1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 10082011 MGR.NO. 051 PAGE 001 CONT 6188 SEC 33 JOB 001 RES ENGR BROWNING, DUANE PROJ EMC - 618833001 HWY US0190 8450 EASTEX FRWY BEAUMONT CNTY TYLER DIST 20 CONTRACT PRICE $ 169,997.52 REPORT DATE 11/20/2008 11.07.18 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD OCT 25,2008 TO OCT 30,2008 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 25, 2008 TIME COMPUTED FROM OCT 25, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 30 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 08 TOTAL DAYS ALLOWED = 30 DATE WORK COMPLETED 10/30/08 DAYS CHARGED TO DATE = 5 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 0 0 LIQUIDATED DAMAGES 0 DAYS AT $ 0 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - 0 25 1 TIME BEGAN/WORK BEGAN 26 1 SUNDAY 27 1 28 1 29 1 30 1 WORK COMPLETE AND ACCEPTED 0 ----- ----- ----- 6 5 1 0 SATURDAY 1 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 10082011 MGR.NO. 051 PAGE 001 CONT 6188 SEC 33 JOB 001 RES ENGR BROWNING, DUANE PROJ EMC - 618833001 HWY US0190 8450 EASTEX FRWY BEAUMONT CNTY TYLER DIST 20 CONTRACT PRICE $ 169,997.52 REPORT DATE 11/20/2008 11.07.18 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD OCT 25,2008 TO OCT 30,2008 EST NO 002 & FINAL DIST. 20 COUNTY TYLER CONTROL 6188-33-001 PROJECT EMC - 618833001 HIGHWAY US0190 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- EMERGENCY DEBRIS REMOVAL HURRICANE IKE 0 0005 DEBRIS REMOVAL TYLER CO. HURRICANE IKE 0 0055 ROADWAY NET LENGTH 1.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 7425 DEBRIS REMOVAL/DISPOSAL-HURRICANE I MI 173.955 173.955 977.250 169,997.52 0065 7425*DEBRIS REMOVAL/DISPOSAL-HURRICANE I MI 30.500 30.500 2,295.080 69,999.94 0 SUBTOTAL BID ITEMS $ 239,997.46 0 TOTAL AMOUNT WORK DONE ROADWAY $ 239,997.46 0 TOTAL AMOUNT WORK DONE CONTROL 6188-33-001 $ 239,997.46 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 10082011 MGR.NO. 051 PAGE 001 CONT 6188 SEC 33 JOB 001 RES ENGR BROWNING, DUANE PROJ EMC - 618833001 HWY US0190 8450 EASTEX FRWY BEAUMONT CNTY TYLER DIST 20 CONTRACT PRICE $ 169,997.52 REPORT DATE 11/20/2008 11.07.18 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD OCT 25,2008 TO OCT 30,2008 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN OCT 25, 2008 WORKING DAYS USED 5 PERCENT COMPLETE 100.00 PERCENT TIME USED 16.60 DATE COMPLETED OCT 30 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6188-33-001 EMC - 618833001 20 US0190 TYLER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -7425 DEBRIS REMOVAL/DISPOSAL-HURRICANE I MI 173.955 173.955 977.250 169,997.52 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 07425* DEBRIS REMOVAL/DISPOSAL-HURRICANE I MI 30.500 30.500 2,295.080 69,999.94 0 SUBTOTAL BID ITEMS $ 239,997.46 0 CONTRACT TOTAL ALL ITEMS $ 239,997.46 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 10082011 MGR.NO. 051 PAGE 001 CONT 6188 SEC 33 JOB 001 RES ENGR BROWNING, DUANE PROJ EMC - 618833001 HWY US0190 8450 EASTEX FRWY BEAUMONT CNTY TYLER DIST 20 CONTRACT PRICE $ 169,997.52 REPORT DATE 11/20/2008 11.07.18 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD OCT 25,2008 TO OCT 30,2008 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 229 EMC - 618833001 6188-33-001 239,997.46 .00 239,997.46 .00 .00 239,997.46 239,997.46 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 239,997.46 .00 239,997.46 .00 .00 239,997.46 239,997.46 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 10082011 MGR.NO. 051 PAGE 001 CONT 6188 SEC 33 JOB 001 RES ENGR BROWNING, DUANE PROJ EMC - 618833001 HWY US0190 8450 EASTEX FRWY BEAUMONT CNTY TYLER DIST 20 CONTRACT PRICE $ 169,997.52 REPORT DATE 11/20/2008 11.07.19 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD OCT 25,2008 TO OCT 30,2008 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6188-33-001 EMC - 618833001 20 US0190 TYLER -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 239,997.46