1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 3122003 MGR.NO. 053 PAGE 001 CONT 6229 SEC 02 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 622902001 HWY FM1746 3304 US 190 W JASPER CNTY TYLER DIST 20 CONTRACT PRICE $ 190,454.02 REPORT DATE 10/01/2012 13.47.54 CONTRACTOR APAC-TEXAS, INC. 154 EST PERIOD JUL 01,2012 TO AUG 13,2012 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 01, 2012 TIME COMPUTED FROM JUL 01, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 30 31 14 17 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 12 1 1 TOTAL DAYS ALLOWED = 30 2 1 DATE WORK COMPLETED 08/13/12 3 1 DAYS CHARGED TO DATE = 22 4 1 SATURDAY ASSESSED LIQ DAMAGES = 0 5 1 SUNDAY LIQ DAMAGE RATE $ 590 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 590 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 SATURDAY CERTIFIED AS CORRECT AND 12 1 SUNDAY ONE COPY HAS BEEN GIVEN 13 1 WORK COMPLETED AND ACCEPTED TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 44 22 22 2 SATURDAY 2 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 3122003 MGR.NO. 053 PAGE 001 CONT 6229 SEC 02 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 622902001 HWY FM1746 3304 US 190 W JASPER CNTY TYLER DIST 20 CONTRACT PRICE $ 190,454.02 REPORT DATE 10/01/2012 13.47.56 CONTRACTOR APAC-TEXAS, INC. 154 EST PERIOD JUL 01,2012 TO AUG 13,2012 EST NO 002 & FINAL DIST. 20 COUNTY TYLER CONTROL 6229-02-001 PROJECT RMC - 622902001 HIGHWAY FM1746 0LIMITS- 0.936 MILES WEST OF FM 2992, EAST 1.012 MILES 0TYPE OF WORK- EDGE STABILIZATION 0 0005 EDGE STABILIZATION, P. RYAN, PM 0 0055 ROADWAY NET LENGTH 1.012 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0112 SUBGRADE WIDENING (ORD COMP) STA 53.460 53.460 370.000 19,780.20 0065 0150 BLADING HR 27.000 27.000 95.000 2,565.00 0070 0247 FL BS (CMP IN PLC)(TY D GR 2)(8") SY 4,752.000 4,752.000 18.000 85,536.00 0075 0310 PRIME COAT (AE-P) GAL 950.000 950.000 4.300 4,085.00 0080 0316 ASPH (TIER II) GAL 8,720.000 8,687.000 3.600 31,273.20 0085 0316 AGGR (GR 4) CY 187.000 183.000 90.000 16,470.00 0090 0500 MOBILIZATION LS 1.000 1.000 11,900.000 11,900.00 0095 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 760.000 1,520.00 0100 0506 BACKHOE WORK (EROSION & SEDM CONT) HR 4.000 0.000 95.000 .00 0105 0530 DRIVEWAYS (SURF TREAT) EA 1.000 1.000 640.000 640.00 0110 0530 TURNOUTS (SURF TREAT) EA 2.000 2.000 1,900.000 3,800.00 0115 0560 MAILBOX INSTALL-S(TWW-POST)TY 4 FND- EA 2.000 2.000 140.000 280.00 0120 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 534.000 125.000 1.450 181.25 0125 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 10,571.000 10,571.000 .460 4,862.66 0130 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 670.000 670.000 .500 335.00 0135 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 7,762.000 7,762.000 .480 3,725.76 0140 0672 REFL PAV MRKR TY II-A-A EA 131.000 120.000 5.100 612.00 0145 5049 BIODGRD EROSION CONTROL LOGS (12" DIA) LF 300.000 122.000 4.600 561.20 0 SUBTOTAL BID ITEMS $ 188,127.27 1 TOTAL AMOUNT WORK DONE ROADWAY $ 188,127.27 0 TOTAL AMOUNT WORK DONE CONTROL 6229-02-001 $ 188,127.27 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 3122003 MGR.NO. 053 PAGE 001 CONT 6229 SEC 02 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 622902001 HWY FM1746 3304 US 190 W JASPER CNTY TYLER DIST 20 CONTRACT PRICE $ 190,454.02 REPORT DATE 10/01/2012 13.47.57 CONTRACTOR APAC-TEXAS, INC. 154 EST PERIOD JUL 01,2012 TO AUG 13,2012 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - 0.936 MILES WEST OF FM 2992, EAST 0 1.012 MILES DATE WORK BEGAN JUL 1 , 2012 WORKING DAYS USED 22 PERCENT COMPLETE 100.00 PERCENT TIME USED 73.30 DATE COMPLETED AUG 13 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6229-02-001 RMC - 622902001 20 FM1746 TYLER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0112 SUBGRADE WIDENING (ORD COMP) STA 53.460 53.460 370.000 19,780.20 0150 BLADING HR 27.000 27.000 95.000 2,565.00 0247 FL BS (CMP IN PLC)(TY D GR 2)(8") SY 4,752.000 4,752.000 18.000 85,536.00 0310 PRIME COAT (AE-P) GAL 950.000 950.000 4.300 4,085.00 0316 ASPH (TIER II) GAL 8,720.000 8,687.000 3.600 31,273.20 0316 AGGR (GR 4) CY 187.000 183.000 90.000 16,470.00 0500 MOBILIZATION LS 1.000 1.000 11,900.000 11,900.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 760.000 1,520.00 0530 DRIVEWAYS (SURF TREAT) EA 1.000 1.000 640.000 640.00 0530 TURNOUTS (SURF TREAT) EA 2.000 2.000 1,900.000 3,800.00 0560 MAILBOX INSTALL-S(TWW-POST)TY 4 FND- EA 2.000 2.000 140.000 280.00 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 534.000 125.000 1.450 181.25 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 10,571.000 10,571.000 .460 4,862.66 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 670.000 670.000 .500 335.00 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 7,762.000 7,762.000 .480 3,725.76 0672 REFL PAV MRKR TY II-A-A EA 131.000 120.000 5.100 612.00 5049 BIODGRD EROSION CONTROL LOGS (12" DIA) LF 300.000 122.000 4.600 561.20 1 SUBTOTAL BID ITEMS $ 188,127.27 0 CONTRACT TOTAL ALL ITEMS $ 188,127.27 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 3122003 MGR.NO. 053 PAGE 001 CONT 6229 SEC 02 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 622902001 HWY FM1746 3304 US 190 W JASPER CNTY TYLER DIST 20 CONTRACT PRICE $ 190,454.02 REPORT DATE 10/01/2012 13.47.57 CONTRACTOR APAC-TEXAS, INC. 154 EST PERIOD JUL 01,2012 TO AUG 13,2012 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 229 RMC - 622902001 6229-02-001 188,127.27 .00 188,127.27 .00 .00 188,127.27 140,117.60 48,009.67 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 188,127.27 .00 188,127.27 .00 .00 188,127.27 140,117.60 48,009.67 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 3122003 MGR.NO. 053 PAGE 001 CONT 6229 SEC 02 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 622902001 HWY FM1746 3304 US 190 W JASPER CNTY TYLER DIST 20 CONTRACT PRICE $ 190,454.02 REPORT DATE 10/01/2012 13.47.58 CONTRACTOR APAC-TEXAS, INC. 154 EST PERIOD JUL 01,2012 TO AUG 13,2012 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6229-02-001 RMC - 622902001 20 FM1746 TYLER -LIMITS - 0.936 MILES WEST OF FM 2992, EAST 1.012 MILES LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0150 BLADING HR 27.000 27.000 95.000 2,565.00 80 0316 ASPH (TIER II) GAL 8,720.000 6,305.000 3.600 22,698.00 85 0316 AGGR (GR 4) CY 187.000 120.000 90.000 10,800.00 90 0500 MOBILIZATION LS 1.000 0.100 11,900.000 1,190.00 95 0502 BARRICADES, SIGNS AND MO 2.000 1.000 760.000 760.00 TRAFFIC HANDLING 115 0560 MAILBOX EA 2.000 2.000 140.000 280.00 INSTALL-S(TWW-POST)TY 4 120 0662 WK ZN PAV MRK SHT TERM (TAB) EA 534.000 125.000 1.450 181.25 TY Y-2 125 0666 REFL PAV MRK TY I (W) 4" LF 10,571.000 10,571.000 0.460 4,862.66 (SLD)(100MIL) 130 0666 REFL PAV MRK TY I (Y) 4" LF 670.000 670.000 0.500 335.00 (BRK)(100MIL) 135 0666 REFL PAV MRK TY I (Y) 4" LF 7,762.000 7,762.000 0.480 3,725.76 (SLD)(100MIL) 140 0672 REFL PAV MRKR TY II-A-A EA 131.000 120.000 5.100 612.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 48,009.67 0 TOTAL AMOUNT WORK DONE TO DATE - $ 188,127.27