1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6094023 MGR.NO. 054 PAGE 001 CONT 6194 SEC 71 JOB 001 RES ENGR GBUR, STEPHEN PROJ RMC - 619471001 HWY SH0146 209 LAYL DR LIBERTY CNTY LIBERTY DIST 20 CONTRACT PRICE $ 413,629.42 REPORT DATE 02/08/2010 11.27.44 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD AUG 20,2009 TO JAN 31,2010 EST NO 006 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 20, 2009 TIME COMPUTED FROM AUG 20, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 30 134 47 87 BROUGHT FORWARD ADDL DAYS GRANTED = 3 JAN 10 1 1 HOLIDAY TOTAL DAYS ALLOWED = 33 2 1 SATURDAY DATE WORK COMPLETED 01/31/10 3 1 SUNDAY DAYS CHARGED TO DATE = 47 4 1 WORK SUSPENDED ASSESSED LIQ DAMAGES = 14 5 1 WORK SUSPENDED LIQ DAMAGE RATE $ 500 6 1 WORK SUSPENDED 7 1 WORK SUSPENDED LIQUIDATED DAMAGES 8 1 WORK SUSPENDED 14 DAYS AT $ 500 PER DAY 9 1 SATURDAY TOTAL = $ 7,000.00 10 1 SUNDAY 11 1 WORK SUSPENDED CERTIFIED AS CORRECT AND 12 1 WORK SUSPENDED ONE COPY HAS BEEN GIVEN 13 1 WORK SUSPENDED TO THE CONTRACTOR 14 1 WORK SUSPENDED 15 1 WORK SUSPENDED 16 1 SATURDAY ---------------------------- 17 1 SUNDAY AREA/PROJECT ENGINEER 18 1 WORK SUSPENDED 19 1 WORK SUSPENDED 20 1 WORK SUSPENDED 21 1 WORK SUSPENDED 22 1 WORK SUSPENDED 23 1 SATURDAY 24 1 SUNDAY 25 1 WORK SUSPENDED 26 1 WORK SUSPENDED 27 1 WORK SUSPENDED 28 1 WORK SUSPENDED 29 1 WORK SUSPENDED 30 1 SATURDAY 31 1 WORK COMPLETED AND ACCEPTED ----- ----- ----- 165 47 118 5 SATURDAY 4 SUNDAY 1 HOLIDAY 20 WORK SUSPENDED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6094023 MGR.NO. 054 PAGE 001 CONT 6194 SEC 71 JOB 001 RES ENGR GBUR, STEPHEN PROJ RMC - 619471001 HWY SH0146 209 LAYL DR LIBERTY CNTY LIBERTY DIST 20 CONTRACT PRICE $ 413,629.42 REPORT DATE 02/08/2010 11.27.45 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD AUG 20,2009 TO JAN 31,2010 EST NO 006 & FINAL DIST. 20 COUNTY LIBERTY CONTROL 6194-71-001 PROJECT RMC - 619471001 HIGHWAY SH0146 0LIMITS- SH146 IN LIBERTY AND CHAMBERS COUNTIES 0TYPE OF WORK- JOINT SEAL AND JOINT REPAIR 0 0005 THIS IS A JOINT CLEAN & SEAL PROJECT, S.GBUR, MGR 0 0055 CLEAN AND SEAL JOINTS NET LENGTH 5.880 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0340 D-GR HMA(METH) TY-D SAC-B PG70-22 TON 172.000 151.410 135.000 20,440.35 0065 0354 PLANE ASPH CONC PAV (1.5") SY 2,085.000 2,068.110 4.150 8,582.66 0070 0361 FULL-DEPTH REPAIR CPJR (11") SY 97.000 97.670 280.000 27,347.60 0075 0438 CLEAN EXIST JOINTS LF 164.000 92.000 10.000 920.00 0080 0438 CLEAN AND SEAL EXIST JOINTS LF 308,329.000 304,673.000 .810 246,785.13 0085 0438 CLEAN AND SEAL JOINTS LF 18,778.000 18,500.000 .810 14,985.00 0090 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 18,000.000 36,000.00 0095 3181 FIBER REINFORCED POLYMER PATCHING MTL LB 20,000.000 42,594.330 2.600 110,745.26 0 SUBTOTAL BID ITEMS $ 465,806.00 0 TOTAL AMOUNT WORK DONE CLEAN AND SEAL JOINTS $ 465,806.00 0 TOTAL AMOUNT WORK DONE CONTROL 6194-71-001 $ 465,806.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6094023 MGR.NO. 054 PAGE 001 CONT 6194 SEC 71 JOB 001 RES ENGR GBUR, STEPHEN PROJ RMC - 619471001 HWY SH0146 209 LAYL DR LIBERTY CNTY LIBERTY DIST 20 CONTRACT PRICE $ 413,629.42 REPORT DATE 02/08/2010 11.27.45 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD AUG 20,2009 TO JAN 31,2010 EST NO 006 & FINAL 0*********************************************************************************************************************************** -LIMITS - SH146 IN LIBERTY AND 0 CHAMBERS COUNTIES DATE WORK BEGAN AUG 20, 2009 WORKING DAYS USED 47 PERCENT COMPLETE 100.00 PERCENT TIME USED 142.40 DATE COMPLETED JAN 31 2010 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6194-71-001 RMC - 619471001 20 SH0146 LIBERTY - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0340 D-GR HMA(METH) TY-D SAC-B PG70-22 TON 172.000 151.410 135.000 20,440.35 0354 PLANE ASPH CONC PAV (1.5") SY 2,085.000 2,068.110 4.150 8,582.66 0361 FULL-DEPTH REPAIR CPJR (11") SY 97.000 97.670 280.000 27,347.60 0438 CLEAN EXIST JOINTS LF 164.000 92.000 10.000 920.00 0438 CLEAN AND SEAL EXIST JOINTS LF 308,329.000 304,673.000 .810 246,785.13 0438 CLEAN AND SEAL JOINTS LF 18,778.000 18,500.000 .810 14,985.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 18,000.000 36,000.00 3181 FIBER REINFORCED POLYMER PATCHING MTL LB 20,000.000 42,594.330 2.600 110,745.26 0 SUBTOTAL BID ITEMS $ 465,806.00 0 CONTRACT TOTAL ALL ITEMS $ 465,806.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6094023 MGR.NO. 054 PAGE 001 CONT 6194 SEC 71 JOB 001 RES ENGR GBUR, STEPHEN PROJ RMC - 619471001 HWY SH0146 209 LAYL DR LIBERTY CNTY LIBERTY DIST 20 CONTRACT PRICE $ 413,629.42 REPORT DATE 02/08/2010 11.27.45 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD AUG 20,2009 TO JAN 31,2010 EST NO 006 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 146 RMC - 619471001 6194-71-001 465,806.00 .00 465,806.00 .00 7,000.00 458,806.00 457,306.00 1,500.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 465,806.00 .00 465,806.00 .00 7,000.00 458,806.00 457,306.00 1,500.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6094023 MGR.NO. 054 PAGE 001 CONT 6194 SEC 71 JOB 001 RES ENGR GBUR, STEPHEN PROJ RMC - 619471001 HWY SH0146 209 LAYL DR LIBERTY CNTY LIBERTY DIST 20 CONTRACT PRICE $ 413,629.42 REPORT DATE 02/08/2010 11.27.45 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD AUG 20,2009 TO JAN 31,2010 EST NO 006 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6194-71-001 RMC - 619471001 20 SH0146 LIBERTY -LIMITS - SH146 IN LIBERTY AND CHAMBERS COUNTIES - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 465,806.00