1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11074005 MGR.NO. 585 PAGE 001 CONT 6161 SEC 49 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616149001 HWY US0079 7901 N. IH 35 AUSTIN CNTY WILLIAMSON DIST 14 CONTRACT PRICE $ 349,928.34 REPORT DATE 12/10/2008 16.21.41 CONTRACTOR METRO-TEX UTILITIES, INC. 10642 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 005 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 07, 2008 TIME COMPUTED FROM JUL 15, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 120 117 7 110 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 08 1 1 TIME NOT STARTED TOTAL DAYS ALLOWED = 120 2 1 SATURDAY DATE WORK COMPLETED 3 1 SUNDAY DAYS CHARGED TO DATE = 7 4 1 TIME NOT STARTED ASSESSED LIQ DAMAGES = 0 5 1 TIME NOT STARTED LIQ DAMAGE RATE $ 500 6 1 TIME NOT STARTED 7 1 TIME NOT STARTED LIQUIDATED DAMAGES 8 1 SATURDAY 0 DAYS AT $ 500 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 TIME NOT STARTED 11 1 TIME NOT STARTED CERTIFIED AS CORRECT AND 12 1 TIME NOT STARTED ONE COPY HAS BEEN GIVEN 13 1 TIME NOT STARTED TO THE CONTRACTOR 14 1 TIME NOT STARTED 15 1 SATURDAY 16 1 SUNDAY ---------------------------- 17 1 TIME NOT STARTED AREA/PROJECT ENGINEER 18 1 TIME NOT STARTED 19 1 TIME NOT STARTED 20 1 TIME NOT STARTED 21 1 TIME NOT STARTED 22 1 SATURDAY 23 1 SUNDAY 24 1 TIME NOT STARTED 25 1 TIME NOT STARTED 26 1 TIME NOT STARTED 27 1 HOLIDAY 28 1 TIME NOT STARTED 29 1 SATURDAY 30 1 SUNDAY 0 ----- ----- ----- 147 7 140 5 SATURDAY 5 SUNDAY 1 HOLIDAY 19 TIME NOT STARTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11074005 MGR.NO. 585 PAGE 001 CONT 6161 SEC 49 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616149001 HWY US0079 7901 N. IH 35 AUSTIN CNTY WILLIAMSON DIST 14 CONTRACT PRICE $ 349,928.34 REPORT DATE 12/10/2008 16.21.42 CONTRACTOR METRO-TEX UTILITIES, INC. 10642 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 005 DIST. 14 COUNTY WILLIAMSON CONTROL 6161-49-001 PROJECT RMC - 616149001 HIGHWAY US0079 0LIMITS- VARIOUS LOCATIONS IN WILLIAMSON, TRAVIS AND BASTROP COUNTIES 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 PREPARED BY LESLIE MILLER 09-17-2007 0 0055 MOWING SEGEMENT NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 STRIP MOWING AC 2,320.000 0.000 29.490 .00 0065 0730 FULL-WIDTH MOWING AC 9,496.000 4,748.000 29.490 140,018.52 0070 0730 SPOT MOWING AC 50.000 45.000 29.490 1,327.05 0 SUBTOTAL BID ITEMS $ 141,345.57 0 TOTAL AMOUNT WORK DONE MOWING SEGEMENT $ 141,345.57 0 TOTAL AMOUNT WORK DONE CONTROL 6161-49-001 $ 141,345.57 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11074005 MGR.NO. 585 PAGE 001 CONT 6161 SEC 49 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616149001 HWY US0079 7901 N. IH 35 AUSTIN CNTY WILLIAMSON DIST 14 CONTRACT PRICE $ 349,928.34 REPORT DATE 12/10/2008 16.21.42 CONTRACTOR METRO-TEX UTILITIES, INC. 10642 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 005 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN WILLIAMSON, TRAVIS 0 AND BASTROP COUNTIES DATE WORK BEGAN JUL 7 , 2008 WORKING DAYS USED 7 PERCENT COMPLETE 40.39 PERCENT TIME USED 5.80 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6161-49-001 RMC - 616149001 14 US0079 WILLIAMSON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 9,496.000 4,748.000 29.490 140,018.52 0730 SPOT MOWING AC 50.000 45.000 29.490 1,327.05 0 SUBTOTAL BID ITEMS $ 141,345.57 0 CONTRACT TOTAL ALL ITEMS $ 141,345.57 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11074005 MGR.NO. 585 PAGE 001 CONT 6161 SEC 49 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616149001 HWY US0079 7901 N. IH 35 AUSTIN CNTY WILLIAMSON DIST 14 CONTRACT PRICE $ 349,928.34 REPORT DATE 12/10/2008 16.21.42 CONTRACTOR METRO-TEX UTILITIES, INC. 10642 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 005 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 246 RMC - 616149001 6161-49-001 141,345.57 .00 141,345.57 .00 .00 141,345.57 70,717.02 70,628.55 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 141,345.57 .00 141,345.57 .00 .00 141,345.57 70,717.02 70,628.55 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11074005 MGR.NO. 585 PAGE 001 CONT 6161 SEC 49 JOB 001 RES ENGR MILLER, LESLIE PROJ RMC - 616149001 HWY US0079 7901 N. IH 35 AUSTIN CNTY WILLIAMSON DIST 14 CONTRACT PRICE $ 349,928.34 REPORT DATE 12/10/2008 16.21.42 CONTRACTOR METRO-TEX UTILITIES, INC. 10642 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 005 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6161-49-001 RMC - 616149001 14 US0079 WILLIAMSON -LIMITS - VARIOUS LOCATIONS IN WILLIAMSON, TRAVIS AND BASTROP COUNTIES LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0730 FULL-WIDTH MOWING AC 9,496.000 2,374.000 29.490 70,009.26 70 0730 SPOT MOWING AC 50.000 21.000 29.490 619.29 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 70,628.55 0 TOTAL AMOUNT WORK DONE TO DATE - $ 141,345.57