1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4121431 MGR.NO. 055 PAGE 001 CONT 6243 SEC 18 JOB 001 RES ENGR WAGNER,JOHN PROJ SUP - 624318001 HWY FM0487 2727 S AUSTIN AVE GEORGET CNTY WILLIAMSON DIST 14 CONTRACT PRICE $ 123,732.04 REPORT DATE 05/01/2013 08.48.03 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 012 EASTER-SEALS CENTRAL TEXAS, INC. 10984 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 22, 2012 TIME COMPUTED FROM MAY 21, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 731 315 315 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 13 1 1 TOTAL DAYS ALLOWED = 731 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 345 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 345 345 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4121431 MGR.NO. 055 PAGE 001 CONT 6243 SEC 18 JOB 001 RES ENGR WAGNER,JOHN PROJ SUP - 624318001 HWY FM0487 2727 S AUSTIN AVE GEORGET CNTY WILLIAMSON DIST 14 CONTRACT PRICE $ 123,732.04 REPORT DATE 05/01/2013 08.48.04 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 012 EASTER-SEALS CENTRAL TEXAS, INC. 10984 DIST. 14 COUNTY WILLIAMSON CONTROL 6243-18-001 PROJECT SUP - 624318001 HIGHWAY FM0487 0LIMITS- VARIOUS LOCATIONS IN WILLIAMSON COUNTY 0TYPE OF WORK- LITTER REMOVAL 0 0005 PREPARED BY LORI WAGNER 0 0055 LITTER PICK UP AND DISPOSAL NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL - TRACT (1) AC 798.000 363.000 8.960 3,252.48 0065 0734 LITTER REMOVAL - TRACT (2) AC 80.000 0.000 11.600 .00 0070 0734 LITTER REMOVAL - TRACT (3) AC 72.000 36.000 26.240 944.64 0075 0734 LITTER REMOVAL - TRACT (4) AC 192.000 63.000 15.600 982.80 0080 0734 LITTER REMOVAL - TRACT (5) AC 116.000 58.000 7.110 412.38 0085 0734 LITTER REMOVAL - TRACT (6) AC 420.000 104.000 9.250 962.00 0090 0734 LITTER REMOVAL - TRACT (7) AC 192.000 96.000 13.290 1,275.84 0095 0734 LITTER REMOVAL - TRACT (8) AC 136.000 68.000 8.760 595.68 0100 0734 LITTER REMOVAL - TRACT (9) AC 172.000 86.000 12.120 1,042.32 0105 0734 LITTER REMOVAL - TRACT (10) AC 132.000 66.000 7.680 506.88 0110 0734 LITTER REMOVAL - TRACT (11) AC 468.000 186.000 8.500 1,581.00 0115 0734 LITTER REMOVAL - TRACT (12) AC 356.000 105.000 6.420 674.10 0120 0734 LITTER REMOVAL - TRACT (13) AC 236.000 90.000 8.620 775.80 0125 0734 LITTER REMOVAL - TRACT (15) AC 376.000 188.000 20.700 3,891.60 0130 0734 LITTER REMOVAL - TRACT (16) AC 1,032.000 516.000 11.520 5,944.32 0135 0734 LITTER REMOVAL - TRACT (17) AC 504.000 171.000 29.780 5,092.38 0140 0734 LITTER REMOVAL - TRACT (18) AC 2,544.000 1,144.000 9.780 11,188.32 0145 0734 LITTER REMOVAL - TRACT (19) AC 1,920.000 960.000 10.210 9,801.60 0150 0734 LITTER REMOVAL - TRACT (20) AC 144.000 72.000 12.090 870.48 0155 0734 LITTER REMOVAL - TRACT (21) AC 660.000 330.000 12.750 4,207.50 0160 0734 LITTER REMOVAL - TRACT (22) AC 72.000 36.000 12.400 446.40 0165 0734 LITTER REMOVAL - TRACT (23) AC 64.000 32.000 11.050 353.60 0170 0734*LITTER REMOVAL - TRACT (14) AC 120.000 48.000 11.370 545.76 0 SUBTOTAL BID ITEMS $ 55,347.88 0 TOTAL AMOUNT WORK DONE LITTER PICK UP AND DISPOSAL $ 55,347.88 0 TOTAL AMOUNT WORK DONE CONTROL 6243-18-001 $ 55,347.88 1 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4121431 MGR.NO. 055 PAGE 001 CONT 6243 SEC 18 JOB 001 RES ENGR WAGNER,JOHN PROJ SUP - 624318001 HWY FM0487 2727 S AUSTIN AVE GEORGET CNTY WILLIAMSON DIST 14 CONTRACT PRICE $ 123,732.04 REPORT DATE 05/01/2013 08.48.05 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 012 EASTER-SEALS CENTRAL TEXAS, INC. 10984 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS 0 IN WILLIAMSON COUNTY DATE WORK BEGAN MAY 22, 2012 WORKING DAYS USED 345 PERCENT COMPLETE 44.73 PERCENT TIME USED 47.10 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6243-18-001 SUP - 624318001 14 FM0487 WILLIAMSON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL - TRACT (1) AC 798.000 363.000 8.960 3,252.48 0734 LITTER REMOVAL - TRACT (3) AC 72.000 36.000 26.240 944.64 0734 LITTER REMOVAL - TRACT (4) AC 192.000 63.000 15.600 982.80 0734 LITTER REMOVAL - TRACT (5) AC 116.000 58.000 7.110 412.38 0734 LITTER REMOVAL - TRACT (6) AC 420.000 104.000 9.250 962.00 0734 LITTER REMOVAL - TRACT (7) AC 192.000 96.000 13.290 1,275.84 0734 LITTER REMOVAL - TRACT (8) AC 136.000 68.000 8.760 595.68 0734 LITTER REMOVAL - TRACT (9) AC 172.000 86.000 12.120 1,042.32 0734 LITTER REMOVAL - TRACT (10) AC 132.000 66.000 7.680 506.88 0734 LITTER REMOVAL - TRACT (11) AC 468.000 186.000 8.500 1,581.00 0734 LITTER REMOVAL - TRACT (12) AC 356.000 105.000 6.420 674.10 0734 LITTER REMOVAL - TRACT (13) AC 236.000 90.000 8.620 775.80 0734 LITTER REMOVAL - TRACT (15) AC 376.000 188.000 20.700 3,891.60 0734 LITTER REMOVAL - TRACT (16) AC 1,032.000 516.000 11.520 5,944.32 0734 LITTER REMOVAL - TRACT (17) AC 504.000 171.000 29.780 5,092.38 0734 LITTER REMOVAL - TRACT (18) AC 2,544.000 1,144.000 9.780 11,188.32 0734 LITTER REMOVAL - TRACT (19) AC 1,920.000 960.000 10.210 9,801.60 0734 LITTER REMOVAL - TRACT (20) AC 144.000 72.000 12.090 870.48 0734 LITTER REMOVAL - TRACT (21) AC 660.000 330.000 12.750 4,207.50 0734 LITTER REMOVAL - TRACT (22) AC 72.000 36.000 12.400 446.40 0734 LITTER REMOVAL - TRACT (23) AC 64.000 32.000 11.050 353.60 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00734* LITTER REMOVAL - TRACT (14) AC 120.000 48.000 11.370 545.76 1 SUBTOTAL BID ITEMS $ 55,347.88 0 CONTRACT TOTAL ALL ITEMS $ 55,347.88 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4121431 MGR.NO. 055 PAGE 001 CONT 6243 SEC 18 JOB 001 RES ENGR WAGNER,JOHN PROJ SUP - 624318001 HWY FM0487 2727 S AUSTIN AVE GEORGET CNTY WILLIAMSON DIST 14 CONTRACT PRICE $ 123,732.04 REPORT DATE 05/01/2013 08.48.05 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 012 EASTER-SEALS CENTRAL TEXAS, INC. 10984 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 246 SUP - 624318001 6243-18-001 55,347.88 .00 55,347.88 .00 .00 55,347.88 52,530.14 2,817.74 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 55,347.88 .00 55,347.88 .00 .00 55,347.88 52,530.14 2,817.74 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4121431 MGR.NO. 055 PAGE 001 CONT 6243 SEC 18 JOB 001 RES ENGR WAGNER,JOHN PROJ SUP - 624318001 HWY FM0487 2727 S AUSTIN AVE GEORGET CNTY WILLIAMSON DIST 14 CONTRACT PRICE $ 123,732.04 REPORT DATE 05/01/2013 08.48.06 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 012 EASTER-SEALS CENTRAL TEXAS, INC. 10984 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6243-18-001 SUP - 624318001 14 FM0487 WILLIAMSON -LIMITS - VARIOUS LOCATIONS IN WILLIAMSON COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 130 0734 LITTER REMOVAL - TRACT (16) AC 1,032.000 43.000 11.520 495.36 135 0734 LITTER REMOVAL - TRACT (17) AC 504.000 21.000 29.780 625.38 140 0734 LITTER REMOVAL - TRACT (18) AC 2,544.000 90.000 9.780 880.20 145 0734 LITTER REMOVAL - TRACT (19) AC 1,920.000 80.000 10.210 816.80 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 2,817.74 0 TOTAL AMOUNT WORK DONE TO DATE - $ 55,347.88