1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1082001 MGR.NO. 051 PAGE 001 CONT 6173 SEC 23 JOB 001 RES ENGR BROWNING, DUANE PROJ BPM - 617323001 HWY US0069 8450 EASTEX FRWY BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 57,310.75 REPORT DATE 04/14/2008 13.10.13 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD MAR 05,2008 TO MAR 18,2008 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAR 05, 2008 TIME COMPUTED FROM MAR 05, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 15 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAR 08 TOTAL DAYS ALLOWED = 15 DATE WORK COMPLETED 03/18/08 DAYS CHARGED TO DATE = 5 ASSESSED LIQ DAMAGES = 0 5 1 TIME BEGAN- WORK BEGAN LIQ DAMAGE RATE $ 400 6 1 7 1 RAIN LIQUIDATED DAMAGES 8 1 SATURDAY 0 DAYS AT $ 400 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 RAIN 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 WORK COMPLETED 15 1 WORK COMPLETED 16 1 WORK COMPLETED ---------------------------- 17 1 WORK COMPLETED AREA/PROJECT ENGINEER 18 1 WORK COMPLETED AND ACCEPTED - - - - 0 ----- ----- ----- 14 5 9 1 SATURDAY 1 SUNDAY 0 HOLIDAY 2 RAIN 4 WORK COMPLETED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1082001 MGR.NO. 051 PAGE 001 CONT 6173 SEC 23 JOB 001 RES ENGR BROWNING, DUANE PROJ BPM - 617323001 HWY US0069 8450 EASTEX FRWY BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 57,310.75 REPORT DATE 04/14/2008 13.10.14 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD MAR 05,2008 TO MAR 18,2008 EST NO 002 & FINAL DIST. 20 COUNTY HARDIN CONTROL 6173-23-001 PROJECT BPM - 617323001 HIGHWAY US0069 0LIMITS- DISTRICTWIDE DISTRICTWIDE 0TYPE OF WORK- TREAT DETERIORATING BEAM & REPAIR COLUMN 0 0050 ROUTINE PREVENTIVE MAINTENANCE NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0055 0500 MOBILIZATION LS 1.000 1.000 26,000.000 26,000.00 0060 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 11,000.000 11,000.00 0065 4124 TRT FOR PREMATURE CONC DETERIORATION SF 5,217.000 5,217.000 2.750 14,346.75 0070 4191 CARBON FIBER REINF POLY CONC STRENGTHEN SF 213.000 213.000 28.000 5,964.00 0 SUBTOTAL BID ITEMS $ 57,310.75 0 TOTAL AMOUNT WORK DONE ROUTINE PREVENTIVE MAINTENANCE $ 57,310.75 0 TOTAL AMOUNT WORK DONE CONTROL 6173-23-001 $ 57,310.75 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1082001 MGR.NO. 051 PAGE 001 CONT 6173 SEC 23 JOB 001 RES ENGR BROWNING, DUANE PROJ BPM - 617323001 HWY US0069 8450 EASTEX FRWY BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 57,310.75 REPORT DATE 04/14/2008 13.10.14 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD MAR 05,2008 TO MAR 18,2008 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - DISTRICTWIDE 0 DISTRICTWIDE DATE WORK BEGAN MAR 5 , 2008 WORKING DAYS USED 5 PERCENT COMPLETE 100.00 PERCENT TIME USED 33.30 DATE COMPLETED MAR 18 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6173-23-001 BPM - 617323001 20 US0069 HARDIN - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0500 MOBILIZATION LS 1.000 1.000 26,000.000 26,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 11,000.000 11,000.00 4124 TRT FOR PREMATURE CONC DETERIORATION SF 5,217.000 5,217.000 2.750 14,346.75 4191 CARBON FIBER REINF POLY CONC STRENGTHEN SF 213.000 213.000 28.000 5,964.00 0 SUBTOTAL BID ITEMS $ 57,310.75 0 CONTRACT TOTAL ALL ITEMS $ 57,310.75 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1082001 MGR.NO. 051 PAGE 001 CONT 6173 SEC 23 JOB 001 RES ENGR BROWNING, DUANE PROJ BPM - 617323001 HWY US0069 8450 EASTEX FRWY BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 57,310.75 REPORT DATE 04/14/2008 13.10.14 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD MAR 05,2008 TO MAR 18,2008 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 101 BPM - 617323001 6173-23-001 57,310.75 .00 57,310.75 .00 .00 57,310.75 56,530.75 780.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 57,310.75 .00 57,310.75 .00 .00 57,310.75 56,530.75 780.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1082001 MGR.NO. 051 PAGE 001 CONT 6173 SEC 23 JOB 001 RES ENGR BROWNING, DUANE PROJ BPM - 617323001 HWY US0069 8450 EASTEX FRWY BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 57,310.75 REPORT DATE 04/14/2008 13.10.14 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD MAR 05,2008 TO MAR 18,2008 EST NO 002 & FINAL ********************************************************************************************************** - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6173-23-001 BPM - 617323001 20 US0069 HARDIN -LIMITS - DISTRICTWIDE DISTRICTWIDE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 00500 MOBILIZATION LS 1.000 0.030 26,000.000 780.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 780.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 57,310.75