1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6121405 MGR.NO. 051 PAGE 001 CONT 6242 SEC 66 JOB 001 RES ENGR LYONS, HOWARD PROJ RMC - 624266001 HWY US0087 3029 E SH 29 BURNET CNTY MASON DIST 14 CONTRACT PRICE $ 69,870.00 REPORT DATE 02/06/2013 14.54.43 CONTRACTOR H.T.S. CONSTRUCTION EST PERIOD JAN 01,2013 TO JAN 31,2013 EST NO 002 ENTERPRISES, INC. 12607 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN DEC 17, 2012 TIME COMPUTED FROM DEC 17, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 76 15 8 7 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JAN 13 1 1 HOLIDAY TOTAL DAYS ALLOWED = 76 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 14 4 1 RAIN ASSESSED LIQ DAMAGES = 0 5 1 SATURDAY LIQ DAMAGE RATE $ 570 6 1 SUNDAY 7 1 LIQUIDATED DAMAGES 8 1 RAIN 0 DAYS AT $ 570 PER DAY 9 1 RAIN TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 SUNDAY TO THE CONTRACTOR 14 1 WORK COMPLETED 15 1 WORK COMPLETED 16 1 WORK COMPLETED ---------------------------- 17 1 WORK COMPLETED AREA/PROJECT ENGINEER 18 1 WORK COMPLETED 19 1 WORK COMPLETED 20 1 WORK COMPLETED 21 1 WORK COMPLETED 22 1 WORK COMPLETED 23 1 WORK COMPLETED 24 1 WORK COMPLETED 25 1 WORK COMPLETED 26 1 WORK COMPLETED 27 1 WORK COMPLETED 28 1 WORK COMPLETED 29 1 WORK COMPLETED 30 1 WORK COMPLETED 31 1 WORK COMPLETED ----- ----- ----- 46 14 32 1 SATURDAY 2 SUNDAY 1 HOLIDAY 3 RAIN 18 WORK COMPLETED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6121405 MGR.NO. 051 PAGE 001 CONT 6242 SEC 66 JOB 001 RES ENGR LYONS, HOWARD PROJ RMC - 624266001 HWY US0087 3029 E SH 29 BURNET CNTY MASON DIST 14 CONTRACT PRICE $ 69,870.00 REPORT DATE 02/06/2013 14.54.44 CONTRACTOR H.T.S. CONSTRUCTION EST PERIOD JAN 01,2013 TO JAN 31,2013 EST NO 002 ENTERPRISES, INC. 12607 DIST. 14 COUNTY MASON CONTROL 6242-66-001 PROJECT RMC - 624266001 HIGHWAY US0087 0LIMITS- VARIOUS LOCATIONS IN MASON COUNTY . 0TYPE OF WORK- LITTER REMOVAL 0 0005 PREPARED BY BURNET AO 4-5-2012 0 0055 LITTER SEGMENT NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL AC 8,220.000 1,826.000 8.500 15,521.00 0 SUBTOTAL BID ITEMS $ 15,521.00 0 TOTAL AMOUNT WORK DONE LITTER SEGMENT $ 15,521.00 0 TOTAL AMOUNT WORK DONE CONTROL 6242-66-001 $ 15,521.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6121405 MGR.NO. 051 PAGE 001 CONT 6242 SEC 66 JOB 001 RES ENGR LYONS, HOWARD PROJ RMC - 624266001 HWY US0087 3029 E SH 29 BURNET CNTY MASON DIST 14 CONTRACT PRICE $ 69,870.00 REPORT DATE 02/06/2013 14.54.44 CONTRACTOR H.T.S. CONSTRUCTION EST PERIOD JAN 01,2013 TO JAN 31,2013 EST NO 002 ENTERPRISES, INC. 12607 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN MASON COUNTY 0 . DATE WORK BEGAN DEC 17, 2012 WORKING DAYS USED 14 PERCENT COMPLETE 22.21 PERCENT TIME USED 18.40 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6242-66-001 RMC - 624266001 14 US0087 MASON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL AC 8,220.000 1,826.000 8.500 15,521.00 0 SUBTOTAL BID ITEMS $ 15,521.00 0 CONTRACT TOTAL ALL ITEMS $ 15,521.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6121405 MGR.NO. 051 PAGE 001 CONT 6242 SEC 66 JOB 001 RES ENGR LYONS, HOWARD PROJ RMC - 624266001 HWY US0087 3029 E SH 29 BURNET CNTY MASON DIST 14 CONTRACT PRICE $ 69,870.00 REPORT DATE 02/06/2013 14.54.44 CONTRACTOR H.T.S. CONSTRUCTION EST PERIOD JAN 01,2013 TO JAN 31,2013 EST NO 002 ENTERPRISES, INC. 12607 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 157 RMC - 624266001 6242-66-001 15,521.00 .00 15,521.00 .00 .00 15,521.00 4,488.00 11,033.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 15,521.00 .00 15,521.00 .00 .00 15,521.00 4,488.00 11,033.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6121405 MGR.NO. 051 PAGE 001 CONT 6242 SEC 66 JOB 001 RES ENGR LYONS, HOWARD PROJ RMC - 624266001 HWY US0087 3029 E SH 29 BURNET CNTY MASON DIST 14 CONTRACT PRICE $ 69,870.00 REPORT DATE 02/06/2013 14.54.45 CONTRACTOR H.T.S. CONSTRUCTION EST PERIOD JAN 01,2013 TO JAN 31,2013 EST NO 002 ENTERPRISES, INC. 12607 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6242-66-001 RMC - 624266001 14 US0087 MASON -LIMITS - VARIOUS LOCATIONS IN MASON COUNTY . LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0734 LITTER REMOVAL AC 8,220.000 1,298.000 8.500 11,033.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 11,033.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 15,521.00