1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4121430 MGR.NO. 055 PAGE 001 CONT 6243 SEC 24 JOB 001 RES ENGR WAGNER,JOHN PROJ SUP - 624324001 HWY US0290 2727 S AUSTIN AVE GEORGET CNTY TRAVIS DIST 14 CONTRACT PRICE $ 231,277.92 REPORT DATE 05/02/2013 08.52.49 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 012 EASTER-SEALS CENTRAL TEXAS, INC. 10984 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 01, 2012 TIME COMPUTED FROM MAY 08, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 730 335 335 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 13 1 1 TOTAL DAYS ALLOWED = 730 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 365 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 365 365 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4121430 MGR.NO. 055 PAGE 001 CONT 6243 SEC 24 JOB 001 RES ENGR WAGNER,JOHN PROJ SUP - 624324001 HWY US0290 2727 S AUSTIN AVE GEORGET CNTY TRAVIS DIST 14 CONTRACT PRICE $ 231,277.92 REPORT DATE 05/02/2013 08.52.49 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 012 EASTER-SEALS CENTRAL TEXAS, INC. 10984 DIST. 14 COUNTY TRAVIS CONTROL 6243-24-001 PROJECT SUP - 624324001 HIGHWAY US0290 0LIMITS- VARIOUS LOCATIONS IN TRAVIS COUNTY . 0TYPE OF WORK- LITTER REMOVAL 0 0005 PREPARED BY LORI WAGNER 0 0055 LTTER PICK UP & DISPOSAL NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL - TRACT (1) AC 488.000 351.000 21.300 7,476.30 0065 0734 LITTER REMOVAL - TRACT (2) AC 1,064.000 399.000 13.150 5,246.85 0070 0734 LITTER REMOVAL - TRACT (3) AC 2,808.000 1,404.000 13.590 19,080.36 0075 0734 LITTER REMOVAL - TRACT (4) AC 4,368.000 2,182.000 12.100 26,402.20 0080 0734 LITTER REMOVAL - TRACT (5) AC 4,056.000 2,028.000 11.530 23,382.84 0085 0734 LITTER REMOVAL - TRACT (6) AC 720.000 360.000 20.170 7,261.20 0090 0734 LITTER REMOVAL - TRACT (7) AC 568.000 284.000 9.210 2,615.64 0095 0734 LITTER REMOVAL - TRACT (9) AC 1,264.000 790.000 9.280 7,331.20 0100 0734 LITTER REMOVAL - TRACT (10) AC 144.000 48.000 18.350 880.80 0105 0734 LITTER REMOVAL - TRACT (11) AC 672.000 0.000 7.350 .00 0110 0734 LITTER REMOVAL - TRACT (12) AC 432.000 180.000 19.260 3,466.80 0115 0734 LITTER REMOVAL - TRACT (13) AC 480.000 160.000 28.480 4,556.80 0120 0734 LITTER REMOVAL - TRACT (16) AC 720.000 360.000 11.190 4,028.40 0125 9000*LITTER REMOVAL TRACT 17 AC 2,120.000 742.000 12.580 9,334.36 0 SUBTOTAL BID ITEMS $ 121,063.75 0 TOTAL AMOUNT WORK DONE LTTER PICK UP & DISPOSAL $ 121,063.75 0 TOTAL AMOUNT WORK DONE CONTROL 6243-24-001 $ 121,063.75 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4121430 MGR.NO. 055 PAGE 001 CONT 6243 SEC 24 JOB 001 RES ENGR WAGNER,JOHN PROJ SUP - 624324001 HWY US0290 2727 S AUSTIN AVE GEORGET CNTY TRAVIS DIST 14 CONTRACT PRICE $ 231,277.92 REPORT DATE 05/02/2013 08.52.50 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 012 EASTER-SEALS CENTRAL TEXAS, INC. 10984 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN TRAVIS COUNTY 0 . DATE WORK BEGAN MAY 1 , 2012 WORKING DAYS USED 365 PERCENT COMPLETE 52.34 PERCENT TIME USED 50.00 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6243-24-001 SUP - 624324001 14 US0290 TRAVIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL - TRACT (1) AC 488.000 351.000 21.300 7,476.30 0734 LITTER REMOVAL - TRACT (2) AC 1,064.000 399.000 13.150 5,246.85 0734 LITTER REMOVAL - TRACT (3) AC 2,808.000 1,404.000 13.590 19,080.36 0734 LITTER REMOVAL - TRACT (4) AC 4,368.000 2,182.000 12.100 26,402.20 0734 LITTER REMOVAL - TRACT (5) AC 4,056.000 2,028.000 11.530 23,382.84 0734 LITTER REMOVAL - TRACT (6) AC 720.000 360.000 20.170 7,261.20 0734 LITTER REMOVAL - TRACT (7) AC 568.000 284.000 9.210 2,615.64 0734 LITTER REMOVAL - TRACT (9) AC 1,264.000 790.000 9.280 7,331.20 0734 LITTER REMOVAL - TRACT (10) AC 144.000 48.000 18.350 880.80 0734 LITTER REMOVAL - TRACT (12) AC 432.000 180.000 19.260 3,466.80 0734 LITTER REMOVAL - TRACT (13) AC 480.000 160.000 28.480 4,556.80 0734 LITTER REMOVAL - TRACT (16) AC 720.000 360.000 11.190 4,028.40 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09000* LITTER REMOVAL TRACT 17 AC 2,120.000 742.000 12.580 9,334.36 0 SUBTOTAL BID ITEMS $ 121,063.75 0 CONTRACT TOTAL ALL ITEMS $ 121,063.75 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4121430 MGR.NO. 055 PAGE 001 CONT 6243 SEC 24 JOB 001 RES ENGR WAGNER,JOHN PROJ SUP - 624324001 HWY US0290 2727 S AUSTIN AVE GEORGET CNTY TRAVIS DIST 14 CONTRACT PRICE $ 231,277.92 REPORT DATE 05/02/2013 08.52.50 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 012 EASTER-SEALS CENTRAL TEXAS, INC. 10984 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 227 SUP - 624324001 6243-24-001 121,063.75 .00 121,063.75 .00 .00 121,063.75 113,048.67 8,015.08 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 121,063.75 .00 121,063.75 .00 .00 121,063.75 113,048.67 8,015.08 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4121430 MGR.NO. 055 PAGE 001 CONT 6243 SEC 24 JOB 001 RES ENGR WAGNER,JOHN PROJ SUP - 624324001 HWY US0290 2727 S AUSTIN AVE GEORGET CNTY TRAVIS DIST 14 CONTRACT PRICE $ 231,277.92 REPORT DATE 05/02/2013 08.52.50 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 012 EASTER-SEALS CENTRAL TEXAS, INC. 10984 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6243-24-001 SUP - 624324001 14 US0290 TRAVIS -LIMITS - VARIOUS LOCATIONS IN TRAVIS COUNTY . LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 70 0734 LITTER REMOVAL - TRACT (3) AC 2,808.000 117.000 13.590 1,590.03 75 0734 LITTER REMOVAL - TRACT (4) AC 4,368.000 182.000 12.100 2,202.20 80 0734 LITTER REMOVAL - TRACT (5) AC 4,056.000 169.000 11.530 1,948.57 85 0734 LITTER REMOVAL - TRACT (6) AC 720.000 30.000 20.170 605.10 120 0734 LITTER REMOVAL - TRACT (16) AC 720.000 30.000 11.190 335.70 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 125 9000* LITTER REMOVAL TRACT 17 AC 0.000 106.000 12.580 1,333.48 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 8,015.08 0 TOTAL AMOUNT WORK DONE TO DATE - $ 121,063.75