1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 3091710 MGR.NO. 006 PAGE 001 CONT 6191 SEC 68 JOB 001 RES ENGR LANGFORD, HOWARD PROJ RMC - 619168001 HWY SH0075 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 144,227.16 REPORT DATE 01/12/2010 07.50.53 CONTRACTOR LAWRENCE W. SIMS 7052 EST PERIOD MAY 26,2009 TO NOV 16,2009 EST NO 008 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 26, 2009 TIME COMPUTED FROM MAY 26, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 65 159 3 156 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 09 1 1 SUNDAY TOTAL DAYS ALLOWED = 65 2 1 TIME CHARGES BEGIN DATE WORK COMPLETED 11/16/09 3 1 DAYS CHARGED TO DATE = 15 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 425 6 1 7 1 LIQUIDATED DAMAGES 8 1 SUNDAY 0 DAYS AT $ 425 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 SUNDAY 16 1 WORK COMPLETED AND ACCEPTED ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 175 15 160 0 SATURDAY 3 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 3091710 MGR.NO. 006 PAGE 001 CONT 6191 SEC 68 JOB 001 RES ENGR LANGFORD, HOWARD PROJ RMC - 619168001 HWY SH0075 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 144,227.16 REPORT DATE 01/12/2010 07.50.54 CONTRACTOR LAWRENCE W. SIMS 7052 EST PERIOD MAY 26,2009 TO NOV 16,2009 EST NO 008 & FINAL DIST. 17 COUNTY FREESTONE CONTROL 6191-68-001 PROJECT RMC - 619168001 HIGHWAY SH0075 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- ROADSIDE MOWING 0 0005 PREPARED BY BRYAN DISTRICT MAINTENANCE 0 0055 ROADSIDE MOWING NET LENGTH340.700 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 8,514.000 8,514.000 16.940 144,227.16 0 SUBTOTAL BID ITEMS $ 144,227.16 0 TOTAL AMOUNT WORK DONE ROADSIDE MOWING $ 144,227.16 0 TOTAL AMOUNT WORK DONE CONTROL 6191-68-001 $ 144,227.16 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 3091710 MGR.NO. 006 PAGE 001 CONT 6191 SEC 68 JOB 001 RES ENGR LANGFORD, HOWARD PROJ RMC - 619168001 HWY SH0075 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 144,227.16 REPORT DATE 01/12/2010 07.50.54 CONTRACTOR LAWRENCE W. SIMS 7052 EST PERIOD MAY 26,2009 TO NOV 16,2009 EST NO 008 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN MAY 26, 2009 WORKING DAYS USED 15 PERCENT COMPLETE 100.00 PERCENT TIME USED 23.00 DATE COMPLETED NOV 16 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6191-68-001 RMC - 619168001 17 SH0075 FREESTONE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 8,514.000 8,514.000 16.940 144,227.16 0 SUBTOTAL BID ITEMS $ 144,227.16 0 CONTRACT TOTAL ALL ITEMS $ 144,227.16 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 3091710 MGR.NO. 006 PAGE 001 CONT 6191 SEC 68 JOB 001 RES ENGR LANGFORD, HOWARD PROJ RMC - 619168001 HWY SH0075 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 144,227.16 REPORT DATE 01/12/2010 07.50.54 CONTRACTOR LAWRENCE W. SIMS 7052 EST PERIOD MAY 26,2009 TO NOV 16,2009 EST NO 008 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 82 RMC - 619168001 6191-68-001 144,227.16 .00 144,227.16 .00 .00 144,227.16 144,227.16 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 144,227.16 .00 144,227.16 .00 .00 144,227.16 144,227.16 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 3091710 MGR.NO. 006 PAGE 001 CONT 6191 SEC 68 JOB 001 RES ENGR LANGFORD, HOWARD PROJ RMC - 619168001 HWY SH0075 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 144,227.16 REPORT DATE 01/12/2010 07.50.54 CONTRACTOR LAWRENCE W. SIMS 7052 EST PERIOD MAY 26,2009 TO NOV 16,2009 EST NO 008 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6191-68-001 RMC - 619168001 17 SH0075 FREESTONE -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 144,227.16