1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 3122010 MGR.NO. 053 PAGE 001 CONT 6240 SEC 52 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624052001 HWY US0190 3304 US 190 W JASPER CNTY JASPER DIST 20 CONTRACT PRICE $ 2,922.47 REPORT DATE 04/10/2013 10.59.15 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2012 TO MAR 31,2013 EST NO 012 & FINAL BURKE CENTER 08985 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 01, 2012 TIME COMPUTED FROM APR 01, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 334 315 19 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAR 13 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 03/28/13 3 1 DAYS CHARGED TO DATE = 342 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 WORK COMPLETED AND ACCEPTED - ----- ----- ----- 362 342 20 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 3122010 MGR.NO. 053 PAGE 001 CONT 6240 SEC 52 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624052001 HWY US0190 3304 US 190 W JASPER CNTY JASPER DIST 20 CONTRACT PRICE $ 2,922.47 REPORT DATE 04/10/2013 10.59.15 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2012 TO MAR 31,2013 EST NO 012 & FINAL BURKE CENTER 08985 DIST. 20 COUNTY JASPER CONTROL 6240-52-001 PROJECT SUP - 624052001 HIGHWAY US0190 0LIMITS- US 190 US 190 0TYPE OF WORK- JASPER ~ GROUNDS 0 0005 JASPER ~ GROUNDS MAINTENANCE 0 0055 JASPER ~ GROUNDS NET LENGTH 1.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 7205 GROUNDS MAINTENANCE CYC 16.000 11.000 171.910 1,891.01 0065 0745 GROUNDS MAINT (MOWING/TRIMMING) CYC 1.000 1.000 171.910 171.91 0 SUBTOTAL BID ITEMS $ 2,062.92 0 TOTAL AMOUNT WORK DONE JASPER ~ GROUNDS $ 2,062.92 0 TOTAL AMOUNT WORK DONE CONTROL 6240-52-001 $ 2,062.92 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 3122010 MGR.NO. 053 PAGE 001 CONT 6240 SEC 52 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624052001 HWY US0190 3304 US 190 W JASPER CNTY JASPER DIST 20 CONTRACT PRICE $ 2,922.47 REPORT DATE 04/10/2013 10.59.15 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2012 TO MAR 31,2013 EST NO 012 & FINAL BURKE CENTER 08985 0*********************************************************************************************************************************** -LIMITS - US 190 0 US 190 DATE WORK BEGAN APR 1 , 2012 WORKING DAYS USED 342 PERCENT COMPLETE 100.00 PERCENT TIME USED 93.60 DATE COMPLETED MAR 28 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6240-52-001 SUP - 624052001 20 US0190 JASPER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0745 GROUNDS MAINT (MOWING/TRIMMING) CYC 1.000 1.000 171.910 171.91 7205 GROUNDS MAINTENANCE CYC 16.000 11.000 171.910 1,891.01 0 SUBTOTAL BID ITEMS $ 2,062.92 0 CONTRACT TOTAL ALL ITEMS $ 2,062.92 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 3122010 MGR.NO. 053 PAGE 001 CONT 6240 SEC 52 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624052001 HWY US0190 3304 US 190 W JASPER CNTY JASPER DIST 20 CONTRACT PRICE $ 2,922.47 REPORT DATE 04/10/2013 10.59.15 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2012 TO MAR 31,2013 EST NO 012 & FINAL BURKE CENTER 08985 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 122 SUP - 624052001 6240-52-001 2,062.92 .00 2,062.92 .00 .00 2,062.92 1,891.01 171.91 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 2,062.92 .00 2,062.92 .00 .00 2,062.92 1,891.01 171.91 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 3122010 MGR.NO. 053 PAGE 001 CONT 6240 SEC 52 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624052001 HWY US0190 3304 US 190 W JASPER CNTY JASPER DIST 20 CONTRACT PRICE $ 2,922.47 REPORT DATE 04/10/2013 10.59.15 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2012 TO MAR 31,2013 EST NO 012 & FINAL BURKE CENTER 08985 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6240-52-001 SUP - 624052001 20 US0190 JASPER -LIMITS - US 190 US 190 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0745 GROUNDS MAINT CYC 1.000 1.000 171.910 171.91 (MOWING/TRIMMING) --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 171.91 0 TOTAL AMOUNT WORK DONE TO DATE - $ 2,062.92