1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5081432 MGR.NO. 585 PAGE 001 CONT 6180 SEC 18 JOB 001 RES ENGR SMITH, BECKY PROJ SUP - 618018001 HWY US0183 7901 N. IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 3,960.00 REPORT DATE 12/11/2008 09.28.07 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 006 GOODWILL INDUSTRIES OF CENTRAL TEXAS 13330 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 01, 2008 TIME COMPUTED FROM JUN 01, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 153 153 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 08 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 183 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 183 183 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5081432 MGR.NO. 585 PAGE 001 CONT 6180 SEC 18 JOB 001 RES ENGR SMITH, BECKY PROJ SUP - 618018001 HWY US0183 7901 N. IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 3,960.00 REPORT DATE 12/11/2008 09.28.07 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 006 GOODWILL INDUSTRIES OF CENTRAL TEXAS 13330 DIST. 14 COUNTY TRAVIS CONTROL 6180-18-001 PROJECT SUP - 618018001 HIGHWAY US0183 0LIMITS- TRAVIS EAST MAINTENANCE OFFICE . 0TYPE OF WORK- JANITORIAL MAINTENANCE 0 0005 PREPARED BY ROSIE BECK 0 0055 JANITORIAL SEGMENT NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 7013 JANITORIAL MAINTENANCE MO 12.000 6.000 330.000 1,980.00 0 SUBTOTAL BID ITEMS $ 1,980.00 0 TOTAL AMOUNT WORK DONE JANITORIAL SEGMENT $ 1,980.00 0 TOTAL AMOUNT WORK DONE CONTROL 6180-18-001 $ 1,980.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5081432 MGR.NO. 585 PAGE 001 CONT 6180 SEC 18 JOB 001 RES ENGR SMITH, BECKY PROJ SUP - 618018001 HWY US0183 7901 N. IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 3,960.00 REPORT DATE 12/11/2008 09.28.07 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 006 GOODWILL INDUSTRIES OF CENTRAL TEXAS 13330 0*********************************************************************************************************************************** -LIMITS - TRAVIS EAST MAINTENANCE OFFICE 0 . DATE WORK BEGAN JUN 1 , 2008 WORKING DAYS USED 183 PERCENT COMPLETE 50.00 PERCENT TIME USED 50.10 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6180-18-001 SUP - 618018001 14 US0183 TRAVIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -7013 JANITORIAL MAINTENANCE MO 12.000 6.000 330.000 1,980.00 0 SUBTOTAL BID ITEMS $ 1,980.00 0 CONTRACT TOTAL ALL ITEMS $ 1,980.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5081432 MGR.NO. 585 PAGE 001 CONT 6180 SEC 18 JOB 001 RES ENGR SMITH, BECKY PROJ SUP - 618018001 HWY US0183 7901 N. IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 3,960.00 REPORT DATE 12/11/2008 09.28.07 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 006 GOODWILL INDUSTRIES OF CENTRAL TEXAS 13330 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 227 SUP - 618018001 6180-18-001 1,980.00 .00 1,980.00 .00 .00 1,980.00 1,650.00 330.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 1,980.00 .00 1,980.00 .00 .00 1,980.00 1,650.00 330.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5081432 MGR.NO. 585 PAGE 001 CONT 6180 SEC 18 JOB 001 RES ENGR SMITH, BECKY PROJ SUP - 618018001 HWY US0183 7901 N. IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 3,960.00 REPORT DATE 12/11/2008 09.28.07 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 006 GOODWILL INDUSTRIES OF CENTRAL TEXAS 13330 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6180-18-001 SUP - 618018001 14 US0183 TRAVIS -LIMITS - TRAVIS EAST MAINTENANCE OFFICE . LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 7013 JANITORIAL MAINTENANCE MO 12.000 1.000 330.000 330.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 330.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 1,980.00