1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6081713 MGR.NO. 005 PAGE 001 CONT 6182 SEC 48 JOB 001 RES ENGR LAYWELL, BLANE PROJ SUP - 618248001 HWY FM0485 P.O. BOX 468 CAMERON CNTY MILAM DIST 17 CONTRACT PRICE $ 27,510.00 REPORT DATE 06/18/2009 14.29.11 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUL 07,2008 TO JUN 17,2009 EST NO 012 & FINAL RUCON, INC. 10168 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 07, 2008 TIME COMPUTED FROM JUL 07, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 329 329 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUN 09 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 06/17/09 3 1 DAYS CHARGED TO DATE = 346 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 WORK COMPLETED AND ACCEPTED AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 346 346 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6081713 MGR.NO. 005 PAGE 001 CONT 6182 SEC 48 JOB 001 RES ENGR LAYWELL, BLANE PROJ SUP - 618248001 HWY FM0485 P.O. BOX 468 CAMERON CNTY MILAM DIST 17 CONTRACT PRICE $ 27,510.00 REPORT DATE 06/18/2009 14.29.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUL 07,2008 TO JUN 17,2009 EST NO 012 & FINAL RUCON, INC. 10168 DIST. 17 COUNTY MILAM CONTROL 6182-48-001 PROJECT SUP - 618248001 HIGHWAY FM0485 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- DELINEATOR 0 0050 PREPARED BY DISTRICT MAINTENANCE NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 REMOVE AND REPLACE DELINEATORS 0 0075 7275 INSTL DELIN & OBJECT MARKERS ASSMS EA 917.000 917.000 30.000 27,510.00 0 SUBTOTAL BID ITEMS $ 27,510.00 0 TOTAL AMOUNT WORK DONE PREPARED BY DISTRICT MAINTENANCE $ 27,510.00 0 TOTAL AMOUNT WORK DONE CONTROL 6182-48-001 $ 27,510.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6081713 MGR.NO. 005 PAGE 001 CONT 6182 SEC 48 JOB 001 RES ENGR LAYWELL, BLANE PROJ SUP - 618248001 HWY FM0485 P.O. BOX 468 CAMERON CNTY MILAM DIST 17 CONTRACT PRICE $ 27,510.00 REPORT DATE 06/18/2009 14.29.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUL 07,2008 TO JUN 17,2009 EST NO 012 & FINAL RUCON, INC. 10168 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN JUL 7 , 2008 WORKING DAYS USED 346 PERCENT COMPLETE 100.00 PERCENT TIME USED 94.70 DATE COMPLETED JUN 17 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6182-48-001 SUP - 618248001 17 FM0485 MILAM - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -7275 INSTL DELIN & OBJECT MARKERS ASSMS EA 917.000 917.000 30.000 27,510.00 0 SUBTOTAL BID ITEMS $ 27,510.00 0 CONTRACT TOTAL ALL ITEMS $ 27,510.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6081713 MGR.NO. 005 PAGE 001 CONT 6182 SEC 48 JOB 001 RES ENGR LAYWELL, BLANE PROJ SUP - 618248001 HWY FM0485 P.O. BOX 468 CAMERON CNTY MILAM DIST 17 CONTRACT PRICE $ 27,510.00 REPORT DATE 06/18/2009 14.29.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUL 07,2008 TO JUN 17,2009 EST NO 012 & FINAL RUCON, INC. 10168 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 166 SUP - 618248001 6182-48-001 27,510.00 .00 27,510.00 .00 .00 27,510.00 27,510.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 27,510.00 .00 27,510.00 .00 .00 27,510.00 27,510.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6081713 MGR.NO. 005 PAGE 001 CONT 6182 SEC 48 JOB 001 RES ENGR LAYWELL, BLANE PROJ SUP - 618248001 HWY FM0485 P.O. BOX 468 CAMERON CNTY MILAM DIST 17 CONTRACT PRICE $ 27,510.00 REPORT DATE 06/18/2009 14.29.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUL 07,2008 TO JUN 17,2009 EST NO 012 & FINAL RUCON, INC. 10168 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6182-48-001 SUP - 618248001 17 FM0485 MILAM -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 27,510.00