1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4082003 MGR.NO. 056 PAGE 001 CONT 6175 SEC 34 JOB 001 RES ENGR AYERS, SCOTT PROJ RMC - 617534001 HWY SH0347 6101 TWIN CITY HWY PORT A CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 157,971.25 REPORT DATE 07/29/2008 15.30.44 CONTRACTOR SCODELLER CONSTRUCTION, INC. 6998 EST PERIOD JUN 03,2008 TO JUN 20,2008 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 03, 2008 TIME COMPUTED FROM JUN 03, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 45 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUN 08 TOTAL DAYS ALLOWED = 45 DATE WORK COMPLETED 06/20/08 3 1 DAYS CHARGED TO DATE = 12 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 400 6 1 7 1 LIQUIDATED DAMAGES 8 1 SUNDAY 0 DAYS AT $ 400 PER DAY 9 1 TOTAL = $ .00 10 1 RAIN 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 SATURDAY 15 1 SUNDAY 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 WORK COMPLETED 20 1 WORK ACCEPTED - - - - ----- ----- ----- 18 12 6 1 SATURDAY 2 SUNDAY 0 HOLIDAY 1 RAIN 1 WORK COMPLETED 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4082003 MGR.NO. 056 PAGE 001 CONT 6175 SEC 34 JOB 001 RES ENGR AYERS, SCOTT PROJ RMC - 617534001 HWY SH0347 6101 TWIN CITY HWY PORT A CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 157,971.25 REPORT DATE 07/29/2008 15.30.45 CONTRACTOR SCODELLER CONSTRUCTION, INC. 6998 EST PERIOD JUN 03,2008 TO JUN 20,2008 EST NO 002 & FINAL DIST. 20 COUNTY JEFFERSON CONTROL 6175-34-001 PROJECT RMC - 617534001 HIGHWAY SH0347 0LIMITS- SH 87 SH 73 0TYPE OF WORK- JOINT SEAL 0 0005 JOINT SEAL 0 0055 ROADWAY NET LENGTH 1.717 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0438 CLEAN AND SEAL JOINTS LF 116,777.000 120,528.800 1.250 150,661.00 0065 0500 MOBILIZATION LS 1.000 1.000 3,000.000 3,000.00 0070 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 3,000.000 9,000.00 0 SUBTOTAL BID ITEMS $ 162,661.00 0 TOTAL AMOUNT WORK DONE ROADWAY $ 162,661.00 0 TOTAL AMOUNT WORK DONE CONTROL 6175-34-001 $ 162,661.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4082003 MGR.NO. 056 PAGE 001 CONT 6175 SEC 34 JOB 001 RES ENGR AYERS, SCOTT PROJ RMC - 617534001 HWY SH0347 6101 TWIN CITY HWY PORT A CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 157,971.25 REPORT DATE 07/29/2008 15.30.45 CONTRACTOR SCODELLER CONSTRUCTION, INC. 6998 EST PERIOD JUN 03,2008 TO JUN 20,2008 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - SH 87 0 SH 73 DATE WORK BEGAN JUN 3 , 2008 WORKING DAYS USED 12 PERCENT COMPLETE 100.00 PERCENT TIME USED 26.60 DATE COMPLETED JUN 20 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6175-34-001 RMC - 617534001 20 SH0347 JEFFERSON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0438 CLEAN AND SEAL JOINTS LF 116,777.000 120,528.800 1.250 150,661.00 0500 MOBILIZATION LS 1.000 1.000 3,000.000 3,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 3,000.000 9,000.00 0 SUBTOTAL BID ITEMS $ 162,661.00 0 CONTRACT TOTAL ALL ITEMS $ 162,661.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4082003 MGR.NO. 056 PAGE 001 CONT 6175 SEC 34 JOB 001 RES ENGR AYERS, SCOTT PROJ RMC - 617534001 HWY SH0347 6101 TWIN CITY HWY PORT A CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 157,971.25 REPORT DATE 07/29/2008 15.30.46 CONTRACTOR SCODELLER CONSTRUCTION, INC. 6998 EST PERIOD JUN 03,2008 TO JUN 20,2008 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 124 RMC - 617534001 6175-34-001 162,661.00 .00 162,661.00 .00 .00 162,661.00 162,661.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 162,661.00 .00 162,661.00 .00 .00 162,661.00 162,661.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4082003 MGR.NO. 056 PAGE 001 CONT 6175 SEC 34 JOB 001 RES ENGR AYERS, SCOTT PROJ RMC - 617534001 HWY SH0347 6101 TWIN CITY HWY PORT A CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 157,971.25 REPORT DATE 07/29/2008 15.30.46 CONTRACTOR SCODELLER CONSTRUCTION, INC. 6998 EST PERIOD JUN 03,2008 TO JUN 20,2008 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6175-34-001 RMC - 617534001 20 SH0347 JEFFERSON -LIMITS - SH 87 SH 73 - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 162,661.00