1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8122009 MGR.NO. 051 PAGE 001 CONT 6246 SEC 52 JOB 001 RES ENGR CARON, CHRIS PROJ SUP - 624652001 HWY SH0073 6101 TWIN CITY HWY PT ART CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 112,798.81 REPORT DATE 05/01/2013 17.33.48 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 008 SPINDLETOP MHMR SERVICES 09725 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 01, 2012 TIME COMPUTED FROM SEP 01, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 212 208 4 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 13 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 238 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 242 238 4 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8122009 MGR.NO. 051 PAGE 001 CONT 6246 SEC 52 JOB 001 RES ENGR CARON, CHRIS PROJ SUP - 624652001 HWY SH0073 6101 TWIN CITY HWY PT ART CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 112,798.81 REPORT DATE 05/01/2013 17.33.49 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 008 SPINDLETOP MHMR SERVICES 09725 DIST. 20 COUNTY JEFFERSON CONTROL 6246-52-001 PROJECT SUP - 624652001 HIGHWAY SH0073 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- PT ARTHUR ~ LITTER 0 0005 PT ARTHUR MAINTENANCE 0 0055 LITTER REMOVAL NET LENGTH 1.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL(SPOT) AC 600.000 52.000 12.000 624.00 0065 0734 LITTER REMOVAL - TRACT (1) CYC 3.000 2.000 218.940 437.88 0070 0734 LITTER REMOVAL - TRACT (2) CYC 2.000 1.000 2,489.390 2,489.39 0075 0734 LITTER REMOVAL - TRACT (3) CYC 7.000 4.000 5,602.370 22,409.48 0080 0734 LITTER REMOVAL - TRACT (4) CYC 2.000 2.000 5,706.100 11,412.20 0085 0734 LITTER REMOVAL - TRACT (5) CYC 4.000 3.000 3,286.160 9,858.48 0090 0734 LITTER REMOVAL - TRACT (6) CYC 3.000 2.000 2,841.060 5,682.12 0095 0734 LITTER REMOVAL - TRACT (7) CYC 2.000 1.000 380.090 380.09 0100 0734 LITTER REMOVAL - TRACT (8) CYC 8.000 5.000 501.320 2,506.60 0105 0734 LITTER REMOVAL - TRACT (9) CYC 4.000 3.000 1,834.290 5,502.87 0110 0734 LITTER REMOVAL - TRACT (10) CYC 1.000 1.000 956.940 956.94 0115 0734 LITTER REMOVAL - TRACT (11) CYC 3.000 2.000 1,431.080 2,862.16 0120 0734 LITTER REMOVAL - TRACT (12) CYC 9.000 6.000 1,102.740 6,616.44 0125 0734 LITTER REMOVAL - TRACT (13) CYC 2.000 1.000 191.930 191.93 0 SUBTOTAL BID ITEMS $ 71,930.58 0 TOTAL AMOUNT WORK DONE LITTER REMOVAL $ 71,930.58 0 TOTAL AMOUNT WORK DONE CONTROL 6246-52-001 $ 71,930.58 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8122009 MGR.NO. 051 PAGE 001 CONT 6246 SEC 52 JOB 001 RES ENGR CARON, CHRIS PROJ SUP - 624652001 HWY SH0073 6101 TWIN CITY HWY PT ART CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 112,798.81 REPORT DATE 05/01/2013 17.33.49 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 008 SPINDLETOP MHMR SERVICES 09725 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN SEP 1 , 2012 WORKING DAYS USED 238 PERCENT COMPLETE 63.76 PERCENT TIME USED 65.20 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6246-52-001 SUP - 624652001 20 SH0073 JEFFERSON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL(SPOT) AC 600.000 52.000 12.000 624.00 0734 LITTER REMOVAL - TRACT (1) CYC 3.000 2.000 218.940 437.88 0734 LITTER REMOVAL - TRACT (2) CYC 2.000 1.000 2,489.390 2,489.39 0734 LITTER REMOVAL - TRACT (3) CYC 7.000 4.000 5,602.370 22,409.48 0734 LITTER REMOVAL - TRACT (4) CYC 2.000 2.000 5,706.100 11,412.20 0734 LITTER REMOVAL - TRACT (5) CYC 4.000 3.000 3,286.160 9,858.48 0734 LITTER REMOVAL - TRACT (6) CYC 3.000 2.000 2,841.060 5,682.12 0734 LITTER REMOVAL - TRACT (7) CYC 2.000 1.000 380.090 380.09 0734 LITTER REMOVAL - TRACT (8) CYC 8.000 5.000 501.320 2,506.60 0734 LITTER REMOVAL - TRACT (9) CYC 4.000 3.000 1,834.290 5,502.87 0734 LITTER REMOVAL - TRACT (10) CYC 1.000 1.000 956.940 956.94 0734 LITTER REMOVAL - TRACT (11) CYC 3.000 2.000 1,431.080 2,862.16 0734 LITTER REMOVAL - TRACT (12) CYC 9.000 6.000 1,102.740 6,616.44 0734 LITTER REMOVAL - TRACT (13) CYC 2.000 1.000 191.930 191.93 0 SUBTOTAL BID ITEMS $ 71,930.58 0 CONTRACT TOTAL ALL ITEMS $ 71,930.58 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8122009 MGR.NO. 051 PAGE 001 CONT 6246 SEC 52 JOB 001 RES ENGR CARON, CHRIS PROJ SUP - 624652001 HWY SH0073 6101 TWIN CITY HWY PT ART CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 112,798.81 REPORT DATE 05/01/2013 17.33.49 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 008 SPINDLETOP MHMR SERVICES 09725 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 124 SUP - 624652001 6246-52-001 71,930.58 .00 71,930.58 .00 .00 71,930.58 61,334.26 10,596.32 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 71,930.58 .00 71,930.58 .00 .00 71,930.58 61,334.26 10,596.32 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8122009 MGR.NO. 051 PAGE 001 CONT 6246 SEC 52 JOB 001 RES ENGR CARON, CHRIS PROJ SUP - 624652001 HWY SH0073 6101 TWIN CITY HWY PT ART CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 112,798.81 REPORT DATE 05/01/2013 17.33.50 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 008 SPINDLETOP MHMR SERVICES 09725 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6246-52-001 SUP - 624652001 20 SH0073 JEFFERSON -LIMITS - VARIOUS VARIOUS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 80 0734 LITTER REMOVAL - TRACT (4) CYC 2.000 1.000 5,706.100 5,706.10 85 0734 LITTER REMOVAL - TRACT (5) CYC 4.000 1.000 3,286.160 3,286.16 100 0734 LITTER REMOVAL - TRACT (8) CYC 8.000 1.000 501.320 501.32 120 0734 LITTER REMOVAL - TRACT (12) CYC 9.000 1.000 1,102.740 1,102.74 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 10,596.32 0 TOTAL AMOUNT WORK DONE TO DATE - $ 71,930.58