1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6094011 MGR.NO. 055 PAGE 001 CONT 6188 SEC 95 JOB 001 RES ENGR SLACUM, CLARK PROJ RMC - 618895001 HWY SH0012 3128 HWY 62 N ORANGE CNTY ORANGE DIST 20 CONTRACT PRICE $ 496,775.00 REPORT DATE 09/21/2009 08.33.46 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 03,2009 TO AUG 28,2009 EST NO 002 & FINAL INC. 00644 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 03, 2009 TIME COMPUTED FROM AUG 03, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 105 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 09 TOTAL DAYS ALLOWED = 105 DATE WORK COMPLETED 08/28/09 3 1 DAYS CHARGED TO DATE = 25 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 500 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 500 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 WORK COMPLETED AND ACCEPTED - ----- ----- ----- 26 25 1 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6094011 MGR.NO. 055 PAGE 001 CONT 6188 SEC 95 JOB 001 RES ENGR SLACUM, CLARK PROJ RMC - 618895001 HWY SH0012 3128 HWY 62 N ORANGE CNTY ORANGE DIST 20 CONTRACT PRICE $ 496,775.00 REPORT DATE 09/21/2009 08.33.46 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 03,2009 TO AUG 28,2009 EST NO 002 & FINAL INC. 00644 DIST. 20 COUNTY ORANGE CONTROL 6188-95-001 PROJECT RMC - 618895001 HIGHWAY SH0012 0LIMITS- VARIOUS HIGHWAYS IN ORANGE, JASPER, NEWTON COUNTIES 0TYPE OF WORK- ASPHALT BASE AND PAVEMENT 0 0005 BASE REPAIR 0 0055 ROADWAY NET LENGTH 1.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") SY 6,500.000 1,127.000 76.150 85,821.05 0065 0506 BACKHOE WORK (EROSION & SEDM CONT) HR 10.000 0.000 50.000 .00 0070 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 400.000 18.000 1.000 18.00 0075 0662 WK ZN PAV MRK SHT TERM (TAB) TY W EA 400.000 0.000 1.000 .00 0080 5049 BIODGRD EROSION CONTROL LOGS (18" DIA) LF 100.000 0.000 5.000 .00 0 SUBTOTAL BID ITEMS $ 85,839.05 0 TOTAL AMOUNT WORK DONE ROADWAY $ 85,839.05 0 TOTAL AMOUNT WORK DONE CONTROL 6188-95-001 $ 85,839.05 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6094011 MGR.NO. 055 PAGE 001 CONT 6188 SEC 95 JOB 001 RES ENGR SLACUM, CLARK PROJ RMC - 618895001 HWY SH0012 3128 HWY 62 N ORANGE CNTY ORANGE DIST 20 CONTRACT PRICE $ 496,775.00 REPORT DATE 09/21/2009 08.33.47 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 03,2009 TO AUG 28,2009 EST NO 002 & FINAL INC. 00644 0*********************************************************************************************************************************** -LIMITS - VARIOUS HIGHWAYS IN 0 ORANGE, JASPER, NEWTON COUNTIES DATE WORK BEGAN AUG 3 , 2009 WORKING DAYS USED 25 PERCENT COMPLETE 100.00 PERCENT TIME USED 23.80 DATE COMPLETED AUG 28 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6188-95-001 RMC - 618895001 20 SH0012 ORANGE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") SY 6,500.000 1,127.000 76.150 85,821.05 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 400.000 18.000 1.000 18.00 0 SUBTOTAL BID ITEMS $ 85,839.05 0 CONTRACT TOTAL ALL ITEMS $ 85,839.05 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6094011 MGR.NO. 055 PAGE 001 CONT 6188 SEC 95 JOB 001 RES ENGR SLACUM, CLARK PROJ RMC - 618895001 HWY SH0012 3128 HWY 62 N ORANGE CNTY ORANGE DIST 20 CONTRACT PRICE $ 496,775.00 REPORT DATE 09/21/2009 08.33.47 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 03,2009 TO AUG 28,2009 EST NO 002 & FINAL INC. 00644 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 181 RMC - 618895001 6188-95-001 85,839.05 .00 85,839.05 .00 .00 85,839.05 85,839.05 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 85,839.05 .00 85,839.05 .00 .00 85,839.05 85,839.05 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6094011 MGR.NO. 055 PAGE 001 CONT 6188 SEC 95 JOB 001 RES ENGR SLACUM, CLARK PROJ RMC - 618895001 HWY SH0012 3128 HWY 62 N ORANGE CNTY ORANGE DIST 20 CONTRACT PRICE $ 496,775.00 REPORT DATE 09/21/2009 08.33.47 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 03,2009 TO AUG 28,2009 EST NO 002 & FINAL INC. 00644 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6188-95-001 RMC - 618895001 20 SH0012 ORANGE -LIMITS - VARIOUS HIGHWAYS IN ORANGE, JASPER, NEWTON COUNTIES - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 85,839.05