1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5094013 MGR.NO. 056 PAGE 001 CONT 6192 SEC 93 JOB 001 RES ENGR BROWNING, DUANE PROJ RMC - 619293001 HWY SH0087 8450 US 69N BEAUMONT CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 471,679.58 REPORT DATE 10/07/2009 11.20.18 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 05,2009 TO SEP 21,2009 EST NO 002 & FINAL INC. 00644 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 05, 2009 TIME COMPUTED FROM AUG 05, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 30 27 14 13 BROUGHT FORWARD ADDL DAYS GRANTED = 0 SEP 09 1 1 TOTAL DAYS ALLOWED = 30 2 1 DATE WORK COMPLETED 09/21/09 3 1 DAYS CHARGED TO DATE = 21 4 1 ASSESSED LIQ DAMAGES = 0 5 1 SATURDAY LIQ DAMAGE RATE $ 500 6 1 SUNDAY 7 1 HOLIDAY LIQUIDATED DAMAGES 8 1 RAIN 0 DAYS AT $ 500 PER DAY 9 1 RAIN TOTAL = $ .00 10 1 RAIN 11 1 RAIN CERTIFIED AS CORRECT AND 12 1 SATURDAY ONE COPY HAS BEEN GIVEN 13 1 SUNDAY TO THE CONTRACTOR 14 1 RAIN 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 WORK COMPLETED 19 1 SATURDAY 20 1 SUNDAY 21 1 WORK ACCEPTED - - - 0 ----- ----- ----- 48 21 27 3 SATURDAY 3 SUNDAY 1 HOLIDAY 5 RAIN 1 WORK COMPLETED 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5094013 MGR.NO. 056 PAGE 001 CONT 6192 SEC 93 JOB 001 RES ENGR BROWNING, DUANE PROJ RMC - 619293001 HWY SH0087 8450 US 69N BEAUMONT CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 471,679.58 REPORT DATE 10/07/2009 11.20.19 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 05,2009 TO SEP 21,2009 EST NO 002 & FINAL INC. 00644 DIST. 20 COUNTY JEFFERSON CONTROL 6192-93-001 PROJECT RMC - 619293001 HIGHWAY SH0087 0LIMITS- FROM KEITH LAKE BRIDGE NORTH 5000' & AT ICWW BRIDGE SOUTH APPROACH 0TYPE OF WORK- FLEX PAVEMENT REPAIR & LEVEL-UP 0 0005 FLEXIBLE PAVEMENT STRUCTURE REPAIR 0 0055 PREPARED BY VADA BYFORD 2-5-09 NET LENGTH 1.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0134 BACKFILL (TY B) STA 2.000 2.000 1,000.000 2,000.00 0065 0316 ASPH (AC-20-5TR) TON 29.310 29.310 900.000 26,379.00 0070 0316 AGGR (TY-PB GR-4) CY 162.000 171.000 160.000 27,360.00 0075 0340 D-GR HMA(METH) TY-A PG64-22 TON 515.000 196.450 80.000 15,716.00 0075 0340 ADJ EST QUANTITY TO DATE 340.000 0076 0340*D-GR HMA(METH) TY-D PG64-22 TON 175.000 136.880 86.000 11,771.68 0080 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") SY 6,667.000 6,658.670 54.000 359,568.18 0085 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 2,500.000 5,000.00 0090 0540 TRANSITION ADJUSTMENT EA 2.000 2.000 1,000.000 2,000.00 0095 0540 MTL BEAM GD FEN (MOVE AND RESET) LF 200.000 200.000 4.000 800.00 0100 0544 GUARDRAIL END TREATMENT (MOVE & RESET) EA 2.000 2.000 1,000.000 2,000.00 0105 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 1,075.000 1,075.000 1.000 1,075.00 0110 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 10,400.000 10,400.000 .300 3,120.00 0115 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 1,100.000 1,100.000 .340 374.00 0120 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 4,144.000 4,144.000 .320 1,326.08 0125 0672 REFL PAV MRKR TY II-A-A EA 110.000 110.000 4.250 467.50 0 SUBTOTAL BID ITEMS $ 458,957.44 0 TOTAL AMOUNT WORK DONE PREPARED BY VADA BYFORD 2-5-09 $ 458,957.44 1 TOTAL AMOUNT WORK DONE CONTROL 6192-93-001 $ 458,957.44 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5094013 MGR.NO. 056 PAGE 001 CONT 6192 SEC 93 JOB 001 RES ENGR BROWNING, DUANE PROJ RMC - 619293001 HWY SH0087 8450 US 69N BEAUMONT CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 471,679.58 REPORT DATE 10/07/2009 11.20.19 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 05,2009 TO SEP 21,2009 EST NO 002 & FINAL INC. 00644 0*********************************************************************************************************************************** -LIMITS - FROM KEITH LAKE BRIDGE NORTH 5000' 0 & AT ICWW BRIDGE SOUTH APPROACH DATE WORK BEGAN AUG 5 , 2009 WORKING DAYS USED 21 PERCENT COMPLETE 100.00 PERCENT TIME USED 70.00 DATE COMPLETED SEP 21 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6192-93-001 RMC - 619293001 20 SH0087 JEFFERSON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0134 BACKFILL (TY B) STA 2.000 2.000 1,000.000 2,000.00 0316 ASPH (AC-20-5TR) TON 29.310 29.310 900.000 26,379.00 0316 AGGR (TY-PB GR-4) CY 162.000 171.000 160.000 27,360.00 0340 D-GR HMA(METH) TY-A PG64-22 TON 515.000 196.450 80.000 15,716.00 0340 ADJ EST QUANTITY TO DATE 340.000 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") SY 6,667.000 6,658.670 54.000 359,568.18 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 2,500.000 5,000.00 0540 TRANSITION ADJUSTMENT EA 2.000 2.000 1,000.000 2,000.00 0540 MTL BEAM GD FEN (MOVE AND RESET) LF 200.000 200.000 4.000 800.00 0544 GUARDRAIL END TREATMENT (MOVE & RESET) EA 2.000 2.000 1,000.000 2,000.00 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 1,075.000 1,075.000 1.000 1,075.00 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 10,400.000 10,400.000 .300 3,120.00 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 1,100.000 1,100.000 .340 374.00 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 4,144.000 4,144.000 .320 1,326.08 0672 REFL PAV MRKR TY II-A-A EA 110.000 110.000 4.250 467.50 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 10340* D-GR HMA(METH) TY-D PG64-22 TON 175.000 136.880 86.000 11,771.68 0 SUBTOTAL BID ITEMS $ 458,957.44 0 CONTRACT TOTAL ALL ITEMS $ 458,957.44 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5094013 MGR.NO. 056 PAGE 001 CONT 6192 SEC 93 JOB 001 RES ENGR BROWNING, DUANE PROJ RMC - 619293001 HWY SH0087 8450 US 69N BEAUMONT CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 471,679.58 REPORT DATE 10/07/2009 11.20.19 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 05,2009 TO SEP 21,2009 EST NO 002 & FINAL INC. 00644 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 124 RMC - 619293001 6192-93-001 458,957.44 .00 458,957.44 .00 .00 458,957.44 378,255.18 80,702.26 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 458,957.44 .00 458,957.44 .00 .00 458,957.44 378,255.18 80,702.26 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5094013 MGR.NO. 056 PAGE 001 CONT 6192 SEC 93 JOB 001 RES ENGR BROWNING, DUANE PROJ RMC - 619293001 HWY SH0087 8450 US 69N BEAUMONT CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 471,679.58 REPORT DATE 10/07/2009 11.20.19 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 05,2009 TO SEP 21,2009 EST NO 002 & FINAL INC. 00644 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6192-93-001 RMC - 619293001 20 SH0087 JEFFERSON -LIMITS - FROM KEITH LAKE BRIDGE NORTH 5000' & AT ICWW BRIDGE SOUTH APPROACH LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0134 BACKFILL (TY B) STA 2.000 2.000 1,000.000 2,000.00 65 0316 ASPH (AC-20-5TR) TON 29.310 29.310 900.000 26,379.00 70 0316 AGGR (TY-PB GR-4) CY 162.000 171.000 160.000 27,360.00 85 0502 BARRICADES, SIGNS AND MO 2.000 1.000 2,500.000 2,500.00 TRAFFIC HANDLING 90 0540 TRANSITION ADJUSTMENT EA 2.000 2.000 1,000.000 2,000.00 95 0540 MTL BEAM GD FEN (MOVE AND LF 200.000 200.000 4.000 800.00 RESET) 100 0544 GUARDRAIL END TREATMENT EA 2.000 2.000 1,000.000 2,000.00 (MOVE & RESET) 105 0662 WK ZN PAV MRK SHT TERM (TAB) EA 1,075.000 604.000 1.000 604.00 TY Y-2 110 0666 REFL PAV MRK TY I (W) 4" LF 10,400.000 10,400.000 0.300 3,120.00 (SLD)(100MIL) 115 0666 REFL PAV MRK TY I (Y) 4" LF 1,100.000 1,100.000 0.340 374.00 (BRK)(100MIL) 120 0666 REFL PAV MRK TY I (Y) 4" LF 4,144.000 4,144.000 0.320 1,326.08 (SLD)(100MIL) 125 0672 REFL PAV MRKR TY II-A-A EA 110.000 110.000 4.250 467.50 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 76 0340* D-GR HMA(METH) TY-D PG64-22 TON 0.000 136.880 86.000 11,771.68 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 80,702.26 0 TOTAL AMOUNT WORK DONE TO DATE - $ 458,957.44