1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6091701 MGR.NO. 002 PAGE 001 CONT 6193 SEC 80 JOB 001 RES ENGR NORWOOD, WALTER PROJ RMC - 619380001 HWY FM2347 2102 TABOR ROAD BRYAN CNTY BRAZOS DIST 17 CONTRACT PRICE $ 14,680.00 REPORT DATE 11/02/2009 16.27.28 CONTRACTOR DURACO 14333 EST PERIOD AUG 08,2009 TO AUG 17,2009 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 08, 2009 TIME COMPUTED FROM AUG 11, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 2 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 09 TOTAL DAYS ALLOWED = 2 DATE WORK COMPLETED 08/17/09 DAYS CHARGED TO DATE = 2 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 425 0 LIQUIDATED DAMAGES 8 1 MOBILIZATION 0 DAYS AT $ 425 PER DAY 9 1 MOBILIZATION TOTAL = $ .00 10 1 MOBILIZATION 11 1 DAY CREDIT PER AE CERTIFIED AS CORRECT AND 12 1 UNAVAILABILITY OF MATERIAL ONE COPY HAS BEEN GIVEN 13 1 RAIN TO THE CONTRACTOR 14 1 DAY CREDIT PER AE 15 1 16 1 SUNDAY ---------------------------- 17 1 WORK COMPLETED AND ACCEPTED AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 10 2 8 0 SATURDAY 1 SUNDAY 0 HOLIDAY 3 MOBILIZATION 2 DAY CREDIT PER AE 1 UNAVAILABILITY OF MATERIAL 1 RAIN 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6091701 MGR.NO. 002 PAGE 001 CONT 6193 SEC 80 JOB 001 RES ENGR NORWOOD, WALTER PROJ RMC - 619380001 HWY FM2347 2102 TABOR ROAD BRYAN CNTY BRAZOS DIST 17 CONTRACT PRICE $ 14,680.00 REPORT DATE 11/02/2009 16.27.29 CONTRACTOR DURACO 14333 EST PERIOD AUG 08,2009 TO AUG 17,2009 EST NO 002 & FINAL DIST. 17 COUNTY BRAZOS CONTROL 6193-80-001 PROJECT RMC - 619380001 HIGHWAY FM2347 0LIMITS- RM 426+0.00 RM 426+0.00 0TYPE OF WORK- REPLACE DAMAGED CURB INLET 0 0005 PREPARED BY BRYAN DISTRICT MAINTENANCE 0 0055 INSTALL INLET NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0104 REMOVING CONC (SIDEWALKS) SY 17.000 17.000 23.000 391.00 0065 0104 REMOVING CONC (CURB AND GUTTER) LF 11.000 11.000 52.000 572.00 0070 0276 CM TRT(PT MX)(CL L)(TY A)(GR 1)(FN POS) CY 14.000 14.000 114.000 1,596.00 0075 0464 RC PIPE (CL III)(24 IN) LF 15.000 15.000 45.000 675.00 0080 0465 INLET (COMPL)(TY C) EA 1.000 1.000 3,200.000 3,200.00 0085 0496 REMOV STR (INLET) EA 1.000 1.000 375.000 375.00 0090 0496 REMOV STR (PIPE) LF 9.000 9.000 23.000 207.00 0095 0500 MOBILIZATION LS 1.000 1.000 1,654.000 1,654.00 0100 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 1,000.000 1,000.00 0105 0529 CONC CURB & GUTTER (TY II) LF 16.000 16.000 180.000 2,880.00 0110 0531 CONC SIDEWLKS (4") SY 17.000 17.000 99.000 1,683.00 0115 6834 PORTABLE CHANGEABLE MESSAGE SIGN DAY 5.000 5.000 89.400 447.00 0 SUBTOTAL BID ITEMS $ 14,680.00 0 TOTAL AMOUNT WORK DONE INSTALL INLET $ 14,680.00 0 TOTAL AMOUNT WORK DONE CONTROL 6193-80-001 $ 14,680.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6091701 MGR.NO. 002 PAGE 001 CONT 6193 SEC 80 JOB 001 RES ENGR NORWOOD, WALTER PROJ RMC - 619380001 HWY FM2347 2102 TABOR ROAD BRYAN CNTY BRAZOS DIST 17 CONTRACT PRICE $ 14,680.00 REPORT DATE 11/02/2009 16.27.29 CONTRACTOR DURACO 14333 EST PERIOD AUG 08,2009 TO AUG 17,2009 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - RM 426+0.00 0 RM 426+0.00 DATE WORK BEGAN AUG 8 , 2009 WORKING DAYS USED 2 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED AUG 17 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6193-80-001 RMC - 619380001 17 FM2347 BRAZOS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0104 REMOVING CONC (SIDEWALKS) SY 17.000 17.000 23.000 391.00 0104 REMOVING CONC (CURB AND GUTTER) LF 11.000 11.000 52.000 572.00 0276 CM TRT(PT MX)(CL L)(TY A)(GR 1)(FN POS) CY 14.000 14.000 114.000 1,596.00 0464 RC PIPE (CL III)(24 IN) LF 15.000 15.000 45.000 675.00 0465 INLET (COMPL)(TY C) EA 1.000 1.000 3,200.000 3,200.00 0496 REMOV STR (INLET) EA 1.000 1.000 375.000 375.00 0496 REMOV STR (PIPE) LF 9.000 9.000 23.000 207.00 0500 MOBILIZATION LS 1.000 1.000 1,654.000 1,654.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 1,000.000 1,000.00 0529 CONC CURB & GUTTER (TY II) LF 16.000 16.000 180.000 2,880.00 0531 CONC SIDEWLKS (4") SY 17.000 17.000 99.000 1,683.00 6834 PORTABLE CHANGEABLE MESSAGE SIGN DAY 5.000 5.000 89.400 447.00 0 SUBTOTAL BID ITEMS $ 14,680.00 0 CONTRACT TOTAL ALL ITEMS $ 14,680.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6091701 MGR.NO. 002 PAGE 001 CONT 6193 SEC 80 JOB 001 RES ENGR NORWOOD, WALTER PROJ RMC - 619380001 HWY FM2347 2102 TABOR ROAD BRYAN CNTY BRAZOS DIST 17 CONTRACT PRICE $ 14,680.00 REPORT DATE 11/02/2009 16.27.29 CONTRACTOR DURACO 14333 EST PERIOD AUG 08,2009 TO AUG 17,2009 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 21 RMC - 619380001 6193-80-001 14,680.00 .00 14,680.00 .00 .00 14,680.00 14,680.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 14,680.00 .00 14,680.00 .00 .00 14,680.00 14,680.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6091701 MGR.NO. 002 PAGE 001 CONT 6193 SEC 80 JOB 001 RES ENGR NORWOOD, WALTER PROJ RMC - 619380001 HWY FM2347 2102 TABOR ROAD BRYAN CNTY BRAZOS DIST 17 CONTRACT PRICE $ 14,680.00 REPORT DATE 11/02/2009 16.27.29 CONTRACTOR DURACO 14333 EST PERIOD AUG 08,2009 TO AUG 17,2009 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6193-80-001 RMC - 619380001 17 FM2347 BRAZOS -LIMITS - RM 426+0.00 RM 426+0.00 - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 14,680.00