1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 3112008 MGR.NO. 053 PAGE 001 CONT 6223 SEC 86 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 622386001 HWY US0096 3304 US 190 WEST JASPER CNTY JASPER DIST 20 CONTRACT PRICE $ 6,134.22 REPORT DATE 04/26/2012 09.07.35 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2011 TO MAR 31,2012 EST NO 012 & FINAL BURKE CENTER 08985 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 01, 2011 TIME COMPUTED FROM APR 01, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 335 236 99 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAR 12 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 03/31/12 3 1 DAYS CHARGED TO DATE = 266 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 WORK COMPLETED AND ACCEPTED ----- ----- ----- 366 266 100 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 3112008 MGR.NO. 053 PAGE 001 CONT 6223 SEC 86 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 622386001 HWY US0096 3304 US 190 WEST JASPER CNTY JASPER DIST 20 CONTRACT PRICE $ 6,134.22 REPORT DATE 04/26/2012 09.07.35 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2011 TO MAR 31,2012 EST NO 012 & FINAL BURKE CENTER 08985 DIST. 20 COUNTY JASPER CONTROL 6223-86-001 PROJECT SUP - 622386001 HIGHWAY US0096 0LIMITS- US 96 FM 1007 0TYPE OF WORK- JASPER - PICNIC 0 0005 JASPER - PICNIC MAINTENANCE 0 0055 CREATED BY SUSAN WILL NET LENGTH 1.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0751 LITTER PICKUP (SITE A) CYC 52.000 52.000 46.160 2,400.32 0065 0745 GROUNDS MAINT-PICNIC MOW/TRIM-SITE (1) CYC 16.000 13.000 72.940 948.22 0070 0745 GROUNDS MAINT (MOWING/TRIMMING) CYC 1.000 0.000 72.940 .00 0075 0751 LEAF REMOVAL (SITE A) CYC 1.000 0.000 500.000 .00 0080 0745 GROUNDS MAINT-PICNIC MOW/TRIM-SITE (2) CYC 16.000 13.000 62.120 807.56 0085 0751 LEAF REMOVAL (SITE B) CYC 1.000 0.000 1,000.000 .00 0 SUBTOTAL BID ITEMS $ 4,156.10 0 TOTAL AMOUNT WORK DONE CREATED BY SUSAN WILL $ 4,156.10 0 TOTAL AMOUNT WORK DONE CONTROL 6223-86-001 $ 4,156.10 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 3112008 MGR.NO. 053 PAGE 001 CONT 6223 SEC 86 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 622386001 HWY US0096 3304 US 190 WEST JASPER CNTY JASPER DIST 20 CONTRACT PRICE $ 6,134.22 REPORT DATE 04/26/2012 09.07.35 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2011 TO MAR 31,2012 EST NO 012 & FINAL BURKE CENTER 08985 0*********************************************************************************************************************************** -LIMITS - US 96 0 FM 1007 DATE WORK BEGAN APR 1 , 2011 WORKING DAYS USED 266 PERCENT COMPLETE 100.00 PERCENT TIME USED 72.80 DATE COMPLETED MAR 31 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6223-86-001 SUP - 622386001 20 US0096 JASPER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0745 GROUNDS MAINT-PICNIC MOW/TRIM-SITE (1) CYC 16.000 13.000 72.940 948.22 0745 GROUNDS MAINT-PICNIC MOW/TRIM-SITE (2) CYC 16.000 13.000 62.120 807.56 0751 LITTER PICKUP (SITE A) CYC 52.000 52.000 46.160 2,400.32 0 SUBTOTAL BID ITEMS $ 4,156.10 0 CONTRACT TOTAL ALL ITEMS $ 4,156.10 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 3112008 MGR.NO. 053 PAGE 001 CONT 6223 SEC 86 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 622386001 HWY US0096 3304 US 190 WEST JASPER CNTY JASPER DIST 20 CONTRACT PRICE $ 6,134.22 REPORT DATE 04/26/2012 09.07.35 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2011 TO MAR 31,2012 EST NO 012 & FINAL BURKE CENTER 08985 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 122 SUP - 622386001 6223-86-001 4,156.10 .00 4,156.10 .00 .00 4,156.10 3,836.40 319.70 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 4,156.10 .00 4,156.10 .00 .00 4,156.10 3,836.40 319.70 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 3112008 MGR.NO. 053 PAGE 001 CONT 6223 SEC 86 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 622386001 HWY US0096 3304 US 190 WEST JASPER CNTY JASPER DIST 20 CONTRACT PRICE $ 6,134.22 REPORT DATE 04/26/2012 09.07.35 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2011 TO MAR 31,2012 EST NO 012 & FINAL BURKE CENTER 08985 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6223-86-001 SUP - 622386001 20 US0096 JASPER -LIMITS - US 96 FM 1007 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0745 GROUNDS MAINT-PICNIC CYC 16.000 1.000 72.940 72.94 MOW/TRIM-SITE (1) 80 0745 GROUNDS MAINT-PICNIC CYC 16.000 1.000 62.120 62.12 MOW/TRIM-SITE (2) 60 0751 LITTER PICKUP (SITE A) CYC 52.000 4.000 46.160 184.64 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 319.70 0 TOTAL AMOUNT WORK DONE TO DATE - $ 4,156.10