1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8081440 MGR.NO. 585 PAGE 001 CONT 6183 SEC 62 JOB 001 RES ENGR SMITH, BECKY PROJ EMC - 618362001 HWY US0290 7901 N. IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 204,893.50 REPORT DATE 09/04/2008 11.29.59 CONTRACTOR AARON CONCRETE CONTRACTORS, EST PERIOD AUG 07,2008 TO AUG 13,2008 EST NO 002 & FINAL L.P. 11123 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 07, 2008 TIME COMPUTED FROM AUG 08, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 5 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 08 TOTAL DAYS ALLOWED = 5 DATE WORK COMPLETED 08/13/08 DAYS CHARGED TO DATE = 5 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 0 0 7 1 TIME NOT STARTED LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 WORK COMPLETED TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 7 5 2 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 TIME NOT STARTED 1 WORK COMPLETED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8081440 MGR.NO. 585 PAGE 001 CONT 6183 SEC 62 JOB 001 RES ENGR SMITH, BECKY PROJ EMC - 618362001 HWY US0290 7901 N. IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 204,893.50 REPORT DATE 09/04/2008 11.30.00 CONTRACTOR AARON CONCRETE CONTRACTORS, EST PERIOD AUG 07,2008 TO AUG 13,2008 EST NO 002 & FINAL L.P. 11123 DIST. 14 COUNTY TRAVIS CONTROL 6183-62-001 PROJECT EMC - 618362001 HIGHWAY US0290 0LIMITS- S. BOUND US 290 LAMAR ENTRANCE RAMP GOR 700' WEST OF LAMAR RAMP GORE 0TYPE OF WORK- REMOVE CONC PAV,REPAIR RCP,REPLACE PAV 0 0050 EMERGENCY CONTRACT_BY RICK HARRIS NET LENGTH 0.151 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 DATE: JULY 22,2008 0 0075 0104 REMOVING CONC (PAV) SY 854.000 888.000 75.000 66,600.00 0075 0104 ADJ EST QUANTITY TO DATE 888.000 0080 0340 D-GR HMA(METH) TY-C SAC-B PG64-22 TON 3.000 0.000 800.000 .00 0080 0340 ADJ EST QUANTITY TO DATE 0.000 0085 0360 CONC PVMT (CONT REINF-CRCP)(11") SY 854.000 888.000 80.000 71,040.00 0085 0360 ADJ EST QUANTITY TO DATE 888.000 0105 0401 FLOWABLE BACKFILL CY 55.000 40.000 140.000 5,600.00 0110 0438 CLEAN AND SEAL JOINTS LF 320.000 333.000 17.000 5,661.00 0115 0472 REMOV & RE-LAY PIPE (24 IN) LF 8.000 8.000 500.000 4,000.00 0120 0500 MOBILIZATION LS 1.000 1.000 15,000.000 15,000.00 0125 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 9,000.000 9,000.00 0130 0512 PORT CTB (DES SOURCE)(SAFETY SH)(TY 2) LF 630.000 720.000 14.000 10,080.00 0130 0512 ADJ EST QUANTITY TO DATE 720.000 0135 0512 PORT CTB (STKPL)(SAFETY SH)(TY 2) LF 630.000 720.000 14.000 10,080.00 0135 0512 ADJ EST QUANTITY TO DATE 720.000 0140 0662 WK ZN PAV MRK REMOV (W) 4" (BRK) LF 350.000 350.000 1.750 612.50 0145 0662 WK ZN PAV MRK REMOV (Y) 4" (SLD) LF 1,400.000 1,400.000 1.750 2,450.00 0150 0666 REFL PAV MRK TY I (W) 4" (BRK)(090MIL) LF 180.000 530.000 2.750 1,457.50 0155 0666 REFL PAV MRK TY I (W) 4" (SLD)(090MIL) LF 360.000 360.000 2.750 990.00 1 0160 0666 REF PAV MRK TY II (W) 4" (BRK) LF 180.000 180.000 .550 99.00 0165 0666 REF PAV MRK TY II (W) 4" (SLD) LF 360.000 360.000 .550 198.00 0170 0672 REFL PAV MRKR TY II-C-R EA 34.000 34.000 11.000 374.00 0175 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 1,750.000 1,750.000 3.500 6,125.00 0180 0105*REMOVING STAB BASE AND ASPH PAV (2"-6") SY 858.000 858.000 10.000 8,580.00 0185 0340*D-GR HMA(METH) TY-B PG64-22 TON 277.750 277.750 112.500 31,246.88 0 SUBTOTAL BID ITEMS $ 249,193.88 0 TOTAL AMOUNT WORK DONE EMERGENCY CONTRACT_BY RICK HARRIS $ 249,193.88 0 TOTAL AMOUNT WORK DONE CONTROL 6183-62-001 $ 249,193.88 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8081440 MGR.NO. 585 PAGE 001 CONT 6183 SEC 62 JOB 001 RES ENGR SMITH, BECKY PROJ EMC - 618362001 HWY US0290 7901 N. IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 204,893.50 REPORT DATE 09/04/2008 11.30.00 CONTRACTOR AARON CONCRETE CONTRACTORS, EST PERIOD AUG 07,2008 TO AUG 13,2008 EST NO 002 & FINAL L.P. 11123 0*********************************************************************************************************************************** -LIMITS - S. BOUND US 290 LAMAR ENTRANCE RAMP GOR 0 700' WEST OF LAMAR RAMP GORE DATE WORK BEGAN AUG 7 , 2008 WORKING DAYS USED 5 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED AUG 13 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6183-62-001 EMC - 618362001 14 US0290 TRAVIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0104 REMOVING CONC (PAV) SY 854.000 888.000 75.000 66,600.00 0104 ADJ EST QUANTITY TO DATE 888.000 0360 CONC PVMT (CONT REINF-CRCP)(11") SY 854.000 888.000 80.000 71,040.00 0360 ADJ EST QUANTITY TO DATE 888.000 0401 FLOWABLE BACKFILL CY 55.000 40.000 140.000 5,600.00 0438 CLEAN AND SEAL JOINTS LF 320.000 333.000 17.000 5,661.00 0472 REMOV & RE-LAY PIPE (24 IN) LF 8.000 8.000 500.000 4,000.00 0500 MOBILIZATION LS 1.000 1.000 15,000.000 15,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 9,000.000 9,000.00 0512 PORT CTB (DES SOURCE)(SAFETY SH)(TY 2) LF 630.000 720.000 14.000 10,080.00 0512 ADJ EST QUANTITY TO DATE 720.000 0512 PORT CTB (STKPL)(SAFETY SH)(TY 2) LF 630.000 720.000 14.000 10,080.00 0512 ADJ EST QUANTITY TO DATE 720.000 0662 WK ZN PAV MRK REMOV (W) 4" (BRK) LF 350.000 350.000 1.750 612.50 0662 WK ZN PAV MRK REMOV (Y) 4" (SLD) LF 1,400.000 1,400.000 1.750 2,450.00 0666 REFL PAV MRK TY I (W) 4" (BRK)(090MIL) LF 180.000 530.000 2.750 1,457.50 0666 REFL PAV MRK TY I (W) 4" (SLD)(090MIL) LF 360.000 360.000 2.750 990.00 10666 REF PAV MRK TY II (W) 4" (BRK) LF 180.000 180.000 .550 99.00 0666 REF PAV MRK TY II (W) 4" (SLD) LF 360.000 360.000 .550 198.00 0672 REFL PAV MRKR TY II-C-R EA 34.000 34.000 11.000 374.00 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 1,750.000 1,750.000 3.500 6,125.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00105* REMOVING STAB BASE AND ASPH PAV (2"-6") SY 858.000 858.000 10.000 8,580.00 0340* D-GR HMA(METH) TY-B PG64-22 TON 277.750 277.750 112.500 31,246.88 0 SUBTOTAL BID ITEMS $ 249,193.88 0 CONTRACT TOTAL ALL ITEMS $ 249,193.88 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8081440 MGR.NO. 585 PAGE 001 CONT 6183 SEC 62 JOB 001 RES ENGR SMITH, BECKY PROJ EMC - 618362001 HWY US0290 7901 N. IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 204,893.50 REPORT DATE 09/04/2008 11.30.00 CONTRACTOR AARON CONCRETE CONTRACTORS, EST PERIOD AUG 07,2008 TO AUG 13,2008 EST NO 002 & FINAL L.P. 11123 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 227 EMC - 618362001 6183-62-001 249,193.88 .00 249,193.88 .00 .00 249,193.88 249,193.88 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 249,193.88 .00 249,193.88 .00 .00 249,193.88 249,193.88 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8081440 MGR.NO. 585 PAGE 001 CONT 6183 SEC 62 JOB 001 RES ENGR SMITH, BECKY PROJ EMC - 618362001 HWY US0290 7901 N. IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 204,893.50 REPORT DATE 09/04/2008 11.30.01 CONTRACTOR AARON CONCRETE CONTRACTORS, EST PERIOD AUG 07,2008 TO AUG 13,2008 EST NO 002 & FINAL L.P. 11123 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6183-62-001 EMC - 618362001 14 US0290 TRAVIS -LIMITS - S. BOUND US 290 LAMAR ENTRANCE RAMP GOR 700' WEST OF LAMAR RAMP GORE - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 249,193.88