1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 3084004 MGR.NO. 004 PAGE 001 CONT 6146 SEC 53 JOB 001 RES ENGR PAVLAS, ROB PROJ RMC - 614653001 HWY SH0021 2157 SH 36 CALDWELL CNTY BURLESON DIST 17 CONTRACT PRICE $ 325,814.85 REPORT DATE 07/28/2008 15.44.41 CONTRACTOR BIG CREEK CONSTRUCTION, LTD. 8175 EST PERIOD MAY 12,2008 TO JUL 15,2008 EST NO 004 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 12, 2008 TIME COMPUTED FROM MAY 12, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 30 50 24 26 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 08 1 1 AWAITING CHANGE ORDER TOTAL DAYS ALLOWED = 30 2 1 AWAITING CHANGE ORDER DATE WORK COMPLETED 07/15/08 3 1 AWAITING CHANGE ORDER DAYS CHARGED TO DATE = 24 4 1 AWAITING CHANGE ORDER ASSESSED LIQ DAMAGES = 0 5 1 AWAITING CHANGE ORDER LIQ DAMAGE RATE $ 500 6 1 AWAITING CHANGE ORDER 7 1 AWAITING CHANGE ORDER LIQUIDATED DAMAGES 8 1 AWAITING CHANGE ORDER 0 DAYS AT $ 500 PER DAY 9 1 AWAITING CHANGE ORDER TOTAL = $ .00 10 1 AWAITING CHANGE ORDER 11 1 AWAITING CHANGE ORDER CERTIFIED AS CORRECT AND 12 1 AWAITING CHANGE ORDER ONE COPY HAS BEEN GIVEN 13 1 AWAITING CHANGE ORDER TO THE CONTRACTOR 14 1 AWAITING CHANGE ORDER 15 1 WORK COMPLETED AND ACCEPTED ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 65 24 41 0 SATURDAY 0 SUNDAY 0 HOLIDAY 14 AWAITING CHANGE ORDER 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 3084004 MGR.NO. 004 PAGE 001 CONT 6146 SEC 53 JOB 001 RES ENGR PAVLAS, ROB PROJ RMC - 614653001 HWY SH0021 2157 SH 36 CALDWELL CNTY BURLESON DIST 17 CONTRACT PRICE $ 325,814.85 REPORT DATE 07/28/2008 15.44.41 CONTRACTOR BIG CREEK CONSTRUCTION, LTD. 8175 EST PERIOD MAY 12,2008 TO JUL 15,2008 EST NO 004 & FINAL DIST. 17 COUNTY BURLESON CONTROL 6146-53-001 PROJECT RMC - 614653001 HIGHWAY SH0021 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- PLANE & LEVEL-UP OF EXISTING PAVEMENT 0 0005 PREPARED BY DISTRICT DESIGN 0 0055 MILL & INLAY NET LENGTH 0.995 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0134 BACKFILL (TY A OR B) STA 56.530 56.530 100.000 5,653.00 0065 0164 STRAW/HAY MLCH SEED(PERM)(RURAL)(SANDY) SY 7,286.000 0.000 .200 .00 0065 0164 ADJ EST QUANTITY TO DATE 0.000 0070 0168 VEGETATIVE WATERING MG 58.290 0.000 10.000 .00 0070 0168 ADJ EST QUANTITY TO DATE 0.000 0075 0341 D-GR HMA(QCQA) TY-C SAC-B PG64-22 TON 2,806.000 3,055.140 85.000 259,686.90 0075 0341 ADJ EST QUANTITY TO DATE 3,055.140 0080 0354 PLANE ASPH CONC PAV(0" TO 4") SY 18,446.000 18,711.776 1.750 32,745.61 0080 0354 ADJ EST QUANTITY TO DATE 18,711.776 0085 0354 PLANE ASPH CONC PAV (4" TO 11") SY 3,356.000 3,386.665 5.000 16,933.33 0085 0354 ADJ EST QUANTITY TO DATE 3,386.665 0090 0500 MOBILIZATION LS 1.000 1.000 10,000.000 10,000.00 0095 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 2,200.000 4,400.00 0100 0506 TEMPORARY SEDIMENT CONTROL FENCE LF 825.000 0.000 3.000 .00 0100 0506 ADJ EST QUANTITY TO DATE 0.000 0105 0533 SHOULDER TEXTURING (MILLED) LF 9,978.000 8,393.000 .550 4,616.15 0105 0533 ADJ EST QUANTITY TO DATE 8,393.000 0110 0662 WK ZN PAV MRK SHT TERM (TAB) TY W EA 427.000 621.000 1.000 621.00 0110 0662 ADJ EST QUANTITY TO DATE 621.000 0115 0666 REFL PAV MRK TY I (W) 4" (BRK)(090MIL) LF 1,420.000 1,560.000 .450 702.00 1 0115 0666 ADJ EST QUANTITY TO DATE 1,560.000 0120 0666 REFL PAV MRK TY I (W) 4" (SLD)(090MIL) LF 5,653.000 6,605.000 .450 2,972.25 0120 0666 ADJ EST QUANTITY TO DATE 6,605.000 0125 0666 REFL PAV MRK TY I (W) 8" (SLD)(090MIL) LF 123.000 120.000 1.000 120.00 0125 0666 ADJ EST QUANTITY TO DATE 120.000 0130 0666 REFL PAV MRK TY I (W) (ARROW) (090MIL) EA 4.000 3.000 150.000 450.00 0130 0666 ADJ EST QUANTITY TO DATE 3.000 0135 0666 REFL PAV MRK TY I (W) (WORD) (090MIL) EA 2.000 2.000 200.000 400.00 0140 0666 REFL PAV MRK TY I (Y) 4" (SLD)(090MIL) LF 5,135.000 5,575.000 .500 2,787.50 0140 0666 ADJ EST QUANTITY TO DATE 5,575.000 0145 0672 REFL PAV MRKR TY II-C-R EA 74.000 90.000 12.000 1,080.00 0145 0672 ADJ EST QUANTITY TO DATE 90.000 0 SUBTOTAL BID ITEMS $ 343,167.74 0 TOTAL AMOUNT WORK DONE MILL & INLAY $ 343,167.74 0 TOTAL AMOUNT WORK DONE CONTROL 6146-53-001 $ 343,167.74 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 3084004 MGR.NO. 004 PAGE 001 CONT 6146 SEC 53 JOB 001 RES ENGR PAVLAS, ROB PROJ RMC - 614653001 HWY SH0021 2157 SH 36 CALDWELL CNTY BURLESON DIST 17 CONTRACT PRICE $ 325,814.85 REPORT DATE 07/28/2008 15.44.41 CONTRACTOR BIG CREEK CONSTRUCTION, LTD. 8175 EST PERIOD MAY 12,2008 TO JUL 15,2008 EST NO 004 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN MAY 12, 2008 WORKING DAYS USED 24 PERCENT COMPLETE 100.00 PERCENT TIME USED 80.00 DATE COMPLETED JUL 15 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6146-53-001 RMC - 614653001 17 SH0021 BURLESON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0134 BACKFILL (TY A OR B) STA 56.530 56.530 100.000 5,653.00 0341 D-GR HMA(QCQA) TY-C SAC-B PG64-22 TON 2,806.000 3,055.140 85.000 259,686.90 0341 ADJ EST QUANTITY TO DATE 3,055.140 0354 PLANE ASPH CONC PAV(0" TO 4") SY 18,446.000 18,711.776 1.750 32,745.61 0354 ADJ EST QUANTITY TO DATE 18,711.776 0354 PLANE ASPH CONC PAV (4" TO 11") SY 3,356.000 3,386.665 5.000 16,933.33 0354 ADJ EST QUANTITY TO DATE 3,386.665 0500 MOBILIZATION LS 1.000 1.000 10,000.000 10,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 2,200.000 4,400.00 0533 SHOULDER TEXTURING (MILLED) LF 9,978.000 8,393.000 .550 4,616.15 0533 ADJ EST QUANTITY TO DATE 8,393.000 0662 WK ZN PAV MRK SHT TERM (TAB) TY W EA 427.000 621.000 1.000 621.00 0662 ADJ EST QUANTITY TO DATE 621.000 0666 REFL PAV MRK TY I (W) 4" (BRK)(090MIL) LF 1,420.000 1,560.000 .450 702.00 0666 ADJ EST QUANTITY TO DATE 1,560.000 0666 REFL PAV MRK TY I (W) 4" (SLD)(090MIL) LF 5,653.000 6,605.000 .450 2,972.25 0666 ADJ EST QUANTITY TO DATE 6,605.000 0666 REFL PAV MRK TY I (W) 8" 1 (SLD)(090MIL) LF 123.000 120.000 1.000 120.00 0666 ADJ EST QUANTITY TO DATE 120.000 0666 REFL PAV MRK TY I (W) (ARROW) (090MIL) EA 4.000 3.000 150.000 450.00 0666 ADJ EST QUANTITY TO DATE 3.000 0666 REFL PAV MRK TY I (W) (WORD) (090MIL) EA 2.000 2.000 200.000 400.00 0666 REFL PAV MRK TY I (Y) 4" (SLD)(090MIL) LF 5,135.000 5,575.000 .500 2,787.50 0666 ADJ EST QUANTITY TO DATE 5,575.000 0672 REFL PAV MRKR TY II-C-R EA 74.000 90.000 12.000 1,080.00 0672 ADJ EST QUANTITY TO DATE 90.000 0 SUBTOTAL BID ITEMS $ 343,167.74 0 CONTRACT TOTAL ALL ITEMS $ 343,167.74 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 3084004 MGR.NO. 004 PAGE 001 CONT 6146 SEC 53 JOB 001 RES ENGR PAVLAS, ROB PROJ RMC - 614653001 HWY SH0021 2157 SH 36 CALDWELL CNTY BURLESON DIST 17 CONTRACT PRICE $ 325,814.85 REPORT DATE 07/28/2008 15.44.41 CONTRACTOR BIG CREEK CONSTRUCTION, LTD. 8175 EST PERIOD MAY 12,2008 TO JUL 15,2008 EST NO 004 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 26 RMC - 614653001 6146-53-001 343,167.74 .00 343,167.74 .00 .00 343,167.74 343,167.74 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 343,167.74 .00 343,167.74 .00 .00 343,167.74 343,167.74 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 3084004 MGR.NO. 004 PAGE 001 CONT 6146 SEC 53 JOB 001 RES ENGR PAVLAS, ROB PROJ RMC - 614653001 HWY SH0021 2157 SH 36 CALDWELL CNTY BURLESON DIST 17 CONTRACT PRICE $ 325,814.85 REPORT DATE 07/28/2008 15.44.42 CONTRACTOR BIG CREEK CONSTRUCTION, LTD. 8175 EST PERIOD MAY 12,2008 TO JUL 15,2008 EST NO 004 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6146-53-001 RMC - 614653001 17 SH0021 BURLESON -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 343,167.74