1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2124031 MGR.NO. 053 PAGE 001 CONT 6224 SEC 28 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 622428001 HWY US0096 3304 US HWY 190 W JASPER CNTY JASPER DIST 20 CONTRACT PRICE $ 245,876.00 REPORT DATE 09/27/2012 10.26.22 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD APR 23,2012 TO SEP 18,2012 EST NO 006 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 23, 2012 TIME COMPUTED FROM APR 23, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 30 131 27 104 BROUGHT FORWARD ADDL DAYS GRANTED = 0 SEP 12 1 1 SATURDAY TOTAL DAYS ALLOWED = 30 2 1 SUNDAY DATE WORK COMPLETED 09/18/12 3 1 RIVER ELEV. TOO HIGH DAYS CHARGED TO DATE = 30 4 1 RIVER ELEV. TOO HIGH ASSESSED LIQ DAMAGES = 0 5 1 RIVER ELEV. TOO HIGH LIQ DAMAGE RATE $ 590 6 1 7 1 LIQUIDATED DAMAGES 8 1 SATURDAY 0 DAYS AT $ 590 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 11 1 AWAITING A.E. ACCEPTANCE CERTIFIED AS CORRECT AND 12 1 AWAITING A.E. ACCEPTANCE ONE COPY HAS BEEN GIVEN 13 1 AWAITING A.E. ACCEPTANCE TO THE CONTRACTOR 14 1 AWAITING A.E. ACCEPTANCE 15 1 SATURDAY 16 1 SUNDAY ---------------------------- 17 1 AWAITING D.E. ACCEPTANCE AREA/PROJECT ENGINEER 18 1 WORK COMPLETED AND ACCEPTED - - - - 0 ----- ----- ----- 149 30 119 3 SATURDAY 3 SUNDAY 0 HOLIDAY 3 RIVER ELEV. TOO HIGH 4 AWAITING A.E. ACCEPTANCE 1 AWAITING D.E. ACCEPTANCE 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2124031 MGR.NO. 053 PAGE 001 CONT 6224 SEC 28 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 622428001 HWY US0096 3304 US HWY 190 W JASPER CNTY JASPER DIST 20 CONTRACT PRICE $ 245,876.00 REPORT DATE 09/27/2012 10.26.22 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD APR 23,2012 TO SEP 18,2012 EST NO 006 & FINAL DIST. 20 COUNTY JASPER CONTROL 6224-28-001 PROJECT RMC - 622428001 HIGHWAY US0096 0LIMITS- AT NECHES RIVER BRIDGE AND RELIEF BRIDGES 0TYPE OF WORK- REPAIR BRIDGE DECK, COLUMNS AND JOINTS 0 0005 BRIDGE REPAIR PROJ P RYAN, PM 0 0055 BRIDGE NET LENGTH 1.100 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0420 CL C CONC (COLLAR) CY 29.000 31.050 1,250.000 38,812.50 0065 0429 CNC STR REP (BRDG DECK)(FULL DEPTH) SF 136.000 204.000 86.000 17,544.00 0070 0454 HEADER TYPE EXPANSION JOINT LF 2,622.000 2,303.000 65.000 149,695.00 0075 0500 MOBILIZATION LS 1.000 1.000 21,500.000 21,500.00 0080 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 3,000.000 6,000.00 0 SUBTOTAL BID ITEMS $ 233,551.50 0 TOTAL AMOUNT WORK DONE BRIDGE $ 233,551.50 0 TOTAL AMOUNT WORK DONE CONTROL 6224-28-001 $ 233,551.50 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2124031 MGR.NO. 053 PAGE 001 CONT 6224 SEC 28 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 622428001 HWY US0096 3304 US HWY 190 W JASPER CNTY JASPER DIST 20 CONTRACT PRICE $ 245,876.00 REPORT DATE 09/27/2012 10.26.22 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD APR 23,2012 TO SEP 18,2012 EST NO 006 & FINAL 0*********************************************************************************************************************************** -LIMITS - AT NECHES RIVER BRIDGE AND RELIEF 0 BRIDGES DATE WORK BEGAN APR 23, 2012 WORKING DAYS USED 30 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED SEP 18 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6224-28-001 RMC - 622428001 20 US0096 JASPER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0420 CL C CONC (COLLAR) CY 29.000 31.050 1,250.000 38,812.50 0429 CNC STR REP (BRDG DECK)(FULL DEPTH) SF 136.000 204.000 86.000 17,544.00 0454 HEADER TYPE EXPANSION JOINT LF 2,622.000 2,303.000 65.000 149,695.00 0500 MOBILIZATION LS 1.000 1.000 21,500.000 21,500.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 3,000.000 6,000.00 0 SUBTOTAL BID ITEMS $ 233,551.50 0 CONTRACT TOTAL ALL ITEMS $ 233,551.50 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2124031 MGR.NO. 053 PAGE 001 CONT 6224 SEC 28 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 622428001 HWY US0096 3304 US HWY 190 W JASPER CNTY JASPER DIST 20 CONTRACT PRICE $ 245,876.00 REPORT DATE 09/27/2012 10.26.22 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD APR 23,2012 TO SEP 18,2012 EST NO 006 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 122 RMC - 622428001 6224-28-001 233,551.50 .00 233,551.50 .00 .00 233,551.50 233,551.50 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 233,551.50 .00 233,551.50 .00 .00 233,551.50 233,551.50 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2124031 MGR.NO. 053 PAGE 001 CONT 6224 SEC 28 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 622428001 HWY US0096 3304 US HWY 190 W JASPER CNTY JASPER DIST 20 CONTRACT PRICE $ 245,876.00 REPORT DATE 09/27/2012 10.26.23 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD APR 23,2012 TO SEP 18,2012 EST NO 006 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6224-28-001 RMC - 622428001 20 US0096 JASPER -LIMITS - AT NECHES RIVER BRIDGE AND RELIEF BRIDGES - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 233,551.50