1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 9112008 MGR.NO. 053 PAGE 001 CONT 6227 SEC 79 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 622779001 HWY US0069 3304 US 190 JASPER CNTY TYLER DIST 20 CONTRACT PRICE $ 116,584.33 REPORT DATE 11/08/2012 17.04.19 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 15,2011 TO AUG 31,2012 EST NO 013 & FINAL BURKE CENTER 08985 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 15, 2011 TIME COMPUTED FROM SEP 15, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 321 274 47 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 12 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 08/31/12 3 1 DAYS CHARGED TO DATE = 304 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 WORK COMPLETED AND ACCEPTED ----- ----- ----- 352 304 48 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 9112008 MGR.NO. 053 PAGE 001 CONT 6227 SEC 79 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 622779001 HWY US0069 3304 US 190 JASPER CNTY TYLER DIST 20 CONTRACT PRICE $ 116,584.33 REPORT DATE 11/08/2012 17.04.20 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 15,2011 TO AUG 31,2012 EST NO 013 & FINAL BURKE CENTER 08985 DIST. 20 COUNTY TYLER CONTROL 6227-79-001 PROJECT SUP - 622779001 HIGHWAY US0069 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- WOODVILLE ~ LITTER PICK UP 0 0005 WOODVILLE 0 0055 LITTER PICK UP NET LENGTH 1.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL(SPOT) AC 10.000 5.000 12.000 60.00 0065 0734 LITTER REMOVAL - TRACT (1) CYC 9.000 9.000 3,455.530 31,099.77 0070 0734 LITTER REMOVAL - TRACT (2) CYC 5.000 4.000 2,535.060 10,140.24 0075 0734 LITTER REMOVAL - TRACT (3) CYC 5.000 4.000 1,677.510 6,710.04 0080 0734 LITTER REMOVAL - TRACT (4) CYC 3.000 2.000 298.980 597.96 0085 0734 LITTER REMOVAL - TRACT (5) CYC 3.000 3.000 2,583.490 7,750.47 0090 0734 LITTER REMOVAL - TRACT (6) CYC 5.000 4.000 509.760 2,039.04 0095 0734 LITTER REMOVAL - TRACT (7) CYC 6.000 6.000 2,036.880 12,221.28 0100 0734 LITTER REMOVAL - TRACT (8) CYC 9.000 9.000 1,882.100 16,938.90 0105 0734 LITTER REMOVAL - TRACT (9) CYC 1.000 1.000 1,908.200 1,908.20 0110 0734 LITTER REMOVAL - TRACT (10) CYC 3.000 2.000 546.480 1,092.96 0115 0734 LITTER REMOVAL - TRACT (11) CYC 1.000 0.000 1,345.400 .00 0120 0734 LITTER REMOVAL - TRACT (12) CYC 5.000 3.000 331.760 995.28 0125 0734 LITTER REMOVAL - TRACT (13) CYC 4.000 3.000 477.360 1,432.08 0130 0734 LITTER REMOVAL - TRACT (14) CYC 5.000 4.000 1,277.600 5,110.40 0135 0734 LITTER REMOVAL - TRACT (15) CYC 2.000 1.000 1,719.700 1,719.70 0140 0734 LITTER REMOVAL - TRACT (16) CYC 4.000 3.000 1,214.400 3,643.20 0145 0734 LITTER REMOVAL - TRACT (17) CYC 2.000 2.000 118.510 237.02 0150 0734 LITTER REMOVAL - TRACT (18) CYC 1.000 1.000 562.020 562.02 0 SUBTOTAL BID ITEMS $ 104,258.56 0 TOTAL AMOUNT WORK DONE LITTER PICK UP $ 104,258.56 0 TOTAL AMOUNT WORK DONE CONTROL 6227-79-001 $ 104,258.56 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 9112008 MGR.NO. 053 PAGE 001 CONT 6227 SEC 79 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 622779001 HWY US0069 3304 US 190 JASPER CNTY TYLER DIST 20 CONTRACT PRICE $ 116,584.33 REPORT DATE 11/08/2012 17.04.20 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 15,2011 TO AUG 31,2012 EST NO 013 & FINAL BURKE CENTER 08985 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN SEP 15, 2011 WORKING DAYS USED 304 PERCENT COMPLETE 100.00 PERCENT TIME USED 83.20 DATE COMPLETED AUG 31 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6227-79-001 SUP - 622779001 20 US0069 TYLER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL(SPOT) AC 10.000 5.000 12.000 60.00 0734 LITTER REMOVAL - TRACT (1) CYC 9.000 9.000 3,455.530 31,099.77 0734 LITTER REMOVAL - TRACT (2) CYC 5.000 4.000 2,535.060 10,140.24 0734 LITTER REMOVAL - TRACT (3) CYC 5.000 4.000 1,677.510 6,710.04 0734 LITTER REMOVAL - TRACT (4) CYC 3.000 2.000 298.980 597.96 0734 LITTER REMOVAL - TRACT (5) CYC 3.000 3.000 2,583.490 7,750.47 0734 LITTER REMOVAL - TRACT (6) CYC 5.000 4.000 509.760 2,039.04 0734 LITTER REMOVAL - TRACT (7) CYC 6.000 6.000 2,036.880 12,221.28 0734 LITTER REMOVAL - TRACT (8) CYC 9.000 9.000 1,882.100 16,938.90 0734 LITTER REMOVAL - TRACT (9) CYC 1.000 1.000 1,908.200 1,908.20 0734 LITTER REMOVAL - TRACT (10) CYC 3.000 2.000 546.480 1,092.96 0734 LITTER REMOVAL - TRACT (12) CYC 5.000 3.000 331.760 995.28 0734 LITTER REMOVAL - TRACT (13) CYC 4.000 3.000 477.360 1,432.08 0734 LITTER REMOVAL - TRACT (14) CYC 5.000 4.000 1,277.600 5,110.40 0734 LITTER REMOVAL - TRACT (15) CYC 2.000 1.000 1,719.700 1,719.70 0734 LITTER REMOVAL - TRACT (16) CYC 4.000 3.000 1,214.400 3,643.20 0734 LITTER REMOVAL - TRACT (17) CYC 2.000 2.000 118.510 237.02 0734 LITTER REMOVAL - TRACT (18) CYC 1.000 1.000 562.020 562.02 0 SUBTOTAL BID ITEMS $ 104,258.56 0 CONTRACT TOTAL ALL ITEMS $ 104,258.56 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 9112008 MGR.NO. 053 PAGE 001 CONT 6227 SEC 79 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 622779001 HWY US0069 3304 US 190 JASPER CNTY TYLER DIST 20 CONTRACT PRICE $ 116,584.33 REPORT DATE 11/08/2012 17.04.20 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 15,2011 TO AUG 31,2012 EST NO 013 & FINAL BURKE CENTER 08985 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 229 SUP - 622779001 6227-79-001 104,258.56 .00 104,258.56 .00 .00 104,258.56 104,258.56 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 104,258.56 .00 104,258.56 .00 .00 104,258.56 104,258.56 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 9112008 MGR.NO. 053 PAGE 001 CONT 6227 SEC 79 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 622779001 HWY US0069 3304 US 190 JASPER CNTY TYLER DIST 20 CONTRACT PRICE $ 116,584.33 REPORT DATE 11/08/2012 17.04.20 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 15,2011 TO AUG 31,2012 EST NO 013 & FINAL BURKE CENTER 08985 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6227-79-001 SUP - 622779001 20 US0069 TYLER -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 104,258.56