)(30 IN)(RCP)(3:1)(C) EA 1.000 1.000 1,300.000 1,300.00 0467 SET (TY II)(30 IN)(RCP)(4:1)(C) EA 1.000 1.000 1,500.000 1,500.00 0467 SET (TY II)(24 IN)(RCP)(6:1)(C) EA 1.000 1.000 980.000 980.00 0496 REMOV STR (INLET) EA 1.000 1.000 500.000 500.00 0496 REMOV STR (SET) EA 1.000 1.000 500.000 500.00 0496 REMOV STR (PIPE) EA 4.000 4.000 500.000 2,000.00 0500 MOBILIZATION LS 1.000 1.000 29,632.860 29,632.86 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 5,897.230 11,794.46 0506 ROCK FILTER DAMS (INSTALL) (TY 1) LF 36.000 36.000 35.000 1,260.00 0506 TEMPORARY SEDIMENT CONTROL FENCE LF 235.000 240.000 3.000 720.00 0506 SANDBAGS FOR EROSION CONTROL (6 IN) LF 32.000 34.000 8.000 272.00 0508 CONSTRUCTING DETOURS EA 4.000 4.000 8,500.000 34,000.00 0552 WIRE FENCE (TY A) LF 90.000 75.000 25.000 1,875.00 0 SUBTOTAL BID ITEMS $ 211,160.04 0 CONTRACT TOTAL ALL ITEMS $ 211,160.04 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7111701 MGR.NO. 050 PAGE 001 CONT 6219 SEC 34 JOB 001 RES ENGR LAYWELL, BLANE PROJ RMC - 621934001 HWY FM0485 3303 N TRAVIS CAMERON CNTY MILAM DIST 17 CONTRACT PRICE $ 219,328.56 REPORT DATE 06/12/2012 14.57.22 CONTRACTOR RAY FARIS, INC. 643 EST PERIOD FEB 07,2012 TO MAY 31,2012 EST NO 004 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 166 RMC - 621934001 6219-34-001 211,160.04 .00 211,160.04 .00 .00 211,160.04 152,534.26 58,625.78 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 211,160.04 .00 211,160.04 .00 .00 211,160.04 152,534.26 58,625.78 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7111701 MGR.NO. 050 PAGE 001 CONT 6219 SEC 34 JOB 001 RES ENGR LAYWELL, BLANE PROJ RMC - 621934001 HWY FM0485 3303 N TRAVIS CAMERON CNTY MILAM DIST 17 CONTRACT PRICE $ 219,328.56 REPORT DATE 06/12/2012 14.57.23 CONTRACTOR RAY FARIS, INC. 643 EST PERIOD FEB 07,2012 TO MAY 31,2012 EST NO 004 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6219-34-001 RMC - 621934001 17 FM0485 MILAM -LIMITS - VARIOUS VARIOUS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0100 PREPARING ROW STA 3.000 1.000 1,900.000 1,900.00 75 0158 SPEC EXCAV WORK (BACKHOE) HR 12.000 3.000 50.000 150.00 80 0158 SPEC EXCAV WORK (HYD HR 9.000 3.000 135.000 405.00 EXCAVATOR) 85 0164 STRAW/HAY MLCH SY 261.000 355.556 3.840 1,365.34 SEED(PERM)(RURAL)(SANDY) 95 0400 CEM STABIL BKFL CY 290.000 87.000 80.000 6,960.00 100 0400 CUT & RESTORING PAV SY 54.000 26.000 60.000 1,560.00 105 0401 FLOWABLE BACKFILL CY 33.000 23.000 78.000 1,794.00 110 0402 TRENCH EXCAVATION PROTECTION LF 230.000 150.000 5.000 750.00 115 0403 TEMPORARY SPL SHORING SF 1,207.000 494.000 20.000 9,880.00 120 0432 RIPRAP (CONC)(4 IN) CY 10.000 10.000 350.000 3,500.00 125 0432 RIPRAP (STONE PROTECTION)(15 CY 44.000 14.000 95.000 1,330.00 IN) 140 0464 RC PIPE (CL III)(24 IN) LF 99.000 52.000 95.000 4,940.00 150 0464 RC PIPE (CL III)(36 IN) LF 44.000 17.000 87.000 1,479.00 160 0465 MANH (COMPL)(JUNCT BOX)(TY EA 2.000 1.000 3,300.000 3,300.00 M) 165 0466 HEADWALL (CH-FW-0)(DIA= 36 EA 2.000 2.000 5,900.000 11,800.00 IN) 180 0467 SET (TY II)(30 EA 1.000 1.000 1,500.000 1,500.00 IN)(RCP)(4:1)(C) 200 0496 REMOV STR (PIPE) EA 4.000 1.000 500.000 500.00 205 0500 MOBILIZATION LS 1.000 0.260 29,632.860 7,704.54 215 0506 ROCK FILTER DAMS (INSTALL) LF 36.000 24.000 35.000 840.00 (TY 1) 230 0506 TEMPORARY SEDIMENT CONTROL LF 235.000 105.000 3.000 315.00 FENCE 245 0552 WIRE FENCE (TY A) LF 90.000 75.000 25.000 1,875.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 63,847.88 0 TOTAL AMOUNT WORK DONE TO DATE - $ 211,160.04