1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11074005 MGR.NO. 585 PAGE 001 CONT 6161 SEC 49 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616149001 HWY US0079 7901 N. IH 35 AUSTIN CNTY WILLIAMSON DIST 14 CONTRACT PRICE $ 349,928.34 REPORT DATE 07/21/2009 10.31.55 CONTRACTOR METRO-TEX UTILITIES, INC. 10642 EST PERIOD JUL 01,2009 TO JUL 31,2009 EST NO 013 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 07, 2008 TIME COMPUTED FROM JUL 15, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 120 359 7 352 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 09 1 1 TIME NOT STARTED TOTAL DAYS ALLOWED = 120 2 1 TIME NOT STARTED DATE WORK COMPLETED 3 1 TIME NOT STARTED DAYS CHARGED TO DATE = 8 4 1 SATURDAY ASSESSED LIQ DAMAGES = 0 5 1 SUNDAY LIQ DAMAGE RATE $ 500 6 1 7 1 TIME NOT STARTED LIQUIDATED DAMAGES 8 1 TIME NOT STARTED 0 DAYS AT $ 500 PER DAY 9 1 TIME NOT STARTED TOTAL = $ .00 10 1 TIME NOT STARTED 11 1 SATURDAY CERTIFIED AS CORRECT AND 12 1 SUNDAY ONE COPY HAS BEEN GIVEN 13 1 TIME NOT STARTED TO THE CONTRACTOR 14 1 TIME NOT STARTED 15 1 TIME NOT STARTED 16 1 TIME NOT STARTED ---------------------------- 17 1 TIME NOT STARTED AREA/PROJECT ENGINEER 18 1 SATURDAY 19 1 SUNDAY 20 1 TIME NOT STARTED 21 1 TIME NOT STARTED 22 1 TIME NOT STARTED 23 1 TIME NOT STARTED 24 1 TIME NOT STARTED 25 1 SATURDAY 26 1 SUNDAY 27 1 TIME NOT STARTED 28 1 TIME NOT STARTED 29 1 TIME NOT STARTED 30 1 TIME NOT STARTED 31 1 TIME NOT STARTED ----- ----- ----- 390 8 382 4 SATURDAY 4 SUNDAY 0 HOLIDAY 22 TIME NOT STARTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11074005 MGR.NO. 585 PAGE 001 CONT 6161 SEC 49 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616149001 HWY US0079 7901 N. IH 35 AUSTIN CNTY WILLIAMSON DIST 14 CONTRACT PRICE $ 349,928.34 REPORT DATE 07/21/2009 10.31.56 CONTRACTOR METRO-TEX UTILITIES, INC. 10642 EST PERIOD JUL 01,2009 TO JUL 31,2009 EST NO 013 DIST. 14 COUNTY WILLIAMSON CONTROL 6161-49-001 PROJECT RMC - 616149001 HIGHWAY US0079 0LIMITS- VARIOUS LOCATIONS IN WILLIAMSON, TRAVIS AND BASTROP COUNTIES 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 PREPARED BY LESLIE MILLER 09-17-2007 0 0055 MOWING SEGEMENT NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 STRIP MOWING AC 2,320.000 0.000 29.490 .00 0065 0730 FULL-WIDTH MOWING AC 9,496.000 7,122.000 29.490 210,027.78 0070 0730 SPOT MOWING AC 50.000 66.000 29.490 1,946.34 0 SUBTOTAL BID ITEMS $ 211,974.12 0 TOTAL AMOUNT WORK DONE MOWING SEGEMENT $ 211,974.12 0 TOTAL AMOUNT WORK DONE CONTROL 6161-49-001 $ 211,974.12 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11074005 MGR.NO. 585 PAGE 001 CONT 6161 SEC 49 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616149001 HWY US0079 7901 N. IH 35 AUSTIN CNTY WILLIAMSON DIST 14 CONTRACT PRICE $ 349,928.34 REPORT DATE 07/21/2009 10.31.56 CONTRACTOR METRO-TEX UTILITIES, INC. 10642 EST PERIOD JUL 01,2009 TO JUL 31,2009 EST NO 013 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN WILLIAMSON, TRAVIS 0 AND BASTROP COUNTIES DATE WORK BEGAN JUL 7 , 2008 WORKING DAYS USED 8 PERCENT COMPLETE 60.57 PERCENT TIME USED 6.60 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6161-49-001 RMC - 616149001 14 US0079 WILLIAMSON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 9,496.000 7,122.000 29.490 210,027.78 0730 SPOT MOWING AC 50.000 66.000 29.490 1,946.34 0 SUBTOTAL BID ITEMS $ 211,974.12 0 CONTRACT TOTAL ALL ITEMS $ 211,974.12 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11074005 MGR.NO. 585 PAGE 001 CONT 6161 SEC 49 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616149001 HWY US0079 7901 N. IH 35 AUSTIN CNTY WILLIAMSON DIST 14 CONTRACT PRICE $ 349,928.34 REPORT DATE 07/21/2009 10.31.56 CONTRACTOR METRO-TEX UTILITIES, INC. 10642 EST PERIOD JUL 01,2009 TO JUL 31,2009 EST NO 013 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 246 RMC - 616149001 6161-49-001 211,974.12 .00 211,974.12 .00 .00 211,974.12 157,535.58 54,438.54 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 211,974.12 .00 211,974.12 .00 .00 211,974.12 157,535.58 54,438.54 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11074005 MGR.NO. 585 PAGE 001 CONT 6161 SEC 49 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616149001 HWY US0079 7901 N. IH 35 AUSTIN CNTY WILLIAMSON DIST 14 CONTRACT PRICE $ 349,928.34 REPORT DATE 07/21/2009 10.31.56 CONTRACTOR METRO-TEX UTILITIES, INC. 10642 EST PERIOD JUL 01,2009 TO JUL 31,2009 EST NO 013 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6161-49-001 RMC - 616149001 14 US0079 WILLIAMSON -LIMITS - VARIOUS LOCATIONS IN WILLIAMSON, TRAVIS AND BASTROP COUNTIES LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0730 FULL-WIDTH MOWING AC 9,496.000 1,825.000 29.490 53,819.25 70 0730 SPOT MOWING AC 50.000 21.000 29.490 619.29 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 54,438.54 0 TOTAL AMOUNT WORK DONE TO DATE - $ 211,974.12