1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2111406 MGR.NO. 051 PAGE 001 CONT 6213 SEC 22 JOB 001 RES ENGR LYONS, HOWARD PROJ RMC - 621322001 HWY SH0071 3029 E HWY 29 BURNET CNTY LLANO DIST 14 CONTRACT PRICE $ 174,216.00 REPORT DATE 03/01/2013 07.13.35 CONTRACTOR AUSTIN ENGINEERING CO., INC. 166 EST PERIOD MAY 19,2011 TO FEB 28,2013 EST NO 020 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 19, 2011 TIME COMPUTED FROM MAY 19, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 76 532 58 474 BROUGHT FORWARD ADDL DAYS GRANTED = 0 FEB 13 1 1 CYCLE COMPLETE TOTAL DAYS ALLOWED = 76 2 1 CYCLE COMPLETE DATE WORK COMPLETED 3 1 CYCLE COMPLETE DAYS CHARGED TO DATE = 64 4 1 CYCLE COMPLETE ASSESSED LIQ DAMAGES = 0 5 1 CYCLE COMPLETE LIQ DAMAGE RATE $ 500 6 1 CYCLE COMPLETE 7 1 CYCLE COMPLETE LIQUIDATED DAMAGES 8 1 CYCLE COMPLETE 0 DAYS AT $ 500 PER DAY 9 1 CYCLE COMPLETE TOTAL = $ .00 10 1 CYCLE COMPLETE 11 1 CYCLE COMPLETE CERTIFIED AS CORRECT AND 12 1 CYCLE COMPLETE ONE COPY HAS BEEN GIVEN 13 1 CYCLE COMPLETE TO THE CONTRACTOR 14 1 CYCLE COMPLETE 15 1 CYCLE COMPLETE 16 1 CYCLE COMPLETE ---------------------------- 17 1 TIME NOT STARTED AREA/PROJECT ENGINEER 18 1 SUNDAY 19 1 20 1 21 1 HEAVY TRAFFIC 22 1 HOLIDAY 23 1 HEAVY TRAFFIC 24 1 SATURDAY 25 1 SUNDAY 26 1 27 1 28 1 29 1 30 1 CYCLE COMPLETE 0 ----- ----- ----- 562 64 498 1 SATURDAY 2 SUNDAY 1 HOLIDAY 17 CYCLE COMPLETE 1 TIME NOT STARTED 2 HEAVY TRAFFIC 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2111406 MGR.NO. 051 PAGE 001 CONT 6213 SEC 22 JOB 001 RES ENGR LYONS, HOWARD PROJ RMC - 621322001 HWY SH0071 3029 E HWY 29 BURNET CNTY LLANO DIST 14 CONTRACT PRICE $ 174,216.00 REPORT DATE 03/01/2013 07.13.36 CONTRACTOR AUSTIN ENGINEERING CO., INC. 166 EST PERIOD MAY 19,2011 TO FEB 28,2013 EST NO 020 & FINAL DIST. 14 COUNTY LLANO CONTROL 6213-22-001 PROJECT RMC - 621322001 HIGHWAY SH0071 0LIMITS- VARIOUS LOCATIONS IN LLANO AND BURNET COUNTIES 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 PREPARED BY BURNET AREA OFFICE 0 0055 MOWNG SEGEMENT NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 8,296.000 8,296.000 21.000 174,216.00 0 SUBTOTAL BID ITEMS $ 174,216.00 0 SPECIAL DEDUCTIONS - 0 LINE MATRL. NO MATERIAL DESCRIPTION UNIT QUANTITY UNIT AMOUNT NO. PRICE($) ($) - 0075 00000000775 7 DAYS LIQ. DAMAGES EA 7.000 500.000 -3,500.00 0 0080 00000000775 7 DAYS LIQ. DAMAGES EA 1.000 500.000 -500.00 0 0085 00000000776 STAT OF REPAIR SIGNS & DEL LS 1.000 3,613.320 -3,613.32 0 TOTAL SPECIAL DEDUCTIONS - $ -7,613.32 0 TOTAL AMOUNT WORK DONE MOWNG SEGEMENT $ 174,216.00 TOTAL SPECIAL DEDUCTIONS MOWNG SEGEMENT $ -7,613.32 0 TOTAL AMOUNT WORK DONE CONTROL 6213-22-001 $ 174,216.00 0 TOTAL SPECIAL DEDUCTIONS CONTROL 6213-22-001 $ -7,613.32 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2111406 MGR.NO. 051 PAGE 001 CONT 6213 SEC 22 JOB 001 RES ENGR LYONS, HOWARD PROJ RMC - 621322001 HWY SH0071 3029 E HWY 29 BURNET CNTY LLANO DIST 14 CONTRACT PRICE $ 174,216.00 REPORT DATE 03/01/2013 07.13.36 CONTRACTOR AUSTIN ENGINEERING CO., INC. 166 EST PERIOD MAY 19,2011 TO FEB 28,2013 EST NO 020 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN LLANO AND BURNET 0 COUNTIES DATE WORK BEGAN MAY 19, 2011 WORKING DAYS USED 64 PERCENT COMPLETE 99.99 PERCENT TIME USED 84.20 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6213-22-001 RMC - 621322001 14 SH0071 LLANO - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 8,296.000 8,296.000 21.000 174,216.00 0 SUBTOTAL BID ITEMS $ 174,216.00 0 CONTRACT TOTAL ALL ITEMS $ 174,216.00 SPECIAL DEDUCTIONS 0 UNIT AMOUNT MATRL. NO. MATERIAL DESCRIPTION UNIT QUANTITY PRICE ($) ($) 0 00000000775 7 DAYS LIQ. DAMAGES EA 7.000 500.000 -3,500.00 0 00000000776 STAT OF REPAIR SIGNS & DEL LS 1.000 3,613.320 -3,613.32 0 00000000775 7 DAYS LIQ. DAMAGES EA 1.000 500.000 -500.00 0 TOTAL SPECIAL DEDUCTIONS $ -7,613.32 0 CONTRACT TOTAL SPECIAL DEDUCTIONS $ -7,613.32 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2111406 MGR.NO. 051 PAGE 001 CONT 6213 SEC 22 JOB 001 RES ENGR LYONS, HOWARD PROJ RMC - 621322001 HWY SH0071 3029 E HWY 29 BURNET CNTY LLANO DIST 14 CONTRACT PRICE $ 174,216.00 REPORT DATE 03/01/2013 07.13.36 CONTRACTOR AUSTIN ENGINEERING CO., INC. 166 EST PERIOD MAY 19,2011 TO FEB 28,2013 EST NO 020 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 150 RMC - 621322001 6213-22-001 174,216.00 .00 174,216.00 7,613.32 .00 166,602.68 166,602.68 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 174,216.00 .00 174,216.00 7,613.32 .00 166,602.68 166,602.68 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2111406 MGR.NO. 051 PAGE 001 CONT 6213 SEC 22 JOB 001 RES ENGR LYONS, HOWARD PROJ RMC - 621322001 HWY SH0071 3029 E HWY 29 BURNET CNTY LLANO DIST 14 CONTRACT PRICE $ 174,216.00 REPORT DATE 03/01/2013 07.13.36 CONTRACTOR AUSTIN ENGINEERING CO., INC. 166 EST PERIOD MAY 19,2011 TO FEB 28,2013 EST NO 020 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6213-22-001 RMC - 621322001 14 SH0071 LLANO -LIMITS - VARIOUS LOCATIONS IN LLANO AND BURNET COUNTIES - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 174,216.00