1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5094006 MGR.NO. 585 PAGE 001 CONT 6191 SEC 05 JOB 001 RES ENGR SMITH, BECKY PROJ RMC - 619105001 HWY FM0812 7901 N IH 35 AUSTIN CNTY BASTROP DIST 14 CONTRACT PRICE $ 309,099.71 REPORT DATE 11/18/2009 08.53.47 CONTRACTOR ASPHALT PAVING COMPANY OF EST PERIOD AUG 07,2009 TO AUG 31,2009 EST NO 003 & FINAL AUSTIN, INC. 03151 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 10, 2009 TIME COMPUTED FROM AUG 07, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 16 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 3 AUG 09 TOTAL DAYS ALLOWED = 19 DATE WORK COMPLETED 08/31/09 DAYS CHARGED TO DATE = 11 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 500 0 7 1 LIQUIDATED DAMAGES 8 1 SATURDAY 0 DAYS AT $ 500 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 SATURDAY 16 1 SUNDAY ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 WORK SUSPENDED 21 1 WORK SUSPENDED 22 1 SATURDAY 23 1 SUNDAY 24 1 25 1 26 1 WORK COMPLETED 27 1 WORK COMPLETED 28 1 WORK COMPLETED 29 1 WORK COMPLETED 30 1 WORK COMPLETED 31 1 WORK COMPLETED ----- ----- ----- 25 11 14 3 SATURDAY 3 SUNDAY 0 HOLIDAY 2 WORK SUSPENDED 6 WORK COMPLETED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5094006 MGR.NO. 585 PAGE 001 CONT 6191 SEC 05 JOB 001 RES ENGR SMITH, BECKY PROJ RMC - 619105001 HWY FM0812 7901 N IH 35 AUSTIN CNTY BASTROP DIST 14 CONTRACT PRICE $ 309,099.71 REPORT DATE 11/18/2009 08.53.47 CONTRACTOR ASPHALT PAVING COMPANY OF EST PERIOD AUG 07,2009 TO AUG 31,2009 EST NO 003 & FINAL AUSTIN, INC. 03151 DIST. 14 COUNTY BASTROP CONTROL 6191-05-001 PROJECT RMC - 619105001 HIGHWAY FM0812 0LIMITS- 0.577 MILES SOUTHEAST OF SH 21 FM 672 0TYPE OF WORK- FULL DEPTH PAVEMENT REPAIRS 0 0005 BASE REMOVAL/REPLACEMENT 0 0055 FULL DEPTH PAVEMENT REPAIRS NET LENGTH 0.716 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") SY 9,101.000 11,815.500 33.100 391,093.05 0060 0351 ADJ EST QUANTITY TO DATE 11,830.000 0065 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 374.000 440.000 .750 330.00 0065 0662 ADJ EST QUANTITY TO DATE 486.000 0070 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 7,515.000 9,540.000 .530 5,056.20 0070 0666 ADJ EST QUANTITY TO DATE 9,770.000 0075 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 300.000 560.000 .510 285.60 0075 0666 ADJ EST QUANTITY TO DATE 390.000 0080 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 6,328.000 7,650.000 .420 3,213.00 0080 0666 ADJ EST QUANTITY TO DATE 8,226.000 0085 0672 REFL PAV MRKR TY I-C EA 96.000 0.000 8.150 .00 0085 0672 ADJ EST QUANTITY TO DATE 0.000 0100 0672*REFL PAV MRKR TY II-A-A EA 126.000 123.000 8.150 1,002.45 0110 9000*SMALL QUANTITY PAVEMENT REPAIR(INVOICE) SY 316.000 316.000 64.130 20,265.08 0 SUBTOTAL BID ITEMS $ 421,245.38 0 TOTAL AMOUNT WORK DONE FULL DEPTH PAVEMENT REPAIRS $ 421,245.38 0 TOTAL AMOUNT WORK DONE CONTROL 6191-05-001 $ 421,245.38 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5094006 MGR.NO. 585 PAGE 001 CONT 6191 SEC 05 JOB 001 RES ENGR SMITH, BECKY PROJ RMC - 619105001 HWY FM0812 7901 N IH 35 AUSTIN CNTY BASTROP DIST 14 CONTRACT PRICE $ 309,099.71 REPORT DATE 11/18/2009 08.53.47 CONTRACTOR ASPHALT PAVING COMPANY OF EST PERIOD AUG 07,2009 TO AUG 31,2009 EST NO 003 & FINAL AUSTIN, INC. 03151 0*********************************************************************************************************************************** -LIMITS - 0.577 MILES SOUTHEAST OF SH 21 0 FM 672 DATE WORK BEGAN AUG 10, 2009 WORKING DAYS USED 11 PERCENT COMPLETE 100.00 PERCENT TIME USED 57.80 DATE COMPLETED AUG 31 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6191-05-001 RMC - 619105001 14 FM0812 BASTROP - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") SY 9,101.000 11,815.500 33.100 391,093.05 0351 ADJ EST QUANTITY TO DATE 11,830.000 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 374.000 440.000 .750 330.00 0662 ADJ EST QUANTITY TO DATE 486.000 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 7,515.000 9,540.000 .530 5,056.20 0666 ADJ EST QUANTITY TO DATE 9,770.000 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 300.000 560.000 .510 285.60 0666 ADJ EST QUANTITY TO DATE 390.000 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 6,328.000 7,650.000 .420 3,213.00 0666* ADJ EST QUANTITY TO DATE 8,226.000 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00672* REFL PAV MRKR TY II-A-A EA 126.000 123.000 8.150 1,002.45 9000* SMALL QUANTITY PAVEMENT REPAIR(INVOICE) SY 316.000 316.000 64.130 20,265.08 0 SUBTOTAL BID ITEMS $ 421,245.38 0 CONTRACT TOTAL ALL ITEMS $ 421,245.38 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5094006 MGR.NO. 585 PAGE 001 CONT 6191 SEC 05 JOB 001 RES ENGR SMITH, BECKY PROJ RMC - 619105001 HWY FM0812 7901 N IH 35 AUSTIN CNTY BASTROP DIST 14 CONTRACT PRICE $ 309,099.71 REPORT DATE 11/18/2009 08.53.47 CONTRACTOR ASPHALT PAVING COMPANY OF EST PERIOD AUG 07,2009 TO AUG 31,2009 EST NO 003 & FINAL AUSTIN, INC. 03151 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 11 RMC - 619105001 6191-05-001 421,245.38 .00 421,245.38 .00 .00 421,245.38 421,245.38 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 421,245.38 .00 421,245.38 .00 .00 421,245.38 421,245.38 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5094006 MGR.NO. 585 PAGE 001 CONT 6191 SEC 05 JOB 001 RES ENGR SMITH, BECKY PROJ RMC - 619105001 HWY FM0812 7901 N IH 35 AUSTIN CNTY BASTROP DIST 14 CONTRACT PRICE $ 309,099.71 REPORT DATE 11/18/2009 08.53.47 CONTRACTOR ASPHALT PAVING COMPANY OF EST PERIOD AUG 07,2009 TO AUG 31,2009 EST NO 003 & FINAL AUSTIN, INC. 03151 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6191-05-001 RMC - 619105001 14 FM0812 BASTROP -LIMITS - 0.577 MILES SOUTHEAST OF SH 21 FM 672 - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 421,245.38