1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8061709 MGR.NO. 005 PAGE 001 CONT 6147 SEC 50 JOB 001 RES ENGR LAYWELL, BLANE PROJ RMC - 614750001 HWY FM1915 3303 N. TRAVIS CAMERON CNTY MILAM DIST 17 CONTRACT PRICE $ 125,892.00 REPORT DATE 12/10/2008 16.07.05 CONTRACTOR SURETEC INSURANCE COMPANY 12115 EST PERIOD NOV 13,2006 TO NOV 11,2008 EST NO 025 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 13, 2006 TIME COMPUTED FROM NOV 13, 2006 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 730 719 719 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 08 1 1 TOTAL DAYS ALLOWED = 730 2 1 DATE WORK COMPLETED 11/11/08 3 1 DAYS CHARGED TO DATE = 730 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 450 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 450 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 WORK COMPLETED AND ACCEPTED CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 730 730 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8061709 MGR.NO. 005 PAGE 001 CONT 6147 SEC 50 JOB 001 RES ENGR LAYWELL, BLANE PROJ RMC - 614750001 HWY FM1915 3303 N. TRAVIS CAMERON CNTY MILAM DIST 17 CONTRACT PRICE $ 125,892.00 REPORT DATE 12/10/2008 16.07.05 CONTRACTOR SURETEC INSURANCE COMPANY 12115 EST PERIOD NOV 13,2006 TO NOV 11,2008 EST NO 025 & FINAL DIST. 17 COUNTY MILAM CONTROL 6147-50-001 PROJECT RMC - 614750001 HIGHWAY FM1915 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- DRIFTWOOD AND DEBRIS REMOVAL 0 0005 PREPARED BY DISTRICT MAINTENANCE 0 0055 DRIFTWOOD REMOVAL NET LENGTH 0.100 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 7126 REML & DISPL DRIFTWOOD & DEBRIS LS 18.000 4.600 6,994.000 32,172.40 0061 7126*REML & DISPL DRIFTWOOD & DEBRIS LS 1.000 1.000 17,429.000 17,429.00 0 SUBTOTAL BID ITEMS $ 49,601.40 0 TOTAL AMOUNT WORK DONE DRIFTWOOD REMOVAL $ 49,601.40 0 TOTAL AMOUNT WORK DONE CONTROL 6147-50-001 $ 49,601.40 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8061709 MGR.NO. 005 PAGE 001 CONT 6147 SEC 50 JOB 001 RES ENGR LAYWELL, BLANE PROJ RMC - 614750001 HWY FM1915 3303 N. TRAVIS CAMERON CNTY MILAM DIST 17 CONTRACT PRICE $ 125,892.00 REPORT DATE 12/10/2008 16.07.05 CONTRACTOR SURETEC INSURANCE COMPANY 12115 EST PERIOD NOV 13,2006 TO NOV 11,2008 EST NO 025 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN NOV 13, 2006 WORKING DAYS USED 730 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED NOV 11 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6147-50-001 RMC - 614750001 17 FM1915 MILAM - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -7126 REML & DISPL DRIFTWOOD & DEBRIS LS 18.000 4.600 6,994.000 32,172.40 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 07126* REML & DISPL DRIFTWOOD & DEBRIS LS 1.000 1.000 17,429.000 17,429.00 0 SUBTOTAL BID ITEMS $ 49,601.40 0 CONTRACT TOTAL ALL ITEMS $ 49,601.40 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8061709 MGR.NO. 005 PAGE 001 CONT 6147 SEC 50 JOB 001 RES ENGR LAYWELL, BLANE PROJ RMC - 614750001 HWY FM1915 3303 N. TRAVIS CAMERON CNTY MILAM DIST 17 CONTRACT PRICE $ 125,892.00 REPORT DATE 12/10/2008 16.07.06 CONTRACTOR SURETEC INSURANCE COMPANY 12115 EST PERIOD NOV 13,2006 TO NOV 11,2008 EST NO 025 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 166 RMC - 614750001 6147-50-001 49,601.40 .00 49,601.40 .00 .00 49,601.40 49,601.40 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 49,601.40 .00 49,601.40 .00 .00 49,601.40 49,601.40 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8061709 MGR.NO. 005 PAGE 001 CONT 6147 SEC 50 JOB 001 RES ENGR LAYWELL, BLANE PROJ RMC - 614750001 HWY FM1915 3303 N. TRAVIS CAMERON CNTY MILAM DIST 17 CONTRACT PRICE $ 125,892.00 REPORT DATE 12/10/2008 16.07.06 CONTRACTOR SURETEC INSURANCE COMPANY 12115 EST PERIOD NOV 13,2006 TO NOV 11,2008 EST NO 025 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6147-50-001 RMC - 614750001 17 FM1915 MILAM -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 49,601.40