1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8122002 MGR.NO. 051 PAGE 001 CONT 6241 SEC 16 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 624116001 HWY SH0073 8450 EASTEX FRWY BEAUMONT CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 141,462.00 REPORT DATE 12/27/2012 11.17.06 CONTRACTOR L.C. JORDAN & SON 15075 EST PERIOD SEP 11,2012 TO NOV 19,2012 EST NO 004 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 18, 2012 TIME COMPUTED FROM SEP 11, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 79 51 33 18 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 12 1 1 TOTAL DAYS ALLOWED = 79 2 1 DATE WORK COMPLETED 11/19/12 3 1 SATURDAY DAYS CHARGED TO DATE = 43 4 1 SUNDAY ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 590 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 590 PER DAY 9 1 TOTAL = $ .00 10 1 SATURDAY 11 1 SUNDAY CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 WORK COMPLETED 16 1 AWAITING ACCEPTANCE ---------------------------- 17 1 SATURDAY AREA/PROJECT ENGINEER 18 1 SUNDAY 19 1 WORK ACCEPTED - - - - ----- ----- ----- 70 43 27 3 SATURDAY 3 SUNDAY 0 HOLIDAY 1 WORK COMPLETED 1 AWAITING ACCEPTANCE 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8122002 MGR.NO. 051 PAGE 001 CONT 6241 SEC 16 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 624116001 HWY SH0073 8450 EASTEX FRWY BEAUMONT CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 141,462.00 REPORT DATE 12/27/2012 11.17.06 CONTRACTOR L.C. JORDAN & SON 15075 EST PERIOD SEP 11,2012 TO NOV 19,2012 EST NO 004 & FINAL DIST. 20 COUNTY JEFFERSON CONTROL 6241-16-001 PROJECT RMC - 624116001 HIGHWAY SH0073 0LIMITS- EASTBOUND BRIDGE AT MAIN"A" CANAL 0TYPE OF WORK- REPLACE DAMAGED BRIDGE RAIL 0 0005 REVISED 5-22-12 0 0055 ROADWAY NET LENGTH 0.152 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0104 REMOVING CONC (RIPRAP) SY 244.000 244.000 8.000 1,952.00 0065 0420 CL C CONC (RAIL FOUNDATION) CY 5.000 5.000 1,850.000 9,250.00 0070 0429 CNC STR REP (BRDG DECK)(FULL DEPTH) SF 35.000 28.000 200.000 5,600.00 0075 0432 RIPRAP (MOW STRIP)(4 IN) CY 24.000 25.530 310.000 7,914.30 0080 0450 RAIL(TY SSTR)(RETROFIT) LF 448.000 448.000 185.000 82,880.00 0085 0452 REMOV RAIL (CONC POST & MTL ELEMENTS) LF 480.000 480.000 8.000 3,840.00 0090 0500 MOBILIZATION LS 1.000 1.000 12,000.000 12,000.00 0095 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 4.000 500.000 2,000.00 0100 0540 MTL W-BEAM GD FEN (TIM POST) LF 350.000 350.000 21.000 7,350.00 0105 0540 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 2.000 2.000 1,800.000 3,600.00 0110 0542 REMOVING METAL BEAM GUARD FENCE LF 250.000 250.000 3.000 750.00 0115 0542 REMOVING TERMINAL ANCHOR SECTION EA 2.000 2.000 150.000 300.00 0120 0544 GUARDRAIL END TREATMENT (MOVE & RESET) EA 2.000 2.000 1,200.000 2,400.00 0125 0658 INSTL DEL ASSM (D-SW)SZ (TYC)CTB EA 3.000 3.000 50.000 150.00 0130 0658 INSTL DEL ASSM (D-SW)SZ (TYC)GF1 EA 3.000 3.000 50.000 150.00 0135 0658 INSTL DEL ASSM (D-SY)SZ (TYC)CTB EA 3.000 3.000 50.000 150.00 0140 0658 INSTL DEL ASSM (D-SY)SZ (TYC)GF1 EA 3.000 3.000 50.000 150.00 0145 0658 INSTL OM ASSM (OM-2Y)(WC) 1 GND EA 2.000 2.000 50.000 100.00 0 SUBTOTAL BID ITEMS $ 140,536.30 0 TOTAL AMOUNT WORK DONE ROADWAY $ 140,536.30 0 TOTAL AMOUNT WORK DONE CONTROL 6241-16-001 $ 140,536.30 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8122002 MGR.NO. 051 PAGE 001 CONT 6241 SEC 16 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 624116001 HWY SH0073 8450 EASTEX FRWY BEAUMONT CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 141,462.00 REPORT DATE 12/27/2012 11.17.06 CONTRACTOR L.C. JORDAN & SON 15075 EST PERIOD SEP 11,2012 TO NOV 19,2012 EST NO 004 & FINAL 0*********************************************************************************************************************************** -LIMITS - EASTBOUND BRIDGE 0 AT MAIN"A" CANAL DATE WORK BEGAN SEP 18, 2012 WORKING DAYS USED 43 PERCENT COMPLETE 100.00 PERCENT TIME USED 54.40 DATE COMPLETED NOV 19 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6241-16-001 RMC - 624116001 20 SH0073 JEFFERSON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0104 REMOVING CONC (RIPRAP) SY 244.000 244.000 8.000 1,952.00 0420 CL C CONC (RAIL FOUNDATION) CY 5.000 5.000 1,850.000 9,250.00 0429 CNC STR REP (BRDG DECK)(FULL DEPTH) SF 35.000 28.000 200.000 5,600.00 0432 RIPRAP (MOW STRIP)(4 IN) CY 24.000 25.530 310.000 7,914.30 0450 RAIL(TY SSTR)(RETROFIT) LF 448.000 448.000 185.000 82,880.00 0452 REMOV RAIL (CONC POST & MTL ELEMENTS) LF 480.000 480.000 8.000 3,840.00 0500 MOBILIZATION LS 1.000 1.000 12,000.000 12,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 4.000 500.000 2,000.00 0540 MTL W-BEAM GD FEN (TIM POST) LF 350.000 350.000 21.000 7,350.00 0540 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 2.000 2.000 1,800.000 3,600.00 0542 REMOVING METAL BEAM GUARD FENCE LF 250.000 250.000 3.000 750.00 0542 REMOVING TERMINAL ANCHOR SECTION EA 2.000 2.000 150.000 300.00 0544 GUARDRAIL END TREATMENT (MOVE & RESET) EA 2.000 2.000 1,200.000 2,400.00 0658 INSTL DEL ASSM (D-SW)SZ (TYC)CTB EA 3.000 3.000 50.000 150.00 0658 INSTL DEL ASSM (D-SW)SZ (TYC)GF1 EA 3.000 3.000 50.000 150.00 0658 INSTL DEL ASSM (D-SY)SZ 1 (TYC)CTB EA 3.000 3.000 50.000 150.00 0658 INSTL DEL ASSM (D-SY)SZ (TYC)GF1 EA 3.000 3.000 50.000 150.00 0658 INSTL OM ASSM (OM-2Y)(WC) GND EA 2.000 2.000 50.000 100.00 0 SUBTOTAL BID ITEMS $ 140,536.30 0 CONTRACT TOTAL ALL ITEMS $ 140,536.30 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8122002 MGR.NO. 051 PAGE 001 CONT 6241 SEC 16 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 624116001 HWY SH0073 8450 EASTEX FRWY BEAUMONT CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 141,462.00 REPORT DATE 12/27/2012 11.17.06 CONTRACTOR L.C. JORDAN & SON 15075 EST PERIOD SEP 11,2012 TO NOV 19,2012 EST NO 004 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 124 RMC - 624116001 6241-16-001 140,536.30 .00 140,536.30 .00 .00 140,536.30 140,176.30 360.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 140,536.30 .00 140,536.30 .00 .00 140,536.30 140,176.30 360.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8122002 MGR.NO. 051 PAGE 001 CONT 6241 SEC 16 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 624116001 HWY SH0073 8450 EASTEX FRWY BEAUMONT CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 141,462.00 REPORT DATE 12/27/2012 11.17.07 CONTRACTOR L.C. JORDAN & SON 15075 EST PERIOD SEP 11,2012 TO NOV 19,2012 EST NO 004 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6241-16-001 RMC - 624116001 20 SH0073 JEFFERSON -LIMITS - EASTBOUND BRIDGE AT MAIN"A" CANAL LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 90 0500 MOBILIZATION LS 1.000 0.030 12,000.000 360.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 360.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 140,536.30