1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8122007 MGR.NO. 053 PAGE 001 CONT 6246 SEC 50 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624650001 HWY US0190 1009 W COURT ST NEWTON CNTY NEWTON DIST 20 CONTRACT PRICE $ 68,955.13 REPORT DATE 05/02/2013 10.07.53 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 008 BURKE CENTER 08985 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 01, 2012 TIME COMPUTED FROM SEP 01, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 212 204 8 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 13 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 234 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 242 234 8 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8122007 MGR.NO. 053 PAGE 001 CONT 6246 SEC 50 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624650001 HWY US0190 1009 W COURT ST NEWTON CNTY NEWTON DIST 20 CONTRACT PRICE $ 68,955.13 REPORT DATE 05/02/2013 10.07.55 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 008 BURKE CENTER 08985 DIST. 20 COUNTY NEWTON CONTROL 6246-50-001 PROJECT SUP - 624650001 HIGHWAY US0190 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- NEWTON ~ LITTER 0 0005 NEWTON MAINTENANCE 0 0055 LITTER REMOVAL NET LENGTH 1.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL(SPOT) AC 200.000 0.000 12.000 .00 0065 0734 LITTER REMOVAL - TRACT (1) CYC 4.000 3.000 4,747.120 14,241.36 0070 0734 LITTER REMOVAL - TRACT (2) CYC 3.000 2.000 2,904.930 5,809.86 0075 0734 LITTER REMOVAL - TRACT (3) CYC 3.000 2.000 328.860 657.72 0080 0734 LITTER REMOVAL - TRACT (4) CYC 2.000 2.000 1,811.700 3,623.40 0085 0734 LITTER REMOVAL - TRACT (5) CYC 4.000 3.000 1,857.760 5,573.28 0090 0734 LITTER REMOVAL - TRACT (6) CYC 2.000 1.000 982.980 982.98 0095 0734 LITTER REMOVAL - TRACT (7) CYC 3.000 2.000 463.500 927.00 0100 0734 LITTER REMOVAL - TRACT (8) CYC 2.000 1.000 567.100 567.10 0105 0734 LITTER REMOVAL - TRACT (9) CYC 4.000 3.000 1,563.000 4,689.00 0110 0734 LITTER REMOVAL - TRACT (10) CYC 3.000 2.000 2,416.860 4,833.72 0115 0734 LITTER REMOVAL - TRACT (11) CYC 5.000 3.000 435.900 1,307.70 0120 0734 LITTER REMOVAL - TRACT (12) CYC 2.000 1.000 297.800 297.80 0125 0734 LITTER REMOVAL - TRACT (13) CYC 5.000 3.000 373.120 1,119.36 0130 0734 LITTER REMOVAL - TRACT (14) CYC 6.000 4.000 696.150 2,784.60 0 SUBTOTAL BID ITEMS $ 47,414.88 0 TOTAL AMOUNT WORK DONE LITTER REMOVAL $ 47,414.88 0 TOTAL AMOUNT WORK DONE CONTROL 6246-50-001 $ 47,414.88 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8122007 MGR.NO. 053 PAGE 001 CONT 6246 SEC 50 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624650001 HWY US0190 1009 W COURT ST NEWTON CNTY NEWTON DIST 20 CONTRACT PRICE $ 68,955.13 REPORT DATE 05/02/2013 10.07.55 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 008 BURKE CENTER 08985 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN SEP 1 , 2012 WORKING DAYS USED 234 PERCENT COMPLETE 68.76 PERCENT TIME USED 64.10 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6246-50-001 SUP - 624650001 20 US0190 NEWTON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL - TRACT (1) CYC 4.000 3.000 4,747.120 14,241.36 0734 LITTER REMOVAL - TRACT (2) CYC 3.000 2.000 2,904.930 5,809.86 0734 LITTER REMOVAL - TRACT (3) CYC 3.000 2.000 328.860 657.72 0734 LITTER REMOVAL - TRACT (4) CYC 2.000 2.000 1,811.700 3,623.40 0734 LITTER REMOVAL - TRACT (5) CYC 4.000 3.000 1,857.760 5,573.28 0734 LITTER REMOVAL - TRACT (6) CYC 2.000 1.000 982.980 982.98 0734 LITTER REMOVAL - TRACT (7) CYC 3.000 2.000 463.500 927.00 0734 LITTER REMOVAL - TRACT (8) CYC 2.000 1.000 567.100 567.10 0734 LITTER REMOVAL - TRACT (9) CYC 4.000 3.000 1,563.000 4,689.00 0734 LITTER REMOVAL - TRACT (10) CYC 3.000 2.000 2,416.860 4,833.72 0734 LITTER REMOVAL - TRACT (11) CYC 5.000 3.000 435.900 1,307.70 0734 LITTER REMOVAL - TRACT (12) CYC 2.000 1.000 297.800 297.80 0734 LITTER REMOVAL - TRACT (13) CYC 5.000 3.000 373.120 1,119.36 0734 LITTER REMOVAL - TRACT (14) CYC 6.000 4.000 696.150 2,784.60 0 SUBTOTAL BID ITEMS $ 47,414.88 0 CONTRACT TOTAL ALL ITEMS $ 47,414.88 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8122007 MGR.NO. 053 PAGE 001 CONT 6246 SEC 50 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624650001 HWY US0190 1009 W COURT ST NEWTON CNTY NEWTON DIST 20 CONTRACT PRICE $ 68,955.13 REPORT DATE 05/02/2013 10.07.55 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 008 BURKE CENTER 08985 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 176 SUP - 624650001 6246-50-001 47,414.88 .00 47,414.88 .00 .00 47,414.88 39,599.59 7,815.29 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 47,414.88 .00 47,414.88 .00 .00 47,414.88 39,599.59 7,815.29 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8122007 MGR.NO. 053 PAGE 001 CONT 6246 SEC 50 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624650001 HWY US0190 1009 W COURT ST NEWTON CNTY NEWTON DIST 20 CONTRACT PRICE $ 68,955.13 REPORT DATE 05/02/2013 10.07.56 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 008 BURKE CENTER 08985 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6246-50-001 SUP - 624650001 20 US0190 NEWTON -LIMITS - VARIOUS VARIOUS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0734 LITTER REMOVAL - TRACT (1) CYC 4.000 1.000 4,747.120 4,747.12 105 0734 LITTER REMOVAL - TRACT (9) CYC 4.000 1.000 1,563.000 1,563.00 115 0734 LITTER REMOVAL - TRACT (11) CYC 5.000 1.000 435.900 435.90 125 0734 LITTER REMOVAL - TRACT (13) CYC 5.000 1.000 373.120 373.12 130 0734 LITTER REMOVAL - TRACT (14) CYC 6.000 1.000 696.150 696.15 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 7,815.29 0 TOTAL AMOUNT WORK DONE TO DATE - $ 47,414.88