1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 12074024 MGR.NO. 585 PAGE 001 CONT 6161 SEC 58 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616158001 HWY SH0071 7901 N IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 316,520.85 REPORT DATE 08/19/2008 09.33.04 CONTRACTOR CEN-TEX IRRIGATION SYSTEMS 12250 EST PERIOD JUL 01,2008 TO JUL 31,2008 EST NO 001 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 15, 2008 TIME COMPUTED FROM JUL 15, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 78 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 08 TOTAL DAYS ALLOWED = 78 DATE WORK COMPLETED DAYS CHARGED TO DATE = 12 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 500 0 LIQUIDATED DAMAGES 0 DAYS AT $ 500 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR 0 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 SATURDAY 20 1 SUNDAY 21 1 22 1 23 1 24 1 25 1 TOO WET 26 1 SATURDAY 27 1 SUNDAY 28 1 29 1 30 1 31 1 ----- ----- ----- 17 12 5 2 SATURDAY 2 SUNDAY 0 HOLIDAY 1 TOO WET 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 12074024 MGR.NO. 585 PAGE 001 CONT 6161 SEC 58 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616158001 HWY SH0071 7901 N IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 316,520.85 REPORT DATE 08/19/2008 09.33.04 CONTRACTOR CEN-TEX IRRIGATION SYSTEMS 12250 EST PERIOD JUL 01,2008 TO JUL 31,2008 EST NO 001 DIST. 14 COUNTY TRAVIS CONTROL 6161-58-001 PROJECT RMC - 616158001 HIGHWAY SH0071 0LIMITS- VARIOUS LOCATIONS IN TRAVIS AND HAYS COUNTIES 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 PREPARED BY LESLIE MILLER 09-30-2007 0 0055 MOWING SEGEMENT NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 7,865.000 702.000 39.990 28,072.98 0065 0730 SPOT MOWING AC 50.000 0.000 39.990 .00 0 SUBTOTAL BID ITEMS $ 28,072.98 0 TOTAL AMOUNT WORK DONE MOWING SEGEMENT $ 28,072.98 0 TOTAL AMOUNT WORK DONE CONTROL 6161-58-001 $ 28,072.98 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 12074024 MGR.NO. 585 PAGE 001 CONT 6161 SEC 58 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616158001 HWY SH0071 7901 N IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 316,520.85 REPORT DATE 08/19/2008 09.33.04 CONTRACTOR CEN-TEX IRRIGATION SYSTEMS 12250 EST PERIOD JUL 01,2008 TO JUL 31,2008 EST NO 001 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN TRAVIS AND 0 HAYS COUNTIES DATE WORK BEGAN JUL 15, 2008 WORKING DAYS USED 12 PERCENT COMPLETE 8.86 PERCENT TIME USED 15.30 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6161-58-001 RMC - 616158001 14 SH0071 TRAVIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 7,865.000 702.000 39.990 28,072.98 0 SUBTOTAL BID ITEMS $ 28,072.98 0 CONTRACT TOTAL ALL ITEMS $ 28,072.98 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 12074024 MGR.NO. 585 PAGE 001 CONT 6161 SEC 58 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616158001 HWY SH0071 7901 N IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 316,520.85 REPORT DATE 08/19/2008 09.33.04 CONTRACTOR CEN-TEX IRRIGATION SYSTEMS 12250 EST PERIOD JUL 01,2008 TO JUL 31,2008 EST NO 001 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 227 RMC - 616158001 6161-58-001 28,072.98 .00 28,072.98 .00 .00 28,072.98 .00 28,072.98 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 28,072.98 .00 28,072.98 .00 .00 28,072.98 .00 28,072.98 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 12074024 MGR.NO. 585 PAGE 001 CONT 6161 SEC 58 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616158001 HWY SH0071 7901 N IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 316,520.85 REPORT DATE 08/19/2008 09.33.05 CONTRACTOR CEN-TEX IRRIGATION SYSTEMS 12250 EST PERIOD JUL 01,2008 TO JUL 31,2008 EST NO 001 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6161-58-001 RMC - 616158001 14 SH0071 TRAVIS -LIMITS - VARIOUS LOCATIONS IN TRAVIS AND HAYS COUNTIES LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0730 FULL-WIDTH MOWING AC 7,865.000 702.000 39.990 28,072.98 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 28,072.98 0 TOTAL AMOUNT WORK DONE TO DATE - $ 28,072.98