1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2091710 MGR.NO. 007 PAGE 001 CONT 6190 SEC 98 JOB 001 RES ENGR JABLONOWSKI, MIKE PROJ RMC - 619098001 HWY US0079 1183 N. MARKET ST. HEARNE CNTY ROBERTSON DIST 17 CONTRACT PRICE $ 17,821.35 REPORT DATE 07/10/2009 08.46.56 CONTRACTOR JASCO 13481 EST PERIOD APR 30,2009 TO MAY 05,2009 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 30, 2009 TIME COMPUTED FROM MAY 01, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 150 1 0 1 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAY 09 1 1 TOTAL DAYS ALLOWED = 150 2 1 DATE WORK COMPLETED 05/05/09 3 1 DAYS CHARGED TO DATE = 4 4 1 WORK COMPLETED ASSESSED LIQ DAMAGES = 0 5 1 WORK ACCEPTED LIQ DAMAGE RATE $ 400 0 LIQUIDATED DAMAGES 0 DAYS AT $ 400 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 6 4 2 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2091710 MGR.NO. 007 PAGE 001 CONT 6190 SEC 98 JOB 001 RES ENGR JABLONOWSKI, MIKE PROJ RMC - 619098001 HWY US0079 1183 N. MARKET ST. HEARNE CNTY ROBERTSON DIST 17 CONTRACT PRICE $ 17,821.35 REPORT DATE 07/10/2009 08.46.57 CONTRACTOR JASCO 13481 EST PERIOD APR 30,2009 TO MAY 05,2009 EST NO 003 & FINAL DIST. 17 COUNTY ROBERTSON CONTROL 6190-98-001 PROJECT RMC - 619098001 HIGHWAY US0079 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- INSTALL/REMOVAL RPMS 0 0005 PREPARED BY MICHAEL A. JEDLICKA, P.E. 0 0055 REMOV/INSTALL RPMS NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0672 REFL PAV MRKR TY I-C EA 574.000 196.000 2.150 421.40 0065 0672 REFL PAV MRKR TY II-A-A EA 7,715.000 7,788.000 2.150 16,744.20 0 SUBTOTAL BID ITEMS $ 17,165.60 0 TOTAL AMOUNT WORK DONE REMOV/INSTALL RPMS $ 17,165.60 0 TOTAL AMOUNT WORK DONE CONTROL 6190-98-001 $ 17,165.60 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2091710 MGR.NO. 007 PAGE 001 CONT 6190 SEC 98 JOB 001 RES ENGR JABLONOWSKI, MIKE PROJ RMC - 619098001 HWY US0079 1183 N. MARKET ST. HEARNE CNTY ROBERTSON DIST 17 CONTRACT PRICE $ 17,821.35 REPORT DATE 07/10/2009 08.46.57 CONTRACTOR JASCO 13481 EST PERIOD APR 30,2009 TO MAY 05,2009 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN APR 30, 2009 WORKING DAYS USED 4 PERCENT COMPLETE 100.00 PERCENT TIME USED 2.60 DATE COMPLETED MAY 5 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6190-98-001 RMC - 619098001 17 US0079 ROBERTSON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0672 REFL PAV MRKR TY I-C EA 574.000 196.000 2.150 421.40 0672 REFL PAV MRKR TY II-A-A EA 7,715.000 7,788.000 2.150 16,744.20 0 SUBTOTAL BID ITEMS $ 17,165.60 0 CONTRACT TOTAL ALL ITEMS $ 17,165.60 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2091710 MGR.NO. 007 PAGE 001 CONT 6190 SEC 98 JOB 001 RES ENGR JABLONOWSKI, MIKE PROJ RMC - 619098001 HWY US0079 1183 N. MARKET ST. HEARNE CNTY ROBERTSON DIST 17 CONTRACT PRICE $ 17,821.35 REPORT DATE 07/10/2009 08.46.57 CONTRACTOR JASCO 13481 EST PERIOD APR 30,2009 TO MAY 05,2009 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 198 RMC - 619098001 6190-98-001 17,165.60 .00 17,165.60 .00 .00 17,165.60 17,165.60 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 17,165.60 .00 17,165.60 .00 .00 17,165.60 17,165.60 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2091710 MGR.NO. 007 PAGE 001 CONT 6190 SEC 98 JOB 001 RES ENGR JABLONOWSKI, MIKE PROJ RMC - 619098001 HWY US0079 1183 N. MARKET ST. HEARNE CNTY ROBERTSON DIST 17 CONTRACT PRICE $ 17,821.35 REPORT DATE 07/10/2009 08.46.57 CONTRACTOR JASCO 13481 EST PERIOD APR 30,2009 TO MAY 05,2009 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6190-98-001 RMC - 619098001 17 US0079 ROBERTSON -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 17,165.60