1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 3081702 MGR.NO. 008 PAGE 001 CONT 6176 SEC 86 JOB 001 RES ENGR LANGFORD, HOWARD PROJ RMC - 617686001 HWY IH0045 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 106,939.97 REPORT DATE 10/15/2008 15.19.21 CONTRACTOR GIBSON & ASSOCIATES, INC. 3781 EST PERIOD JUN 16,2008 TO AUG 08,2008 EST NO 004 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 16, 2008 TIME COMPUTED FROM JUN 16, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 25 46 18 28 BROUGHT FORWARD ADDL DAYS GRANTED = 15 AUG 08 1 1 NO TIME CHARGE TOTAL DAYS ALLOWED = 40 2 1 SATURDAY DATE WORK COMPLETED 08/08/08 3 1 SUNDAY DAYS CHARGED TO DATE = 22 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 400 6 1 7 1 LIQUIDATED DAMAGES 8 1 WORK COMPLETED AND ACCEPTED 0 DAYS AT $ 400 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 54 22 32 1 SATURDAY 1 SUNDAY 0 HOLIDAY 1 NO TIME CHARGE 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 3081702 MGR.NO. 008 PAGE 001 CONT 6176 SEC 86 JOB 001 RES ENGR LANGFORD, HOWARD PROJ RMC - 617686001 HWY IH0045 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 106,939.97 REPORT DATE 10/15/2008 15.19.22 CONTRACTOR GIBSON & ASSOCIATES, INC. 3781 EST PERIOD JUN 16,2008 TO AUG 08,2008 EST NO 004 & FINAL DIST. 17 COUNTY FREESTONE CONTROL 6176-86-001 PROJECT RMC - 617686001 HIGHWAY IH0045 0LIMITS- CANEY CREEK BRIDGE BNSF RR BRIDGE 0TYPE OF WORK- BRIDGE JOINT REPAIR 0 0005 PREPARED BY DISTRICT BRIDGE 0 0055 BRIDGE JOINT REPAIR NET LENGTH 0.100 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0430 CL K CONC FOR EXT STR (SLAB) CY 8.700 25.246 4,600.000 116,131.60 0060 0430 ADJ EST QUANTITY TO DATE 20.700 0065 0454 ARMOR JOINT LF 175.886 332.897 31.000 10,319.81 0065 0454 ADJ EST QUANTITY TO DATE 319.886 0070 0454 JOINT SEALANT LF 282.500 364.501 27.000 9,841.53 0070 0454 ADJ EST QUANTITY TO DATE 360.500 0075 0500 MOBILIZATION LS 1.000 1.000 12,200.000 12,200.00 0076 9001*RE-MOBILIZATION (DEMOB/REMOB) LS 1.000 1.000 9,142.500 9,142.50 0080 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 3.000 9,300.000 27,900.00 0080 0502 ADJ EST QUANTITY TO DATE 3.000 0085 7380 ARMOR JOINT REPAIR LF 192.000 192.000 120.000 23,040.00 0 SUBTOTAL BID ITEMS $ 208,575.44 0 TOTAL AMOUNT WORK DONE BRIDGE JOINT REPAIR $ 208,575.44 0 TOTAL AMOUNT WORK DONE CONTROL 6176-86-001 $ 208,575.44 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 3081702 MGR.NO. 008 PAGE 001 CONT 6176 SEC 86 JOB 001 RES ENGR LANGFORD, HOWARD PROJ RMC - 617686001 HWY IH0045 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 106,939.97 REPORT DATE 10/15/2008 15.19.22 CONTRACTOR GIBSON & ASSOCIATES, INC. 3781 EST PERIOD JUN 16,2008 TO AUG 08,2008 EST NO 004 & FINAL 0*********************************************************************************************************************************** -LIMITS - CANEY CREEK BRIDGE 0 BNSF RR BRIDGE DATE WORK BEGAN JUN 16, 2008 WORKING DAYS USED 22 PERCENT COMPLETE 100.00 PERCENT TIME USED 55.00 DATE COMPLETED AUG 8 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6176-86-001 RMC - 617686001 17 IH0045 FREESTONE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0430 CL K CONC FOR EXT STR (SLAB) CY 8.700 25.246 4,600.000 116,131.60 0430 ADJ EST QUANTITY TO DATE 20.700 0454 ARMOR JOINT LF 175.886 332.897 31.000 10,319.81 0454 ADJ EST QUANTITY TO DATE 319.886 0454 JOINT SEALANT LF 282.500 364.501 27.000 9,841.53 0454 ADJ EST QUANTITY TO DATE 360.500 0500 MOBILIZATION LS 1.000 1.000 12,200.000 12,200.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 3.000 9,300.000 27,900.00 0502 ADJ EST QUANTITY TO DATE 3.000 7380 ARMOR JOINT REPAIR LF 192.000 192.000 120.000 23,040.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09001* RE-MOBILIZATION (DEMOB/REMOB) LS 1.000 1.000 9,142.500 9,142.50 0 SUBTOTAL BID ITEMS $ 208,575.44 0 CONTRACT TOTAL ALL ITEMS $ 208,575.44 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 3081702 MGR.NO. 008 PAGE 001 CONT 6176 SEC 86 JOB 001 RES ENGR LANGFORD, HOWARD PROJ RMC - 617686001 HWY IH0045 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 106,939.97 REPORT DATE 10/15/2008 15.19.22 CONTRACTOR GIBSON & ASSOCIATES, INC. 3781 EST PERIOD JUN 16,2008 TO AUG 08,2008 EST NO 004 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 82 RMC - 617686001 6176-86-001 208,575.44 .00 208,575.44 .00 .00 208,575.44 208,575.44 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 208,575.44 .00 208,575.44 .00 .00 208,575.44 208,575.44 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 3081702 MGR.NO. 008 PAGE 001 CONT 6176 SEC 86 JOB 001 RES ENGR LANGFORD, HOWARD PROJ RMC - 617686001 HWY IH0045 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 106,939.97 REPORT DATE 10/15/2008 15.19.22 CONTRACTOR GIBSON & ASSOCIATES, INC. 3781 EST PERIOD JUN 16,2008 TO AUG 08,2008 EST NO 004 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6176-86-001 RMC - 617686001 17 IH0045 FREESTONE -LIMITS - CANEY CREEK BRIDGE BNSF RR BRIDGE - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 208,575.44