1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 9091710 MGR.NO. 050 PAGE 001 CONT 6195 SEC 28 JOB 001 RES ENGR HERZOG,DERROL PROJ BPM - 619528001 HWY FM0050 1821_SH_105 BRENHAM CNTY WASHINGTON DIST 17 CONTRACT PRICE $ 69,985.00 REPORT DATE 01/11/2010 15.48.19 CONTRACTOR OCC CONSTRUCTION CORPORATION 13988 EST PERIOD OCT 23,2009 TO DEC 04,2009 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 23, 2009 TIME COMPUTED FROM OCT 30, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 24 39 16 23 BROUGHT FORWARD ADDL DAYS GRANTED = 0 DEC 09 1 1 WORK COMPLETED/PUNCH LIST TOTAL DAYS ALLOWED = 24 2 1 PUNCH LIST DATE WORK COMPLETED 12/04/09 3 1 PUNCH LIST DAYS CHARGED TO DATE = 16 4 1 WORK ACCEPTED ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 425 0 LIQUIDATED DAMAGES 0 DAYS AT $ 425 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 43 16 27 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED/PUNCH LIST 2 PUNCH LIST 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 9091710 MGR.NO. 050 PAGE 001 CONT 6195 SEC 28 JOB 001 RES ENGR HERZOG,DERROL PROJ BPM - 619528001 HWY FM0050 1821_SH_105 BRENHAM CNTY WASHINGTON DIST 17 CONTRACT PRICE $ 69,985.00 REPORT DATE 01/11/2010 15.48.19 CONTRACTOR OCC CONSTRUCTION CORPORATION 13988 EST PERIOD OCT 23,2009 TO DEC 04,2009 EST NO 003 & FINAL DIST. 17 COUNTY WASHINGTON CONTROL 6195-28-001 PROJECT BPM - 619528001 HIGHWAY FM0050 0LIMITS- AT PENN AND LITTLE ROCKY CREEK AT PENN AND LITTLE ROCKY CREEK 0TYPE OF WORK- REPAIR SCOUR DAMAGE UNDER BRIDGES 0 0005 PREPARED_BY BRYAN_DISTRICT_BRIDGE_OFFICE 0 0055 SCOUR_REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0110 EXCAVATION (CHANNEL) CY 205.000 204.978 30.000 6,149.34 0065 0432 RIPRAP (STONE PROTECTION)(18 IN) CY 465.000 464.800 72.000 33,465.60 0070 0432 BEDDING MATERIAL (VAR DEPTH) CY 245.000 244.970 75.000 18,372.75 0075 0500 MOBILIZATION LS 1.000 1.000 5,000.000 5,000.00 0080 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 2,500.000 5,000.00 0085 0506 ROCK FILTER DAMS (INSTALL) (TY 3) LF 66.000 78.000 30.000 2,340.00 0 SUBTOTAL BID ITEMS $ 70,327.69 0 TOTAL AMOUNT WORK DONE SCOUR_REPAIR $ 70,327.69 0 TOTAL AMOUNT WORK DONE CONTROL 6195-28-001 $ 70,327.69 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 9091710 MGR.NO. 050 PAGE 001 CONT 6195 SEC 28 JOB 001 RES ENGR HERZOG,DERROL PROJ BPM - 619528001 HWY FM0050 1821_SH_105 BRENHAM CNTY WASHINGTON DIST 17 CONTRACT PRICE $ 69,985.00 REPORT DATE 01/11/2010 15.48.20 CONTRACTOR OCC CONSTRUCTION CORPORATION 13988 EST PERIOD OCT 23,2009 TO DEC 04,2009 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - AT PENN AND LITTLE ROCKY CREEK 0 AT PENN AND LITTLE ROCKY CREEK DATE WORK BEGAN OCT 23, 2009 WORKING DAYS USED 16 PERCENT COMPLETE 100.00 PERCENT TIME USED 66.60 DATE COMPLETED DEC 4 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6195-28-001 BPM - 619528001 17 FM0050 WASHINGTON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0110 EXCAVATION (CHANNEL) CY 205.000 204.978 30.000 6,149.34 0432 RIPRAP (STONE PROTECTION)(18 IN) CY 465.000 464.800 72.000 33,465.60 0432 BEDDING MATERIAL (VAR DEPTH) CY 245.000 244.970 75.000 18,372.75 0500 MOBILIZATION LS 1.000 1.000 5,000.000 5,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 2,500.000 5,000.00 0506 ROCK FILTER DAMS (INSTALL) (TY 3) LF 66.000 78.000 30.000 2,340.00 0 SUBTOTAL BID ITEMS $ 70,327.69 0 CONTRACT TOTAL ALL ITEMS $ 70,327.69 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 9091710 MGR.NO. 050 PAGE 001 CONT 6195 SEC 28 JOB 001 RES ENGR HERZOG,DERROL PROJ BPM - 619528001 HWY FM0050 1821_SH_105 BRENHAM CNTY WASHINGTON DIST 17 CONTRACT PRICE $ 69,985.00 REPORT DATE 01/11/2010 15.48.20 CONTRACTOR OCC CONSTRUCTION CORPORATION 13988 EST PERIOD OCT 23,2009 TO DEC 04,2009 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 239 BPM - 619528001 6195-28-001 70,327.69 .00 70,327.69 .00 .00 70,327.69 67,327.69 3,000.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 70,327.69 .00 70,327.69 .00 .00 70,327.69 67,327.69 3,000.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 9091710 MGR.NO. 050 PAGE 001 CONT 6195 SEC 28 JOB 001 RES ENGR HERZOG,DERROL PROJ BPM - 619528001 HWY FM0050 1821_SH_105 BRENHAM CNTY WASHINGTON DIST 17 CONTRACT PRICE $ 69,985.00 REPORT DATE 01/11/2010 15.48.20 CONTRACTOR OCC CONSTRUCTION CORPORATION 13988 EST PERIOD OCT 23,2009 TO DEC 04,2009 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6195-28-001 BPM - 619528001 17 FM0050 WASHINGTON -LIMITS - AT PENN AND LITTLE ROCKY CREEK AT PENN AND LITTLE ROCKY CREEK LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 75 0500 MOBILIZATION LS 1.000 0.100 5,000.000 500.00 80 0502 BARRICADES, SIGNS AND MO 2.000 1.000 2,500.000 2,500.00 TRAFFIC HANDLING --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 3,000.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 70,327.69