1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 9071432 MGR.NO. 585 PAGE 001 CONT 6169 SEC 53 JOB 001 RES ENGR MILLER, LESLIE PROJ SUP - 616953001 HWY LP0001 7901 N. IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 430,353.04 REPORT DATE 01/07/2009 14.11.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD DEC 01,2008 TO DEC 31,2008 EST NO 014 EASTER-SEALS CENTRAL TEXAS, INC. 10984 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN DEC 19, 2007 TIME COMPUTED FROM DEC 19, 2007 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 416 348 198 150 BROUGHT FORWARD ADDL DAYS GRANTED = 0 DEC 08 1 1 TOTAL DAYS ALLOWED = 416 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 218 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 500 6 1 SATURDAY 7 1 SUNDAY LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 500 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 SATURDAY TO THE CONTRACTOR 14 1 SUNDAY 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 SATURDAY 21 1 SUNDAY 22 1 23 1 24 1 HOLIDAY 25 1 HOLIDAY 26 1 HOLIDAY 27 1 SATURDAY 28 1 SUNDAY 29 1 30 1 31 1 ----- ----- ----- 379 218 161 4 SATURDAY 4 SUNDAY 3 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 9071432 MGR.NO. 585 PAGE 001 CONT 6169 SEC 53 JOB 001 RES ENGR MILLER, LESLIE PROJ SUP - 616953001 HWY LP0001 7901 N. IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 430,353.04 REPORT DATE 01/07/2009 14.11.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD DEC 01,2008 TO DEC 31,2008 EST NO 014 EASTER-SEALS CENTRAL TEXAS, INC. 10984 DIST. 14 COUNTY TRAVIS CONTROL 6169-53-001 PROJECT SUP - 616953001 HIGHWAY LP0001 0LIMITS- LOOP 1 AND US 183 IN TRAVIS COUNTY . 0TYPE OF WORK- LITTER REMOVAL 0 0005 PREPARED BY BECKY SMITH 8-29-07 0 0055 LITTER SEGMENT NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL AC 57,304.000 28,372.000 7.510 213,073.72 0065 9001*SUPP AGREEMENT #1 MINIMUM WAGE INCREASE MO 17.000 4.000 2,138.280 8,553.12 0 SUBTOTAL BID ITEMS $ 221,626.84 0 TOTAL AMOUNT WORK DONE LITTER SEGMENT $ 221,626.84 0 TOTAL AMOUNT WORK DONE CONTROL 6169-53-001 $ 221,626.84 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 9071432 MGR.NO. 585 PAGE 001 CONT 6169 SEC 53 JOB 001 RES ENGR MILLER, LESLIE PROJ SUP - 616953001 HWY LP0001 7901 N. IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 430,353.04 REPORT DATE 01/07/2009 14.11.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD DEC 01,2008 TO DEC 31,2008 EST NO 014 EASTER-SEALS CENTRAL TEXAS, INC. 10984 0*********************************************************************************************************************************** -LIMITS - LOOP 1 AND US 183 IN TRAVIS COUNTY 0 . DATE WORK BEGAN DEC 19, 2007 WORKING DAYS USED 218 PERCENT COMPLETE 51.49 PERCENT TIME USED 52.40 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6169-53-001 SUP - 616953001 14 LP0001 TRAVIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL AC 57,304.000 28,372.000 7.510 213,073.72 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09001* SUPP AGREEMENT #1 MINIMUM WAGE INCREASE MO 17.000 4.000 2,138.280 8,553.12 0 SUBTOTAL BID ITEMS $ 221,626.84 0 CONTRACT TOTAL ALL ITEMS $ 221,626.84 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 9071432 MGR.NO. 585 PAGE 001 CONT 6169 SEC 53 JOB 001 RES ENGR MILLER, LESLIE PROJ SUP - 616953001 HWY LP0001 7901 N. IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 430,353.04 REPORT DATE 01/07/2009 14.11.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD DEC 01,2008 TO DEC 31,2008 EST NO 014 EASTER-SEALS CENTRAL TEXAS, INC. 10984 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 227 SUP - 616953001 6169-53-001 221,626.84 .00 221,626.84 .00 .00 221,626.84 205,074.80 16,552.04 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 221,626.84 .00 221,626.84 .00 .00 221,626.84 205,074.80 16,552.04 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 9071432 MGR.NO. 585 PAGE 001 CONT 6169 SEC 53 JOB 001 RES ENGR MILLER, LESLIE PROJ SUP - 616953001 HWY LP0001 7901 N. IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 430,353.04 REPORT DATE 01/07/2009 14.11.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD DEC 01,2008 TO DEC 31,2008 EST NO 014 EASTER-SEALS CENTRAL TEXAS, INC. 10984 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6169-53-001 SUP - 616953001 14 LP0001 TRAVIS -LIMITS - LOOP 1 AND US 183 IN TRAVIS COUNTY . LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0734 LITTER REMOVAL AC 57,304.000 2,204.000 7.510 16,552.04 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 16,552.04 0 TOTAL AMOUNT WORK DONE TO DATE - $ 221,626.84