1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1091743 MGR.NO. 002 PAGE 001 CONT 6189 SEC 57 JOB 001 RES ENGR NORWOOD, WALT PROJ SUP - 618957001 HWY FM0974 2102 TABOR RD. BRYAN CNTY BRAZOS DIST 17 CONTRACT PRICE $ 64,849.05 REPORT DATE 11/09/2009 17.38.39 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 009 RUCON, INC. 10168 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN FEB 03, 2009 TIME COMPUTED FROM FEB 03, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 240 240 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 09 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 271 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 271 271 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1091743 MGR.NO. 002 PAGE 001 CONT 6189 SEC 57 JOB 001 RES ENGR NORWOOD, WALT PROJ SUP - 618957001 HWY FM0974 2102 TABOR RD. BRYAN CNTY BRAZOS DIST 17 CONTRACT PRICE $ 64,849.05 REPORT DATE 11/09/2009 17.38.39 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 009 RUCON, INC. 10168 DIST. 17 COUNTY BRAZOS CONTROL 6189-57-001 PROJECT SUP - 618957001 HIGHWAY FM0974 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- REMOVAL & DISPOSAL OF SCRAP WHOLE TIRES 0 0050 SCRAP RUBBER PICKUP FOR BRAZOS COUN NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY DISTRICT MAINTENANCE 0 0075 0735 DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES) MI 2,205.000 1,666.000 29.410 48,997.06 0 SUBTOTAL BID ITEMS $ 48,997.06 0 TOTAL AMOUNT WORK DONE SCRAP RUBBER PICKUP FOR BRAZOS COUN $ 48,997.06 0 TOTAL AMOUNT WORK DONE CONTROL 6189-57-001 $ 48,997.06 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1091743 MGR.NO. 002 PAGE 001 CONT 6189 SEC 57 JOB 001 RES ENGR NORWOOD, WALT PROJ SUP - 618957001 HWY FM0974 2102 TABOR RD. BRYAN CNTY BRAZOS DIST 17 CONTRACT PRICE $ 64,849.05 REPORT DATE 11/09/2009 17.38.39 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 009 RUCON, INC. 10168 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN FEB 3 , 2009 WORKING DAYS USED 271 PERCENT COMPLETE 75.55 PERCENT TIME USED 74.20 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6189-57-001 SUP - 618957001 17 FM0974 BRAZOS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0735 DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES) MI 2,205.000 1,666.000 29.410 48,997.06 0 SUBTOTAL BID ITEMS $ 48,997.06 0 CONTRACT TOTAL ALL ITEMS $ 48,997.06 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1091743 MGR.NO. 002 PAGE 001 CONT 6189 SEC 57 JOB 001 RES ENGR NORWOOD, WALT PROJ SUP - 618957001 HWY FM0974 2102 TABOR RD. BRYAN CNTY BRAZOS DIST 17 CONTRACT PRICE $ 64,849.05 REPORT DATE 11/09/2009 17.38.39 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 009 RUCON, INC. 10168 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 21 SUP - 618957001 6189-57-001 48,997.06 .00 48,997.06 .00 .00 48,997.06 43,232.70 5,764.36 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 48,997.06 .00 48,997.06 .00 .00 48,997.06 43,232.70 5,764.36 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1091743 MGR.NO. 002 PAGE 001 CONT 6189 SEC 57 JOB 001 RES ENGR NORWOOD, WALT PROJ SUP - 618957001 HWY FM0974 2102 TABOR RD. BRYAN CNTY BRAZOS DIST 17 CONTRACT PRICE $ 64,849.05 REPORT DATE 11/09/2009 17.38.39 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 009 RUCON, INC. 10168 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6189-57-001 SUP - 618957001 17 FM0974 BRAZOS -LIMITS - VARIOUS VARIOUS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 75 0735 DEBRIS REMOVAL (CNTR MI 2,205.000 196.000 29.410 5,764.36 MEDIANS/MAINLANES) --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 5,764.36 0 TOTAL AMOUNT WORK DONE TO DATE - $ 48,997.06