1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2091704 MGR.NO. 004 PAGE 001 CONT 6190 SEC 92 JOB 001 RES ENGR PAVLAS, ROBERT PROJ RMC - 619092001 HWY SH0036 2157 SH36 SOUTH CALDWELL CNTY BURLESON DIST 17 CONTRACT PRICE $ 30,829.20 REPORT DATE 09/09/2009 14.00.26 CONTRACTOR JASCO 13481 EST PERIOD JUL 14,2009 TO AUG 20,2009 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 14, 2009 TIME COMPUTED FROM JUL 14, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 150 18 18 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 09 1 1 TOTAL DAYS ALLOWED = 150 2 1 DATE WORK COMPLETED 08/20/09 3 1 DAYS CHARGED TO DATE = 37 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 400 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 400 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 PROJECT COMPLETED AND ACCEPTED - - - - ----- ----- ----- 38 37 1 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 PROJECT COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2091704 MGR.NO. 004 PAGE 001 CONT 6190 SEC 92 JOB 001 RES ENGR PAVLAS, ROBERT PROJ RMC - 619092001 HWY SH0036 2157 SH36 SOUTH CALDWELL CNTY BURLESON DIST 17 CONTRACT PRICE $ 30,829.20 REPORT DATE 09/09/2009 14.00.26 CONTRACTOR JASCO 13481 EST PERIOD JUL 14,2009 TO AUG 20,2009 EST NO 003 & FINAL DIST. 17 COUNTY BURLESON CONTROL 6190-92-001 PROJECT RMC - 619092001 HIGHWAY SH0036 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- INSTALL/REMOVAL RPM'S 0 0005 PREPARED BY MICHAEL A. JEDLICKA, P.E. 0 0055 REMOVE/INSTALL RPMS NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0672 REFL PAV MRKR TY I-C EA 750.000 1,014.000 2.300 2,332.20 0060 0672 ADJ EST QUANTITY TO DATE 955.000 0065 0672 REFL PAV MRKR TY II-A-A EA 12,654.000 12,659.000 2.300 29,115.70 0 SUBTOTAL BID ITEMS $ 31,447.90 0 TOTAL AMOUNT WORK DONE REMOVE/INSTALL RPMS $ 31,447.90 0 TOTAL AMOUNT WORK DONE CONTROL 6190-92-001 $ 31,447.90 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2091704 MGR.NO. 004 PAGE 001 CONT 6190 SEC 92 JOB 001 RES ENGR PAVLAS, ROBERT PROJ RMC - 619092001 HWY SH0036 2157 SH36 SOUTH CALDWELL CNTY BURLESON DIST 17 CONTRACT PRICE $ 30,829.20 REPORT DATE 09/09/2009 14.00.26 CONTRACTOR JASCO 13481 EST PERIOD JUL 14,2009 TO AUG 20,2009 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN JUL 14, 2009 WORKING DAYS USED 37 PERCENT COMPLETE 100.00 PERCENT TIME USED 24.60 DATE COMPLETED AUG 20 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6190-92-001 RMC - 619092001 17 SH0036 BURLESON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0672 REFL PAV MRKR TY I-C EA 750.000 1,014.000 2.300 2,332.20 0672 ADJ EST QUANTITY TO DATE 955.000 0672 REFL PAV MRKR TY II-A-A EA 12,654.000 12,659.000 2.300 29,115.70 0 SUBTOTAL BID ITEMS $ 31,447.90 0 CONTRACT TOTAL ALL ITEMS $ 31,447.90 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2091704 MGR.NO. 004 PAGE 001 CONT 6190 SEC 92 JOB 001 RES ENGR PAVLAS, ROBERT PROJ RMC - 619092001 HWY SH0036 2157 SH36 SOUTH CALDWELL CNTY BURLESON DIST 17 CONTRACT PRICE $ 30,829.20 REPORT DATE 09/09/2009 14.00.26 CONTRACTOR JASCO 13481 EST PERIOD JUL 14,2009 TO AUG 20,2009 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 26 RMC - 619092001 6190-92-001 31,447.90 .00 31,447.90 .00 .00 31,447.90 31,447.90 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 31,447.90 .00 31,447.90 .00 .00 31,447.90 31,447.90 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2091704 MGR.NO. 004 PAGE 001 CONT 6190 SEC 92 JOB 001 RES ENGR PAVLAS, ROBERT PROJ RMC - 619092001 HWY SH0036 2157 SH36 SOUTH CALDWELL CNTY BURLESON DIST 17 CONTRACT PRICE $ 30,829.20 REPORT DATE 09/09/2009 14.00.26 CONTRACTOR JASCO 13481 EST PERIOD JUL 14,2009 TO AUG 20,2009 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6190-92-001 RMC - 619092001 17 SH0036 BURLESON -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 31,447.90