1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1084011 MGR.NO. 585 PAGE 001 CONT 6161 SEC 50 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616150001 HWY SH0071 7901 N IH 35 AUSTIN CNTY BASTROP DIST 14 CONTRACT PRICE $ 337,470.00 REPORT DATE 12/16/2008 14.01.59 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 005 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 07, 2008 TIME COMPUTED FROM JUL 10, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 115 117 23 94 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 08 1 1 SATURDAY TOTAL DAYS ALLOWED = 115 2 1 SUNDAY DATE WORK COMPLETED 3 1 LETTER NOT WRITTEN DAYS CHARGED TO DATE = 25 4 1 LETTER NOT WRITTEN ASSESSED LIQ DAMAGES = 0 5 1 LETTER NOT WRITTEN LIQ DAMAGE RATE $ 500 6 1 LETTER NOT WRITTEN 7 1 LETTER NOT WRITTEN LIQUIDATED DAMAGES 8 1 SATURDAY 0 DAYS AT $ 500 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 LETTER NOT WRITTEN 11 1 LETTER NOT WRITTEN CERTIFIED AS CORRECT AND 12 1 LETTER NOT WRITTEN ONE COPY HAS BEEN GIVEN 13 1 LETTER NOT WRITTEN TO THE CONTRACTOR 14 1 LETTER NOT WRITTEN 15 1 SATURDAY 16 1 SUNDAY ---------------------------- 17 1 TIME NOT STARTED AREA/PROJECT ENGINEER 18 1 TIME NOT STARTED 19 1 TIME NOT STARTED 20 1 TIME NOT STARTED 21 1 TIME NOT STARTED 22 1 SATURDAY 23 1 SUNDAY 24 1 TIME NOT STARTED 25 1 26 1 27 1 HOLIDAY 28 1 HEAVY TRAFFIC 29 1 SATURDAY 30 1 SUNDAY 0 ----- ----- ----- 147 25 122 5 SATURDAY 5 SUNDAY 1 HOLIDAY 10 LETTER NOT WRITTEN 6 TIME NOT STARTED 1 HEAVY TRAFFIC 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1084011 MGR.NO. 585 PAGE 001 CONT 6161 SEC 50 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616150001 HWY SH0071 7901 N IH 35 AUSTIN CNTY BASTROP DIST 14 CONTRACT PRICE $ 337,470.00 REPORT DATE 12/16/2008 14.01.59 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 005 DIST. 14 COUNTY BASTROP CONTROL 6161-50-001 PROJECT RMC - 616150001 HIGHWAY SH0071 0LIMITS- VARIOUS LOCATIONS IN BASTROP COUNTY . 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 PREPARED BY LESLIE MILLER 09-30-2007 0 0055 MOWING SEGEMENT NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 STRIP MOWING AC 1,379.000 0.000 30.000 .00 0065 0730 FULL-WIDTH MOWING AC 10,440.000 3,157.000 27.500 86,817.50 0070 0730 SPOT MOWING AC 300.000 0.000 30.000 .00 0 SUBTOTAL BID ITEMS $ 86,817.50 0 TOTAL AMOUNT WORK DONE MOWING SEGEMENT $ 86,817.50 0 TOTAL AMOUNT WORK DONE CONTROL 6161-50-001 $ 86,817.50 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1084011 MGR.NO. 585 PAGE 001 CONT 6161 SEC 50 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616150001 HWY SH0071 7901 N IH 35 AUSTIN CNTY BASTROP DIST 14 CONTRACT PRICE $ 337,470.00 REPORT DATE 12/16/2008 14.01.59 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 005 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN BASTROP COUNTY 0 . DATE WORK BEGAN JUL 7 , 2008 WORKING DAYS USED 25 PERCENT COMPLETE 25.72 PERCENT TIME USED 21.70 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6161-50-001 RMC - 616150001 14 SH0071 BASTROP - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 10,440.000 3,157.000 27.500 86,817.50 0 SUBTOTAL BID ITEMS $ 86,817.50 0 CONTRACT TOTAL ALL ITEMS $ 86,817.50 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1084011 MGR.NO. 585 PAGE 001 CONT 6161 SEC 50 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616150001 HWY SH0071 7901 N IH 35 AUSTIN CNTY BASTROP DIST 14 CONTRACT PRICE $ 337,470.00 REPORT DATE 12/16/2008 14.01.59 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 005 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 11 RMC - 616150001 6161-50-001 86,817.50 .00 86,817.50 .00 .00 86,817.50 67,155.00 19,662.50 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 86,817.50 .00 86,817.50 .00 .00 86,817.50 67,155.00 19,662.50 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1084011 MGR.NO. 585 PAGE 001 CONT 6161 SEC 50 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616150001 HWY SH0071 7901 N IH 35 AUSTIN CNTY BASTROP DIST 14 CONTRACT PRICE $ 337,470.00 REPORT DATE 12/16/2008 14.01.59 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 005 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6161-50-001 RMC - 616150001 14 SH0071 BASTROP -LIMITS - VARIOUS LOCATIONS IN BASTROP COUNTY . LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0730 FULL-WIDTH MOWING AC 10,440.000 715.000 27.500 19,662.50 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 19,662.50 0 TOTAL AMOUNT WORK DONE TO DATE - $ 86,817.50