1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4071712 MGR.NO. 006 PAGE 001 CONT 6156 SEC 97 JOB 001 RES ENGR LANGFORD, HOWARD PROJ RMC - 615697001 HWY SH0075 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 120,603.00 REPORT DATE 08/10/2008 12.58.51 CONTRACTOR MERKEL CONSTRUCTION CO INC 6935 EST PERIOD JUL 19,2007 TO JUL 24,2008 EST NO 014 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 19, 2007 TIME COMPUTED FROM JUL 26, 2007 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 348 341 7 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 08 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 07/24/08 3 1 DAYS CHARGED TO DATE = 365 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 450 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 450 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 - - 0 ----- ----- ----- 372 365 7 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4071712 MGR.NO. 006 PAGE 001 CONT 6156 SEC 97 JOB 001 RES ENGR LANGFORD, HOWARD PROJ RMC - 615697001 HWY SH0075 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 120,603.00 REPORT DATE 08/10/2008 12.58.52 CONTRACTOR MERKEL CONSTRUCTION CO INC 6935 EST PERIOD JUL 19,2007 TO JUL 24,2008 EST NO 014 & FINAL DIST. 17 COUNTY FREESTONE CONTROL 6156-97-001 PROJECT RMC - 615697001 HIGHWAY SH0075 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- GUARD FENCE REPAIR 0 0005 PREPARED BY DISTRICT MAINTENANCE 0 0055 GUARD FENCE REPAIR NET LENGTH 0.100 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0540 MTL BEAM GD FEN TRANS (TL2) EA 5.000 0.000 1.000 .00 0065 0540 MTL BM GD FN TRANS(THRIE)(RND TIM POST) EA 3.000 0.000 1.000 .00 0070 0542 REMOVING METAL BEAM GUARD FENCE LF 400.000 400.000 4.000 1,600.00 0075 0542 REMOVING TERMINAL ANCHOR SECTION EA 6.000 0.000 400.000 .00 0080 0544 GDRAIL END TRT(INST)(WOOD POST)(TY III) EA 6.000 1.000 2,600.000 2,600.00 0085 0770 REPAIR RAIL ELEMENT (W-BEAM) LF 2,200.000 1,875.000 12.500 23,437.50 0090 0770 REPAIR RAIL ELEMENT (THRIE-BEAM) LF 5.000 0.000 1.000 .00 0095 0770 REP RAIL ELMNT(THRIE-BM TRANS TO W-BM) LF 150.000 0.000 1.000 .00 0100 0770 REM/REPL TIMBER/STL POST W/O CONC FND EA 500.000 216.000 35.000 7,560.00 0105 0770 REM/REPL TIMBER/STL POST W/ CONC FND EA 95.000 0.000 35.000 .00 0110 0770 REPAIR OF TERMINAL ANCHORS POSTS EA 15.000 0.000 1.000 .00 0115 0770 REMOVE GDRAIL END TRT/ REPL WITH SGT EA 15.000 15.000 3,000.000 45,000.00 0120 0770 REMOVE & REPLACE BLOCKOUT EA 500.000 0.000 15.000 .00 0 SUBTOTAL BID ITEMS $ 80,197.50 0 TOTAL AMOUNT WORK DONE GUARD FENCE REPAIR $ 80,197.50 0 TOTAL AMOUNT WORK DONE CONTROL 6156-97-001 $ 80,197.50 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4071712 MGR.NO. 006 PAGE 001 CONT 6156 SEC 97 JOB 001 RES ENGR LANGFORD, HOWARD PROJ RMC - 615697001 HWY SH0075 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 120,603.00 REPORT DATE 08/10/2008 12.58.52 CONTRACTOR MERKEL CONSTRUCTION CO INC 6935 EST PERIOD JUL 19,2007 TO JUL 24,2008 EST NO 014 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN JUL 19, 2007 WORKING DAYS USED 365 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED JUL 24 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6156-97-001 RMC - 615697001 17 SH0075 FREESTONE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0542 REMOVING METAL BEAM GUARD FENCE LF 400.000 400.000 4.000 1,600.00 0544 GDRAIL END TRT(INST)(WOOD POST)(TY III) EA 6.000 1.000 2,600.000 2,600.00 0770 REPAIR RAIL ELEMENT (W-BEAM) LF 2,200.000 1,875.000 12.500 23,437.50 0770 REM/REPL TIMBER/STL POST W/O CONC FND EA 500.000 216.000 35.000 7,560.00 0770 REMOVE GDRAIL END TRT/ REPL WITH SGT EA 15.000 15.000 3,000.000 45,000.00 0 SUBTOTAL BID ITEMS $ 80,197.50 0 CONTRACT TOTAL ALL ITEMS $ 80,197.50 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4071712 MGR.NO. 006 PAGE 001 CONT 6156 SEC 97 JOB 001 RES ENGR LANGFORD, HOWARD PROJ RMC - 615697001 HWY SH0075 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 120,603.00 REPORT DATE 08/10/2008 12.58.52 CONTRACTOR MERKEL CONSTRUCTION CO INC 6935 EST PERIOD JUL 19,2007 TO JUL 24,2008 EST NO 014 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 82 RMC - 615697001 6156-97-001 80,197.50 .00 80,197.50 .00 .00 80,197.50 80,197.50 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 80,197.50 .00 80,197.50 .00 .00 80,197.50 80,197.50 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4071712 MGR.NO. 006 PAGE 001 CONT 6156 SEC 97 JOB 001 RES ENGR LANGFORD, HOWARD PROJ RMC - 615697001 HWY SH0075 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 120,603.00 REPORT DATE 08/10/2008 12.58.52 CONTRACTOR MERKEL CONSTRUCTION CO INC 6935 EST PERIOD JUL 19,2007 TO JUL 24,2008 EST NO 014 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6156-97-001 RMC - 615697001 17 SH0075 FREESTONE -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 80,197.50